ID Date Author Category Type Moduledown Target/Number Subject Text Attachments
  1428   Friday, January 27, 2017, 08:44 chad fisherSouth Hot-CellStandard OperationTM2Ta#50UCx #18 - Ta Feibiad Dummy installed. Target Change Waterline interferenceOn Tuesday, January 24th UCx#18 was removed
from TM2 and Ta febiad dummy installed. I
encountered the same issue mounting the new
 TM2_Waterline_interference.jpg 
  1431   Friday, January 27, 2017, 10:52 David WangConditioning StationStandard OperationTM2 TM2 has been moved from TCS to ITEThe move is successful.   
  1432   Wednesday, February 01, 2017, 12:23 David WangITEStandard OperationTM2 TM2 has been connected in ITE.TM2 has been connected in ITE. The SST
window water lines in ITE can not be connected
properly to TM2. The water line connector
  
  1447   Wednesday, March 08, 2017, 14:09 David WangITEMaintenanceTM2 ITE IG1S increasing.By retrieving data further, It has been
found no directly relationship between IG1S
surging and dump plug water opening. Vacuum
 ITE_IGIS_surge.pngITE_IG1S_and_PNG4.pngITE_IG1S_back_to_normal_overnight.pngITE_IG1S_behavior_from_Feb_08th_to_Mar_10th.png 
  1457   Wednesday, March 22, 2017, 14:05 Travis CaveSouth Hot-CellStandard OperationTM2test targetmodule movedTM#2 has been moved from the east target
station to the south hot cell.
  
  1458   Thursday, March 23, 2017, 09:30 Travis CaveSouth Hot-CellStandard OperationTM2test targetElectrical CheckElectrical check of the Ta test target
on TM#2
 TM2_Ta_Dummytgt_Preandpost.PDF 
  1466   Monday, March 27, 2017, 13:40 Travis CaveSouth Hot-CellStandard OperationTM2no targetElectrical CheckDid the start of the running year electrical
checks of both TM#2 and TM#4 with no target
attached to either module. TM#2 was in the
 TM2__No_Tgt.PDFTM4__No_Tgt.PDF 
  1486   Tuesday, April 11, 2017, 11:30 Travis CaveSouth Hot-CellStandard OperationTM2Ta#51Electrical CheckElectrical check performed on TM#2 with
Ta#51, see attached PDF.
 TM2_Ta51_SHC_elec_chk.PDF 
  1487   Tuesday, April 11, 2017, 14:02 Travis CaveConditioning StationStandard OperationTM2Ta#51module movedTM#2 with Ta#51 has been moved from the
south hot cell to the conditioning station.
  
  1489   Wednesday, April 12, 2017, 07:26 David WangConditioning StationStandard OperationTM2 TM2 and TCS vacuum system has been connected.Roughing down overnight. Turbo pumps are
started this morning. Everything looks good
so far.
  
  1495   Thursday, April 13, 2017, 11:33 David WangConditioning StationStandard OperationTM2 Helium pressure test on TM2 water llines at TCS.LD  BLR :0.0 X E-9 atm.cc/sec. BP:0.0XE-4
torr. helium 70 psi. 3 minutes on each circuit
  
  1496   Thursday, April 13, 2017, 11:44 Anders MjosConditioning StationStandard OperationTM2Ta#51Conditioning Ta#51 Thursday, April 13, 2017, 11:43:
Water package started.
  
  1500   Monday, April 24, 2017, 09:52 David WangConditioning StationStandard OperationTM2 Switch off TCS water system and vacuumsThe TCS bias was turn off before that.
The TM2 and TCS are still under vacuum now.
  
  1501   Monday, April 24, 2017, 16:06 David WangSouth Hot-CellRepairTM2 Crane main hoist strane noise when lifting up TM2  When lifting up TM2 (20000lbs) this
afternoon, TH crane has a strange noise on
main hoist. The module was lift up less than
  
  1502   Monday, April 24, 2017, 16:11 David WangConditioning StationStandard OperationTM2 TCS TP1s is restarted.TCS IG1S  is switched on as well.
The reason to start the pump is to prepare
a possible extended TM2 conditioning at TCS
  
  1505   Wednesday, April 26, 2017, 10:24 David WangITWStandard OperationTM2 TM2 ITWTM2 was moved and connected in ITW yesterday
afternoon. After roughing down, ITW turbo
pumps are started. ITW TP4 can not be started
  
  1549   Wednesday, May 24, 2017, 08:11 David WangITWStandard OperationTM2 TH schedule 132 update weeklySee attachments.  Target_Hall_shedule_132_Apr_to_Sep.mppTarget_Hall_shedule_132_Apr_to_Sep.pdf 
  1550   Tuesday, June 06, 2017, 13:42 chad fisherSouth Hot-CellStandard OperationTM2SiC#36Ta#51 removed SiC#36 installedThis afternoon Ta#51 was removed from TM2
and SiC#36 installed.
All new fasteners used. High current
  
  1551   Wednesday, June 07, 2017, 13:33 David WangConditioning StationStandard OperationTM2 TM2 SiC#36 leakc check and electrical check.The results  are good. See attachment.  TM2_SiC_36#_leak_check_an_delectrical_check..pdf 
  1552   Wednesday, June 07, 2017, 13:34 David WangConditioning StationStandard OperationTM2 TM2 and TCS vacuum system has been connected.I started all turbo pumps.   