  64   Thursday, December 15, 2011, 13:08 Travis CaveSpent Target VaultStandard Operation  Spent Target AssaySpent target assay completed. A total of
16 target were looked at, 13 were low enough
to be assayed and those 13 are at shippable
 Vault_Storage_December_14_2011.pdf 
  65   Wednesday, January 04, 2012, 13:49 Travis CaveSpent Target VaultStandard Operation  Moving the spent targets to mini storage.Well the first of this year's lucky winners
to win a fabulous one way trip to Chalk River
are as follows. UC#1, UC#2, Ta#25, Ta#26,
  
  66   Thursday, January 05, 2012, 11:40 Travis CaveSpent Target VaultStandard Operation  Target swapping Looks like the UC target s #1 and #2 were
found invalidprize winners for their all
inclusive trip to Chalk River and have thus
 Vault_Storage_January_5_2012.pdfMini_Vault_Storage_January_5_2012.pdf 
  67   Monday, January 09, 2012, 14:44 David WangITEMaintenanceTM4 ITE and TM4 2012 winter shut down leak check is completed.I did a vacuum leak check on all ITE primary
vacuum vessel and secondary vessel.I also
did a helium pressure test(80psi ) on all
  
  68   Tuesday, January 10, 2012, 11:51 Grant MinorConditioning StationRepair  IMC at Cond. Station is VENTED - DO NOT PUT MODULE INHi Remote Handling,
The guage on the IMC circuit in the
Target Hall is reading atmosphere, and the
 IMC_Installation_and_Leak_Check_April_28_2011_011.jpg 
  69   Thursday, January 12, 2012, 08:43 Travis CaveSpent Target VaultStandard Operation  Spent targets to F-308sAll targets in the mini storage have been
moved to F-308s and those flasks have been
moved over to rad waste. The transfer of
  
  70   Thursday, January 12, 2012, 14:32 David WangITERepairTM4 TP2 on TM4 has been replaced TP2 on TM4 has been replaced with a new
turbo pump , I didnt  reset the controller
in electrical room.So this new pump start
  
  71   Monday, January 16, 2012, 09:30 David WangITEMaintenance  Changed all old inducion coils for flow sensors in ITEI had changed all old induction coils for
flow sensors in ITE .I checked all ITE water
signals on control boards in electrical room.They
  
  72   Wednesday, February 01, 2012, 09:54 David WangITWMaintenanceTM1 ITW and TM1 winter shut down vacuum leak checkITW and TM1 winter shut down vacuum leak
check had been finished yesterday.All ITW
primary vacuum vessel, secondary vacuum vessel,
  
  79   Monday, April 02, 2012, 08:17 David WangConditioning StationDevelopment  conditioning station IMC pump down.I pumped down conditioning station IMC
today. The inside bellow pressure is -20
psi on the gauge.Visually checked the bellow
  
  80   Tuesday, April 03, 2012, 12:11 David WangConditioning StationDevelopment  leak check on conditioning station vacuum systemI did a leak check on conditioning station
vacuum system today.The vacuum system had
been roughed over night . This morning before
  
  81   Thursday, April 05, 2012, 10:30 David WangITEStandard OperationTM4 I moved 5 shielding blocks back to ITE this morning. MAA is secured .The ITE and MAA are
ready for taking proton beam now.
  
  83   Thursday, April 12, 2012, 14:40 David WangConditioning StationDevelopmentTM1 conditioning staion and TM1 is under TP1 and TP2 pumping now.TM1 moved to conditioning station to today.
After moving, I connected the vacuum system
which include all gauges ,vacuum lines ,
  
  84   Friday, April 13, 2012, 12:31 David WangConditioning StationDevelopmentTM1 TM1 and conditioning station leak check.
 

 Normal
  0

 
   
  
  95   Thursday, April 26, 2012, 09:23 David WangITERepairTM4 changed flow wheel on ITE TM4 contaiment box water circuitThe the magnetic field on ITE TM4 flow
wheel  was gone yesterday.So there is
no water signal on this circuit. The water
  
  96   Thursday, April 26, 2012, 13:01 David WangITERepairTM4 Replaced TM4 EE water flow wheel in ITE.Due to weak magnetic field on TM4 EE water
flow wheel, we have two times  intermittent
water signal on this circuit this morning.
  
  97   Wednesday, May 02, 2012, 11:27 David WangITWStandard OperationTM1  ITW is ready for taking proton beam. I moved 5 shielding blocks from ITE
to ITW .  I checked  all ITW water
signals strength and frequency in electrical
  
  98   Tuesday, May 08, 2012, 10:28 David WangITEStandard OperationTM4 Disconnected TM4 in ITE.I disconnected TM4 in ITE. The heat shield
water circuit is purged. I  closed the
water supply to ITE.Now, the water system
  
  113   Friday, May 25, 2012, 10:48 Travis CaveSpent Target VaultStandard Operation  Moving the spent targets to mini storage.Five targets were moved to the mini storage
today in preparation for transfer of the
targets to the F308s later next week. The
 Mini_Vault_Storage_May_25_2012.pdfVault_Storage_May_25_2012.pdf 
  114   Monday, May 28, 2012, 13:05 David WangITEStandard Operation  I moved 5 shielding blocks from ITW to ITE .5 shielding blocks have  been transferred
from  ITW to ITE. ITE ventilation is
opened, and ITW closed. All ITE water 
  