Saturday, December 03, 2016, 10:01, David Wang, ITW, Repair, TM2, , venting ITW and TM2 with argon.
|
A short between TM2 EE and bias is produced yesterday during tube heater ramp up. Alex asked for an argon venting on ITW to see if the problem could be solved by venting and pumping down yesterday. I set up argon venting system in electrical room and started the venting at 8:30 AM this morning. It will take 5 hours to vent the ITW to 760 torr(mechanical gauge reading). The venting system pressure is set as 2 torr. A pressure relieve valve is installed into ITW venting line to prevent station over venting. The argon bottle valve in electrical room will be closed by isac opps after 5 hours venting. |
Monday, December 05, 2016, 10:10, David Wang, ITW, Standard Operation, TM2, , Five shielding blocks have been transferred from ITE to ITW.
|
The ITW is configured to take proton beam. |
Thursday, January 12, 2017, 14:24, David Wang, ITW, Standard Operation, TM2, , ITW primary and secondary vacuum vessel winter shut down leak check.
|
TM2 is located in ITW for this leak check. Leak detector is installed between ITW BV2s as before. LD base leak rate 0.0XE-9atm.cc/sec, base pressure 0.0XE-4 Torr. First , I leak checked dump module top flange seal which a small leak was found in last year winter shut down. This time,all ITW turbo-pumps cooling fans are switched off during the check. Lots helium are sprayed around the dump module top flange this time. I did not see any response on LD. The check is repeated 3 times. The results are same. There is no leak has been found on ITW dump module top flange seal at this moment. The further confirming check will be repeated when TM2 is moved back to ITW with dummy Febiad target at the end of this month. The rest check result: 1 small leak(1.2 xE-8 atm.cc/sec) is found on one TM2 blue nylon bottom o-ring. This o-ring will be replaced when module is moved out of ITW. It will be an easy job. Another small leak( 1.1XE-8 atm.cc/sec) is found on exit module 1 service cap top plate to frame o-ring seal. Its location is on east-south side of the exit module 1.This side is close and parallel to exit module 2 west-south side. Vacu- seal sprayer is used to fix this problem. After two times spray, the leak is disappeared. This is not a permanent fix. The big top plate o-ring replacement is a complicate and dose taking job. It need to be well planned. The leak rate is small, and the leak source is close to ITW TP3 so there is no rush to replace the big o-ring on exit 1 service cap top plate at this moment. But, we need to close watching on this issue and have a job plan for this o-ring replacement since it could get worse in the future. There is no leak has been found on big T tank seal this year as well. All other primary and secondary vacuum seals in ITW are good. TM2 water lines helum pressurize will be fulfilled In ITW or at TCS later. I will update this e-log when further test are finished.
2017-01-25: The O-ring on 60KV bias blue nylon stand is replaced at TCS. I leak check it. It is perfectly good now. |
Monday, January 16, 2017, 09:32, David Wang, ITW, Standard Operation, TM2, , Helium pressure test on TM2 water llines at ITW
|
TM2 helium pressure test result at ITW. 70 psi helium 3 minutes on each circuit. LD base LR0.0XE-9atm.cc/sec BP 0.0XE-4torr. ITW IG1 1.22Xe-7 torr, ITW IG1S 1.31XE-7torr, ITW PNG4 2.66XE-6Torr(ITW TP4 off).
|
2017-01-13 (atm.cc/sec) |
2017 mini shut down |
HS |
0.0 x E-9 |
|
Window |
0.0 x E-9 |
|
EE |
2.7 x E-9 |
|
Ta+ |
2.2 x E-9 |
|
Ta- |
6.6 x E-9 |
|
Tube- |
1.3 x E-8 |
|
Tube+ |
2.8 x E-8 |
|
Coil 2 |
2.8 x E-9 |
|
coil 1 |
7.1 x E-9 |
|
MSP |
6.7 x E-8 |
|
GE |
leak , no test |
|
All number are getting better comparing to last time check. All ITW vacuum readings are very good. ITW PNG4 was in low E-7 torr range also. At present, it is in low E-6 range due to ITW TP4 switching off. The TM2 water line seals are stable and reliable for 2017 beam run. The same check will be repeated in 2017 mini shut down. |
Tuesday, January 24, 2017, 15:24, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 electrical check and leack check.
|
I did electrical check before and after Fefiad target installation on TM2. The RU (coil) Is till short to 60KV as before. Other result are good. After Febiad target is installed, Tm2 HS line is leak checked. On leak detector, base leak rate pumping down is much slow than before. The base pressure still could be pumped down to 0.0XE-4 torr. After a long time wait, Chad and I leak checked at 2.2XE-8 atm.cc/sec base leak rate. Chad sprayed lots helium around the fittings and target. No any response has been found on LD. At this leak rate, the target and HS line is leak tight. The Tm2 has been moved to THC so a heium pressure check will be fulfilled on HS line at TCS to confirm this leak check result.
