Entry  Wednesday, August 01, 2018, 15:12, Anders Mjos, South Hot-Cell, Standard Operation, TM2, UC#23, Target mounted - water leak on HS line 20180801_180130904_iOS.jpg

The heat shield water lines were not purged ahead of target exchange in the hot cell. This resulted in water leaking onto the new target assembly (heat shield) when the cooling lines were opened at top and bottom (for connecting leak detector). Excess water was wiped up with paper towels.

Entry  Tuesday, August 14, 2018, 10:27, Travis Cave, ITW, Standard Operation, TM2, UC#23, Module move 

 Both the West Entrance and TM#2 with UC#23 have been moved back into their places in the west target station. The Entrance module move wasn't completely smooth as it did suffer a little bumpiness when the shield plug part was installed, I was lifted back out again and no visible damage was observed on the delicate items.

Entry  Monday, August 20, 2018, 09:55, Travis Cave, South Hot-Cell, Standard Operation, TM2, Ta#56 and UC#23, Electrical Check Electrical_Check_TM4_Ta56_SHC.pdfElectrical_Check_TM2_UC23_CS.pdfElectrical_Check_TM2_UC23_SHC.pdf

 Electrical Checks of the last two targets Ta#56 and UC#23

Entry  Tuesday, September 18, 2018, 12:59, Travis Cave, South Hot-Cell, Standard Operation, TM2, UC#23, Module move 

 TM#2 with UC#23 has been moved from ITW to the south hot cell. The shield plug was also installed remotely as well.

Entry  Thursday, September 20, 2018, 08:36, Travis Cave, South Hot-Cell, Standard Operation, TM2, no target, Electrical Check Electrical_Chk_TM2_no_tgt_Sept-20-2018.pdf

 Results of the electrical check on TM#2 with no target after Chad cleaned out the bolt hole on the module where the target mounts.

Entry  Thursday, September 20, 2018, 14:35, Travis Cave, South Hot-Cell, Standard Operation, TM2, nSiC#1, Electrical Check Electrical_Chk_TM2_SHC_nSiC#1_Sept-20-2018.pdf

 TM#2 with the nSiC#1 target had its check done on it at the south hot cell see attached for results.

Entry  Thursday, September 20, 2018, 14:36, Travis Cave, ITW, Standard Operation, TM2, nSiC#1, Module move 

 TM#2 with nSiC#1 has been moved from the south hot cell to the west target station.

Entry  Friday, September 21, 2018, 10:06, David Wang, ITW, Standard Operation, TM2, UCx23, TM2 was disconnected in ITW. TM2_UCx_23#_disconnection_in_ITW..pdf

TM2 was disconnected in ITW this Tuesday. See attachment for checklist.

Entry  Friday, September 21, 2018, 10:07, David Wang, ITW, Standard Operation, TM2, SiC nano, TM2 with SiC nano target was has been connected in ITW. TM2_with_SiC_nano_connection_in_ITW..pdf

Tm2 with SiC nano has been connected in ITW. See attachment for checklist

Entry  Monday, September 24, 2018, 10:21, Anders Mjos, South Hot-Cell, Standard Operation, TM2, UC#23, Post Irradiation Examination (PIE) 20180924_161322929_iOS.jpg

UC#23 experienced short between target and heat shield as it was heated during operation. The inspection of the target after irradiation revealed that the left target leg was close to the heat shield opening and likely the cause of the short. Marks could be seen on the leg indicating contact. See attached photo. More photos are available on DocuShare

Entry  Tuesday, September 25, 2018, 08:01, chad fisher, South Hot-Cell, Standard Operation, TM2, nSiC#1, nSiC#1 install 20180919_132304.jpg20180919_143535.jpg

On September 18th installation of nSiC#1 was attempted on TM2. As usual, new fasteners were tested previous to insertion into hot cell and employed during installation. the last fastener to be installed was for the circuit D block. The fastener/air ratchet stalled immediately indicating a problem. The fastener was removed and a an attempt was made trying a new spare fastener. That fastener also jammed right away but could not be removed or installed any further.

