  1493   Wednesday, April 12, 2017, 16:39 Aurelia LaxdalSouth Hot-CellRepairTM3no targetTM3 Inspection at the South Hot Cell

Found spark signs on TM3's containment on the side of the water blocks. They may be OLD or/and NEW sparking signs, but this in not determined at this moment. Please see picture: first attachment. First and second attachment show the profiles of water block and HV lines.

  1492   Wednesday, April 12, 2017, 13:03 Travis CaveSouth Hot-CellStandard OperationTM3no targetElectrical Check

Electrical check of TM#3 with no target at the south hot cell

  1491   Wednesday, April 12, 2017, 12:51 David WangSouth Hot-CellRepairTM3 TM3 Ram readings @ SHC

 We have a ram installed on SHC pole which is 0.5 meter to  module shielding block surface. the readings we got today during TM3 move:
at containment box center (highest reading): 3.14 msv/hr.
at bottom  of shielding blocks: 960 usv/hr.
at 1/4  of  shielding blocks height from  bottom :700usv/hr.
at 1/2 of shielding blocks height from bottom: 340usv/hr.
at 3/4 of shielding blocks height from bottom:140u/sv/hr.
   The Ram is behind the pole and measured the surface which is 90 degree right side of that opened service tray side. 

  1490   Wednesday, April 12, 2017, 09:20 Travis CaveSouth Hot-CellRepairTM3no targetModule move

 TM#3 is now in the south hot cell.

  1489   Wednesday, April 12, 2017, 07:26 David WangConditioning StationStandard OperationTM2 TM2 and TCS vacuum system has been connected.

Roughing down overnight. Turbo pumps are started this morning. Everything looks good so far.

  1488   Tuesday, April 11, 2017, 14:06 David WangConditioning StationStandard OperationTM4 SHC, TM2 leak check on HS line.

Chad and I did leak check on TM1 HS line at SHC. 0.0XE-9 atm.cc/sec.  No leak.

  1487   Tuesday, April 11, 2017, 14:02 Travis CaveConditioning StationStandard OperationTM2Ta#51module moved

TM#2 with Ta#51 has been moved from the south hot cell to the conditioning station.

  1486   Tuesday, April 11, 2017, 11:30 Travis CaveSouth Hot-CellStandard OperationTM2Ta#51Electrical Check

Electrical check performed on TM#2 with Ta#51, see attached PDF.

  1485   Monday, April 10, 2017, 11:23 Travis CaveConditioning StationStandard OperationTM1no targetModule move

 TM#1 has been moved from the conditioning station to the north west silo.  There was a slight delay in the move as the limits for the hoist drum got way out of whack and had to be adjusted.

  1484   Friday, April 07, 2017, 09:53 Travis CaveConditioning StationMaintenanceTM1no targetElectrical Check and TM1 other checks

Results of an electrical check on TM#1 with no target attached to it.

 I use this e-log entry for TM1 notes as well  1. TM1 IG1 is a dual filament gauge . Its filament is very close to grid now. It shorted one time during the pumping down. It still works fine so far . But, we may need to change it if we use this module in TS again.

TCS 1G1 and 1G1S are pumped to 5Xe-6 torr. IG2 stayed at 2.5XE-5 torr. Since no target is installed on module , I capped top of HS water line. Maybe, the small o-ring seal in cap is too old, I found a big leak on this seal when i use LD check it. That is the reason IG2 stayed too high. Still, Leak check and helium presuure test are fulfilled on TM1. Leak detector BLR 5XE-7 atm.cc/sec, BP 0.0XE-4 torr9.  Back up pressure is 51 mtorr which is high because of leak on HS line cap seal so LD BLR is high. At this level, Ta+-, Tube +-, MSP,  EE are good.  Other air to vacuum seal are good as well at this leak rate.  I will check and change small o-ring seal in HS cap. The TM1 is functional basically.

  1483   Thursday, April 06, 2017, 15:16 Anders MjosConditioning StationMaintenance  Installation of new break out box to accommodate both ITM:MP2 and TCS:MP1

Installation by Marshall. Dave M from controls adjusted circuitry to get TCS:MP1 to start.