TM2 HS line is pressurized with 70 psi helium at TCS. LD base leak rate: 0.0 X E-9 atm.cc/sec. Base pressure 0.0XE-4 torr. 5 minutes test time. The leak rate slowly climed to 3.3XE-9 atm.cc/sec and stabled there( 3minutes). base pressure no change. The leak is too small to be concern. We will run this target as this condition.
|
Tuesday, January 24, 2017, 15:29, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 has been moved to TCS .
|
I connected TCS vacuum system to TM2. The station is under roughing now. All turbo pumps will be started soon. |
Tuesday, January 24, 2017, 15:32, David Wang, ITW, Standard Operation, TM2, , TM2 was moved from ITW to SHC this morning.
|
The move is smooth. Yasmine and Travis did the move. |
Friday, January 27, 2017, 08:44, chad fisher, South Hot-Cell, Standard Operation, TM2, Ta#50, UCx #18 - Ta Feibiad Dummy installed. Target Change Waterline interference
|
On Tuesday, January 24th UCx#18 was removed from TM2 and Ta febiad dummy installed. I encountered the same issue mounting the new target as last time. Was able to determine that the issue is the routing of the waterlines to the right-hand (as viewed from the operator) high current tube heater. The lines interfer the the target mounting plate (bottom right hand corner). |
Friday, January 27, 2017, 10:52, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 has been moved from TCS to ITE
|
The move is successful. |
Wednesday, February 01, 2017, 12:23, David Wang, ITE, Standard Operation, TM2, , TM2 has been connected in ITE.
|
TM2 has been connected in ITE. The SST window water lines in ITE can not be connected properly to TM2. The water line connector on TM2 window is 90 degree CCW installed in direction comparing to TM4.This caused the problem. Solution: Two piece of flexible lines and extra male QC adapters have been used to fix this issue. HV cover and HV fence in ITE work with TM2. Other connections are good as well. |
Wednesday, March 08, 2017, 14:09, David Wang, ITE, Maintenance, TM2, , ITE IG1S increasing.   
|
By retrieving data further, It has been found no directly relationship between IG1S surging and dump plug water opening. Vacuum surging is 10minutes ahead dump water supply to circuit. SEE attachment 1. Also, The ITE IG1S start to behavior unusual in middle of Feburary. See attachment 2. Today, ITE IG1S is still slowly climbing up. I decide to leak check ITE vacuum vessel. Before leak check, for more information and trouble shooting. I closed water supply to ITE to see if vacuum has response on it. I will return water supply to ITE tomorrow morning.
Water supply to ITE is returned this afternoon at 2: 10 PM. Everything works fine so far
I leak checked ITE secondary vessel vacuum. A leak have been found in March 09th noon which is located between entrance module and TM2 top tank flange o-ring seal( on tank flange). It could not be confirm on which side of the o-ring the leak is from.
During last night, ITE IG1S reading went back to normal low E-7 range and stays in this range now. So I leak checked same area again this morning. The leak disappeared now. The o-ring works sometime , but not all the time. The plan for this issue: Change ITE target module side o-ring when TM2 is move out., and watch on the ITE IG1s when TM4 is moved back to ITE and pumped down. |
Wednesday, March 22, 2017, 14:05, Travis Cave, South Hot-Cell, Standard Operation, TM2, test target, module moved
|
TM#2 has been moved from the east target station to the south hot cell. |
Thursday, March 23, 2017, 09:30, Travis Cave, South Hot-Cell, Standard Operation, TM2, test target, Electrical Check
|
Electrical check of the Ta test target on TM#2 |
Monday, March 27, 2017, 13:40, Travis Cave, South Hot-Cell, Standard Operation, TM2, no target, Electrical Check 
|
Did the start of the running year electrical checks of both TM#2 and TM#4 with no target attached to either module. TM#2 was in the south hot cell and TM#4 is in the conditioning station under vacuum. |
Tuesday, April 11, 2017, 11:30, Travis Cave, South Hot-Cell, Standard Operation, TM2, Ta#51, Electrical Check
|
Electrical check performed on TM#2 with Ta#51, see attached PDF. |
Tuesday, April 11, 2017, 14:02, Travis Cave, Conditioning Station, Standard Operation, TM2, Ta#51, module moved
|
TM#2 with Ta#51 has been moved from the south hot cell to the conditioning station. |
Wednesday, April 12, 2017, 07:26, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 and TCS vacuum system has been connected.
|
Roughing down overnight. Turbo pumps are started this morning. Everything looks good so far. |
Thursday, April 13, 2017, 11:33, David Wang, Conditioning Station, Standard Operation, TM2, , Helium pressure test on TM2 water llines at TCS.
|
LD BLR :0.0 X E-9 atm.cc/sec. BP:0.0XE-4 torr. helium 70 psi. 3 minutes on each circuit
HS |
1.8XE-7 ATM.CC/SEC |
TA+ |
1.4 XE-7 |
TA- |
4.3XE-8 |
TUBE+ |
1.0XE-7 |
TUBE- |
5.9XE-8 |
COIL 1 |
2.2XE-9 |
COIL 2 |
0.0XE-9 |
EE |
0.0XE-9 |
MSP |
8.8XE-8 |
ALL TOGETHER |
6.7XE-7 |
ALL TOGETHER WITHOUT HS |
4.7XE-7 |
There is a smallleak HS which we did not see before. The HS is checked in SHC with helium spray yesterday. We did not see the leak . We checked this HS line every time when new target was installed. So mostly, this small leak is from VCRs connected to new target. But, we can not confirm it. Still this line will be checked on next new target. We should have a better understanding when checking next time. Other line are almost same as we checked in last year November. I did not see essential change. |
Thursday, April 13, 2017, 11:44, Anders Mjos, Conditioning Station, Standard Operation, TM2, Ta#51, Conditioning Ta#51
|
Thursday, April 13, 2017, 11:43: Water package started. |
Monday, April 24, 2017, 09:52, David Wang, Conditioning Station, Standard Operation, TM2, , Switch off TCS water system and vacuums
|
The TCS bias was turn off before that. The TM2 and TCS are still under vacuum now. |
|