 

A breaker bar was employed to achieve more torque and the fastener was able to be loosened, although it would not come completely out, dangling and wobbling like it was free. A claw type bar was used to add slight pressure to the fastener while it was loosened allowing the fastener to undo the rest of the way.

Target was removed and discovered that that insulator supporting circuit c and d blocks was quite broken and that a few chunks had fallen off. It was also notice that boefore the breaker bar had been employed that a piece of ceramic was on the table suggesting that the ceramic had been at least partially broken at the time of removal of the previous target. Also, the threads of the insert for circuit d showed damage an swarf.

Swarf was vacuum claned out of the circuit d thread insert and a machine tap ran through the insert twice.

nSiC#1 was reinstalled with new waterline gaskets and new c and d circuit fasteners with a little bit of the first 2-3 threads lightly coated with vacuum grease.

High current fasteners torqued to 130 in lbs.

Entry  Tuesday, October 23, 2018, 10:45, David Wang, ITW, Standard Operation, TM2, SiC nano, TM2 was disconnected in ITW. TM2_SiC_nano_disconnection_in_ITW.pdf

TM2(SiC nano) has been disconnected in ITW. See attachment

Entry  Tuesday, October 30, 2018, 10:50, Travis Cave, ITW, Standard Operation, TM2, nSiC#1, Modules moved 

 Modules were moved, ITW EX2 was moved from the conditioning station to the west target station and TM#2 ,with nSiC#1,  was moved from the west target station to the south hot cell.

Entry  Wednesday, October 31, 2018, 14:20, Travis Cave, Conditioning Station, Standard Operation, TM2, UC#25, Module move 
TM#2 with UC#25 has been moved from the south hot cell to the conditioning station.
Entry  Wednesday, October 31, 2018, 14:23, Travis Cave, South Hot-Cell, Standard Operation, TM2, nSiC#1 and UC#25, Electrical Check Electrical_Chk__TM#2_nSiC#1_SHC_Post_Beam_Oct-31-2018.pdfElectrical_Chk_TM#2_UC#25_SHC_Oct-31-2018.pdf

 TM#2 with targets nSiC#1 (old target) and UC#25 (new target) electrical check results. See attached for details.

Entry  Thursday, November 01, 2018, 11:42, David Wang, Conditioning Station, Standard Operation, TM2, UCx 25., TM2 HS line helium pressure test at TCS and helium spray at SHC.. 

Chad and I did  leak check on TM2 HS line at SHC yesterday. Base LR 0.0XE-9 atm.cc/sec.   No response on LD. during helium spray.   Today , I did helium pressure test at TCS. base LR 0.0xe-9atm.cc/sec. applied 70psi helium for 3 minute. leak rate slowly climbed to2.2 Xe-7 atm.cc/sec ate stopped there.  The result is close to before.

Entry  Monday, November 05, 2018, 14:27, Anders Mjos, Conditioning Station, Standard Operation, TM2, UC#25, Target module disconnected 

Frank and Anders disconnected the water and electrical connections this afternoon after the target was conditioned over the weekend. The heater ramping program ran with the wrong gauge selected, causing the vacuum to go higher than planned. The module will be moved to ITW tomorrow.

Entry  Tuesday, November 06, 2018, 10:59, Travis Cave, ITW, Standard Operation, TM2, UC#25, Module move 

 TM#2 with UC#25 has been moved from the conditioning station to the west target station.

Entry  Wednesday, November 07, 2018, 09:50, Anders Mjos, ITW, Standard Operation, TM2, UC#25, TM2 connected in ITW 

TM2 was connected yesterday by Frank and Anders. The West side panel with IG1S on Exit Module 2 was replaced with a new SST panel with 1 CF flange only (dwg). Link to check list on DocuShare.

Entry  Wednesday, November 14, 2018, 16:10, Anders Mjos, ITW, Repair, TM2, UC#25, ITW:FC5 safety signal troubleshooting 2018-11-13_FC5.pdf

Measured resistance on safety limit switches for FC5 on Exit Module 2. Determined that the in connected signal did not work (shows not connected irregardless of FC position). Confirmed proper operation of the OUT limit. See attachment for details. The Harp 5 x and y signal connectors were checked and reconnected.