1404
|
Wednesday, November 23, 2016, 16:21 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 and TCS vacuum system has been connected. | All vacuum pumps have been started. Air
ballast 50seconds on roughing pump. Everything
is good so far. |
|
1405
|
Thursday, November 24, 2016, 09:33 |
Anders Mjos | Conditioning Station | Standard Operation | TM2 | UC#18 | Conditioning UC#18 | Thursday, November 24, 2016, 09:33: Water
package on
Thursday, November 24, 2016, 09:43: |
|
1406
|
Thursday, November 24, 2016, 10:30 |
David Wang | Conditioning Station | Standard Operation | TM2 | | HV cover is installed on TM2 at TCS | Interlock key are returned back to
B2 level.TM2 is ready for HV conditioning
and heating up at TCS. |
|
1408
|
Tuesday, November 29, 2016, 06:27 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TCS water pumps are stopped | Argon venting on TCS and TM2 is processing |
|
1409
|
Tuesday, November 29, 2016, 07:50 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 is disconnected at TCS. | Argon venting is done. |
|
1410
|
Tuesday, November 29, 2016, 12:57 |
David Wang | ITW | Standard Operation | TM2 | | TM2 is connected in ITW | All turbo pumps are started. Water system
and water signals have been checked. Pumping
down on ITW and TM2 is good so far. |
|
1411
|
Tuesday, November 29, 2016, 14:50 |
Travis Cave | ITW | Standard Operation | TM2 | UC#18 | module moved | TM#2 with UC#18 has been moved to ITW from
the conditioning station. |
|
1413
|
Saturday, December 03, 2016, 10:01 |
David Wang | ITW | Repair | TM2 | | venting ITW and TM2 with argon. | A short between TM2 EE and bias is produced
yesterday during tube heater ramp up.
Alex asked for an argon venting on ITW to |
|
1415
|
Monday, December 05, 2016, 10:10 |
David Wang | ITW | Standard Operation | TM2 | | Five shielding blocks have been transferred from ITE to ITW. | The ITW is configured to take proton beam. |
|
1419
|
Thursday, January 12, 2017, 14:24 |
David Wang | ITW | Standard Operation | TM2 | | ITW primary and secondary vacuum vessel winter shut down leak check. | TM2 is located in ITW for this leak check.
Leak detector is installed between ITW BV2s
as before. LD base leak rate 0.0XE-9atm.cc/sec, |
|
1420
|
Monday, January 16, 2017, 09:32 |
David Wang | ITW | Standard Operation | TM2 | | Helium pressure test on TM2 water llines at ITW | TM2 helium pressure test result at ITW.
70 psi helium 3 minutes on each circuit.
LD base LR0.0XE-9atm.cc/sec BP 0.0XE-4torr. |
|
1425
|
Tuesday, January 24, 2017, 15:24 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 electrical check and leack check. | I did electrical check before and after
Fefiad target installation on TM2. The RU
(coil) Is till short to 60KV as before. Other |
|
1426
|
Tuesday, January 24, 2017, 15:29 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 has been moved to TCS . | I connected TCS vacuum system to TM2. The
station is under roughing now. All turbo
pumps will be started soon. |
|
1427
|
Tuesday, January 24, 2017, 15:32 |
David Wang | ITW | Standard Operation | TM2 | | TM2 was moved from ITW to SHC this morning. | The move is smooth. Yasmine and Travis
did the move. |
|
1428
|
Friday, January 27, 2017, 08:44 |
chad fisher | South Hot-Cell | Standard Operation | TM2 | Ta#50 | UCx #18 - Ta Feibiad Dummy installed. Target Change Waterline interference | On Tuesday, January 24th UCx#18 was removed
from TM2 and Ta febiad dummy installed. I
encountered the same issue mounting the new |
|
1431
|
Friday, January 27, 2017, 10:52 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 has been moved from TCS to ITE | The move is successful. |
|
1432
|
Wednesday, February 01, 2017, 12:23 |
David Wang | ITE | Standard Operation | TM2 | | TM2 has been connected in ITE. | TM2 has been connected in ITE. The SST
window water lines in ITE can not be connected
properly to TM2. The water line connector |
|
1447
|
Wednesday, March 08, 2017, 14:09 |
David Wang | ITE | Maintenance | TM2 | | ITE IG1S increasing. | By retrieving data further, It has been
found no directly relationship between IG1S
surging and dump plug water opening. Vacuum |
   |
1457
|
Wednesday, March 22, 2017, 14:05 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | test target | module moved | TM#2 has been moved from the east target
station to the south hot cell. |
|
1458
|
Thursday, March 23, 2017, 09:30 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | test target | Electrical Check | Electrical check of the Ta test target
on TM#2 |
|