ID Date Author Categorydown Type Module Target/Number Subject
  735   Wednesday, September 03, 2014, 10:50 David WangITWStandard OperationTM1  TM1 has been disconnected in ITW.

  TM1 has been disconnected in ITW.

  744   Wednesday, September 10, 2014, 07:12 David WangITWRepairTM1 Removed ITW HS and COIL flow rate monitors.

Removed ITW HS and COIL flow rate monitors installed at the beginning of this year. They were installed on these two circuits for testing.They are broken during last run in ITW due to radioactive field.

  745   Wednesday, September 10, 2014, 08:52 Travis CaveITWStandard OperationTM1ZrC#6module move

TM#1 with ZrC#6 has been moved from the conditioning station to west target station.

  746   Wednesday, September 10, 2014, 11:47 David WangITWStandard OperationTM1 TM1 has been connected in ITW.

TM1 has been connected in ITW.  ITW and TM1 turbo pumps have been started. Water is supplied to TM1 only. Everything is good so far.

  749   Tuesday, September 16, 2014, 10:41 David WangITWStandard OperationTM1ZrC #45 Shielding blocks have been transferred from ITE to ITW.

5 Shielding blocks have been transferred from ITE to ITW. The ITW is configured to take proton beam

  762   Tuesday, October 14, 2014, 12:19 David WangITWStandard OperationTM1 TM1 was disconnected in ITW.

TM1 was disconnected in ITW this morning. Heat shield circuit is purged.

  782   Thursday, November 06, 2014, 08:07 David WangITWStandard OperationTM1ThO#1TM1 has been connected in ITW.

TM1 has been connected in ITW. All turbo pumps are started. The pumping down on ITW is good so far. The water is supplied to TM1 for HV conditioning.

  783   Thursday, November 06, 2014, 08:55 David WangITWRepairTM1ThO#1 primary vacuum back up pressureITH CG1 ,CG2,CG4A were high.

I found primary vacuum back up pressure ITH CG1, CG2, and CG4A were unusually high this morning. They should be about 10 -20 mtorr after one night pumping, but all of thier reading were 340-350-mtorr. Thease cause the current draw on primary turbo pumps were all over 2.0A(should be about 1.0A). I let Paul closed all BVs on primary side . The pressure dropped quickly to normal range after all BVs were closed. This shows the back up line are good. The problem are from   one of  the connections  on primary BVs. I let Paul opened the BVs one by one,but the problem did not show again. Now ,the current draw on the turbo pumps are back to normal also.

I will keep monitoring the system and take a look on all KF25 clamps on BVs once I have a chance to access to ITW.

  785   Thursday, November 13, 2014, 13:52 David WangITWStandard OperationTM1ThO#15 Shielding blocks have been transferred from ITE to ITW.

Dan and I transferred 5 shielding blocks from ITE to ITW. The ITW is configured to take proton beam.

  786   Thursday, November 13, 2014, 14:01 David WangITWRepairTM1 I replaced flow wheel and coil on ITW MSP water flow sensor.

I replaced flow wheel and coil on ITW MSP water flow sensor which is located in ITW pit. Before replacement, I checked the signal strength and frequency form e-board on this circuit. The signal was good in 10minutes watching. Still, I replaced them. The flow sensor works fine after replacement. I made a comment  on Isac e-fault system about this issue.

  846   Tuesday, February 17, 2015, 13:07 Anders MjosITWDevelopment  Resistance measured of TGHT and TBHT lines to ITW

 See e-log entry for ITE for details. The copper bars have not been removed. They can be used for testing the new power supplies.

Local measurement was done by Ray with a voltmeter. The voltmeter was consistent with EPICS readback and local readback on the power supplies. A voltage drop of 0.137 V @ 580 A was measured across the bus bar from the TGHT power supply to the cooled transmission lines.

  848   Wednesday, February 25, 2015, 10:44 David WangITWMaintenance  2015 shut dwon ITW water sensor coils and pedal wheels replacement

Dan and I replaced pedal wheels and coils on ITW water flow sensors. It is a shut down job we did every two years. See attachment for detail.

Attachment 1: 2015_shut_down_ITW_water_sensors__replacements.pdf
2015_shut_down_ITW_water_sensors__replacements.pdf
  849   Thursday, February 26, 2015, 09:22 David WangITWStandard Operation  TH Shut Down Activities Schedule Feb 23th- Mar 25th

TH shut down activities schedule from Feb 23th-March 25th. The schedule will be updated each week. See attachment 1.

Feb-27-2015: Updated the schedule, and uploaded as PDF file. See attachment 2.

