  ID Date Authordown Category Type Module Target/Number Subject
  676   Tuesday, June 03, 2014, 09:12 David WangConditioning StationStandard OperationTM1UC9#TM1 HS line helium pressure test and TM1 electrical check at CS

TM1 HS line helium pressure test and TM1 electrical check at CS under vacuum are finished. Everything is good. See attachment

Attachment 1: 001.JPG
001.JPG
Attachment 2: 002.JPG
002.JPG
Attachment 3: 003.JPG
003.JPG
Attachment 4: 004.JPG
004.JPG
Attachment 5: 005.JPG
005.JPG
Attachment 6: 006.JPG
006.JPG
Attachment 7: TM1_UC9#_E-check_at_CS.pdf
TM1_UC9#_E-check_at_CS.pdf
  677   Monday, June 09, 2014, 10:33 David WangConditioning StationStandard OperationTM1UC9#Stop TM1 and CS trubo pumps and ruff pump.

The CS and TM1 is still under vacuum. They will be vented with argon tomorrow mornig

  678   Tuesday, June 10, 2014, 07:57 David WangConditioning StationStandard OperationTM1UC#9 TM1 are vented with argon and disconnected at CS.

TM1 will be moved to ITW this morning.

  680   Tuesday, June 10, 2014, 14:02 David WangITWStandard OperationTM1UC9#TM1 and ITW turbo pumps have been started.

TM1 has been connected to ITW. It is pumping down in ITW with 6 turbo-pumps on.

  683   Tuesday, June 17, 2014, 10:46 David WangITWStandard OperationTM1UC#95 Shielding blocks have been transferred from ITE to ITW.

5 shielding blocks have been transferred from ITE to ITW. ITW is configured to take proton beam. Argon venting system for ITW is ready also.

  692   Thursday, June 26, 2014, 10:57 David WangSouth Hot-CellStandard OperationTM3 Leak check on TM3 HS water line with new target. installed.

Chad and I leak checked the TM3 HS water line with new target installed.  No leak has been found during the check. Leak detector base LR 0.0xE-9 atm.cc/sec, base pressure 0.0xE-4 torr. The line will be helium pressurized at CS later.

  695   Friday, June 27, 2014, 10:16 David WangConditioning StationStandard OperationTM3  TM3 HS water lines helium pressure test. at CS

TM3 HS water line helium pressure test is done at CS. 70 psi helium , 3 minutes.Base LR 0.0xE-9 atm.cc/sec, base pressure 0.0xE-4 torr.  No response. The line is leak free.

  698   Wednesday, July 02, 2014, 14:29 David WangITEStandard Operation  Reconnected TM3 in ITE.

I reconnected TM3 in ITE. All turbo pumps have been started. The water supply to TM3 only in ITE. The HV keys are back to electrical room.

  700   Tuesday, July 08, 2014, 09:57 David WangITEStandard OperationTM3 5 Shielding blocks have been transferred from ITW to ITE.

5 Shielding blocks have been transferred from ITW to ITE. The ITE is configured to take proton beam.

  702   Wednesday, July 16, 2014, 11:28 David WangITWStandard OperationTM1 TM1 had been dsiconnected in ITW.

The TM1 and ITW  were vented with argon gas last night. TM1 had been disconnected in ITW this morning.

  708   Thursday, July 17, 2014, 10:13 David WangConditioning StationStandard OperationTM1 Leak check on TM1 HS water line with new target installed

Chad and I leak checked TM1 HS waterline with new target installed at SHC. The LD base LR:0.0xE-9atm.cc/sec, base pressure: 0.0xE-4 torr. Chad sprayed helium on both VCR fittings and flushed helium around the target. No response has been found on leak detector. The target HS line is leak tight so far. I will do helium pressure test on this line at CS on next Monday.

  709   Thursday, July 17, 2014, 11:49 David WangConditioning StationStandard OperationTM1 TM1 and CS turbo pumps have been started

I connected TM1 at CS. All turbo pumps have been started. The pumping down is  good so far.

  710   Monday, July 21, 2014, 13:11 David WangConditioning StationStandard OperationTM1 helium pressure test on TM1 HS water line at CS.

The TM1 HS line is  pressure tested this morning with 70 psi helium  at CS. No response has been found on leak detector.

  711   Tuesday, July 22, 2014, 07:32 David WangConditioning StationStandard OperationTM1 Stop TM1 and CS turbo pumps and ruff pump.

Stop TM1 and CS turbo pumps and ruff pump. TM1 is disconnect at CS. It will be vented tomorrow morning and moved to ITW.

  712   Wednesday, July 23, 2014, 13:36 David WangITWStandard OperationTM1 TM1 in ITW.

  TM1 has been connected in ITW . The new roughing pump replaced on last Friday works good. I started all turbo pumps in ITW. The ITW TP1 controller was broken during the starting time. Dimo and I changed a new controller for ITW TP1 in electrical room. The pumping down is good so far. ITW water supplies to TM1 only.      

  716   Monday, July 28, 2014, 14:37 David WangConditioning StationDevelopmentTM2 helium pressure test on TM2 tube heater +(D)and -(C)water lines.
  • TM2 installed in Conditioning Station
  • Varian Leak detector connected directly to Target Module 2 Service cap.
  • Vacuum draw in Target Station with both module turbo pumps
  • Leak detector baseline normal (10^-4 Torr, 10^-9 Std cc/s He)
  • Since no Source tray is installed, and tube heater supply conductor is blanked off in target enclosure, it was necessary to test both supply and return points.
  • For each line tested, 80 psi He was connected, and waited ~2 min to for a response on the leak detector.
  • Lines tested:
    • conductor D (tube heater), Supply -> no He response
    • conductor D (tube heater), Return -> no He response
    • conductor C (tube heater), Supply -> no He response
    • conductor C (tube heater), Return -> no He response
  • Based on this leak testing, both supply and return lines of conductors C & D are leak tight under 95 psi He (80 psig He supply to vacuum)

 

Attachment 1: 011.JPG
011.JPG
Attachment 2: 012.JPG
012.JPG
Attachment 3: 013.JPG
013.JPG
Attachment 4: 014.JPG
014.JPG
Attachment 5: 015.JPG
015.JPG
Attachment 6: 017.JPG
017.JPG
Attachment 7: 018.JPG
018.JPG
  717   Monday, July 28, 2014, 14:45 David WangConditioning StationDevelopmentTM2 turned off TM2 and CS turbo pumps.

I turned off TM2 and CS turbo-pumps. TM2 will be moved from CS to silo tomorrow morning.

  722   Tuesday, August 05, 2014, 11:53 David WangITERepair  Reconnected ITE entrance module

ITE entrance module is reconnected in ITE.

  726   Thursday, August 07, 2014, 13:58 David WangSouth Hot-CellStandard OperationTM4UCx #10Leak check on TM4 HS water line with new UCX target.

Isaac and I leak checked TM4 HS line with new UCX target. The leak detector base LR 0.0xE-9 atm.cc/sec, base pressure0.0xE-4torr. Isaac sprayed helium  on both VCR connections(5 seconds each) and flushed helium around the target for 6 seconds. No response on leak detector.

  727   Thursday, August 07, 2014, 17:07 David WangConditioning StationStandard OperationTM4UCx #10TM4 is connected in CS.

TM4 is connected at CS. All turbo pumps are started. The pumping down is good so far.