Attachment 1: Target_Hall_shut_down_activities.mpp
Attachment 2: Target_Hall_shut_down_activities.pdf
Target_Hall_shut_down_activities.pdf
  853   Thursday, March 05, 2015, 07:17 David WangITWStandard Operation  TH Shut Down Activities Schedule Feb 23th- Apr 15th update

TH shut down jobs are processing as scheduled this week. Discussed with Don, and we think the jobs scheduled in next week should be processed as we planned. See attachments for updated schedule.

I updated the schedule today. See attachment 3, 4 for updating.  2015-Mar-10.

2013-Mar -13, I updated the schedule to show the jobs we finished this week. See attachment 5,6

Attachment 1: Target_Hall_shut_down_activities.pdf
Target_Hall_shut_down_activities.pdf
Attachment 2: Target_Hall_shut_down_activities.mpp
Attachment 3: Target_Hall_shut_down_activities.pdf
Target_Hall_shut_down_activities.pdf Target_Hall_shut_down_activities.pdf
Attachment 4: Target_Hall_shut_down_activities.mpp
Attachment 5: Target_Hall_shut_down_activities.pdf
Target_Hall_shut_down_activities.pdf Target_Hall_shut_down_activities.pdf
Attachment 6: Target_Hall_shut_down_activities.mpp
  893   Tuesday, April 21, 2015, 13:01 Grant MinorITWDevelopmentTM2 TM2 MK4 Optics Tray - banana plug bore modification (on bench)

The MK4 optics tray prepared for TM2 (as per ITA6082) had an undersized bore for the banana plug, making insertion of the plug extremely difficult / impossible.

Reference stores parts were collected to check the fit:  male plug 3-4/01152 and female jack 1-6/1201.  The size of the female jack was checked with a #21 drill at .159".

The bore on the optics tray was drilled out dry using the #21 drill to the same depth as the original blind hole, by Maico and Dan McDonald.  Chips were carefully collected in a rag, and the hole was blown out with compressed air.

The fit was checked to be snug but possible, using the male plug and the Remote Handling ultem base (ref ITA6023).

Redlines and photos are attached.

 

Attachment 1: ita6092_redlines_gminor_21apr2015.pdf
ita6092_redlines_gminor_21apr2015.pdf
Attachment 2: TM2_Optics_Tray_Bore_Mod_21Apr2015_1.JPG
TM2_Optics_Tray_Bore_Mod_21Apr2015_1.JPG
Attachment 3: TM2_Optics_Tray_Bore_Mod_21Apr2015_2.JPG
TM2_Optics_Tray_Bore_Mod_21Apr2015_2.JPG
Attachment 4: TM2_Optics_Tray_Bore_Mod_21Apr2015_3.JPG
TM2_Optics_Tray_Bore_Mod_21Apr2015_3.JPG
  902   Tuesday, April 28, 2015, 10:26 David WangITWStandard OperationTM1UCx12ITW target pit o-ring seal replacement.

Dan and I replaced ITW target pit o-ring seal(.275DIA X42"ID). It is an annual job before first beam to ITW. The old o-ring was moved and the groove was vacuum cleaned. The new o-ring has been installed properly.

  903   Tuesday, April 28, 2015, 11:09 Anders MjosITWMaintenance  Resistance measured of TGHT and TBHT lines to ITW

The new TBHT and TGHT power supplies were brough up to high current; 350 A and 420 A respectively. The TGHT power supply was limited by PLC to 420 A. The resistance calculated for both the TBHT and TGHT copper lines from the electrical services room to the ITW pit was 1.35 mOhm. See attached spreadsheet for details.

Dave Morris has been contacted to correct the current limit for the TGHT supply to 600 A.

Attachment 1: Resistance_from_Electrical_Room_to_Target_Station.xlsx
  904   Tuesday, April 28, 2015, 11:14 Travis CaveITWStandard OperationTM1UC#12Module move

TM#1 with UC#12 has been moved from the conditioning station to the west target station.

  905   Tuesday, April 28, 2015, 17:17 David WangITWStandard OperationTM1UCx12TM1 has been connected in ITW.

TM1 has been connected in ITW. Five turbo pumps have  been started. The TM1 containment box window line is capped on the service cap and the line is pump town to E-4 torr range.

  916   Friday, May 22, 2015, 15:44 David WangITWStandard OperationTM1UCx125 Shielding blocks have been transferred from ITE to ITW.

5 shielding blocks have been transferred from ITE to ITW. I  checked all ITW water signals, and they are good.  ITW is configured to take proton beam.