Work is being done in preparation for the Module Move Ventilation SAS project

  1482   Thursday, April 06, 2017, 15:11 Grant MinorCraneMaintenance  Target Hall Crane 20 ton hoist - Report by Gordon Crane 5-Apr-2017

-------- Forwarded Message --------

Subject:

ISAC Hoist Brake Repair

Date:

Wed, 05 Apr 2017 20:42:49 -0700

From:

Aidan C. Gordon <aidan@gordoncrane.com>

To:

Curtis Ballard <ballard@triumf.ca>, Neil Wong <nwong@triumf.ca>

CC:

Peter Neumann <peter@gordoncrane.com>, Shelley Cherkowski <Shelley@gordoncrane.com>

 

Hi Curtis

 

Further to the emergency service call at the Isac Target Hall on Thursday March 23rd, we advise as follows:

 

It was reported that the hoist was making an unusual noise and that there was a strong brake odour during operation.

The lift was completed using the auxiliary hoist.

 

A man-lift was arranged and Senior Service Technician Tom Kauss attended site the next morning to troubleshoot.

He determined that one of two hoist brakes (walkway side) had a strong odour and on closer examination it appeared that the 

brake lining material was breaking down and particulate lining material was getting caught between the lining and the discs.

These lining fragments were rubbing and burning off during the hoist operation.

The end cover of the brake had an accumulation of brake lining fragments 

The lining was not overly worn, but appears to be becoming friable, perhaps with age or exposure to radiation.

 

The brake was cleaned with compressed air to remove the friable material and thoroughly tested. 

A test load of approximately 10 tons was lifted and the hoist handled the load without issue

The brake fragment issue did not recur while we on site and the hoist was recommissioned for use.

 

To guard against the likely recurrence of this condition on this critical application crane, and as both brakes have seen identical conditions in operation, 

we recommend that both brake assemblies be replaced.

The brake assembly would include the brake coil, friction discs, steel brake discs and the brake springs

TRIUMF does not have a spare brake on hand, therefore one of the removed brakes could be rebuilt and kept on hand. 

 

Two (2) each  XL-60009637 Complete Brake Assemblies   $ 5,706.00  Each

 

One (1) only XL-60009674 Brake Repair Kit $ 2,435.00

            For Rebuild

 

One (1) only XL-52272125 Brake Spring Kit $     59.72 For Rebuild

Installation & Testing of New Brakes estimated at: $ 1,250.00 Lot

We have one brake in stock in our Vancouver Service Depot. A second brake is available Ex-Ontario

FOB Site

Applicable Taxes Extra

Quote Valid for 30 days, subject to prior sale.

 

We are available next week to perform this work on site.

Please let us know if you have any questions or if you would like us to proceed.

 

Best Regards

          Aidan

 

------------------

Aidan C. Gordon

General Manager

aidan@gordoncrane.com

Gordon Crane & Hoist Inc.

Celebrating 34 years of Excellence (1983-2017)


www.gordoncrane.com

Toll Free 1-866-HOIST-IT

              (1-866-464-7848)

Tel:  (604) 324-2441

105-8475 Ontario St

Vancouver BC  V5X 3E8


Privilege and Confidentiality Notice
The information in this email is intended for the named recipients only. It may contain privileged and confidential information. If you have received this email in error, any use, copying or dissemination of its contents is prohibited. Please notify the sender immediately by telephone at the number indicated on this page to arrange destruction and/or return of the email.  Your co-operation is appreciated. Thank you.

  1481   Thursday, April 06, 2017, 12:33 David WangConditioning StationRepairTM1 TM1 rust inpsection and removal

TM1 inside service cap surface and shielding plug surface are visually inspected yesterday. No rust has been found. I cleaned all rust on top of TM1  today.  Rust on TM1 silo  top plate are cleaned as well.

  1480   Wednesday, April 05, 2017, 14:13 David WangConditioning StationMaintenanceTM1 TM1 and TCS vacuum system are connected together

I started two turbo-pumps on TM1 and one small TP on TCS. They are work fine. 

  1479   Wednesday, April 05, 2017, 11:57 David WangITEMaintenance  ITE target module flange o-ring repalcement

ITE target module tank flange o-ring was replaced yesterday before TM4 moving. ITE: IG1S reading looks fine so far. 

  1478   Wednesday, April 05, 2017, 09:46 Travis CaveConditioning StationStandard OperationTM1no targetmodule moved

TM#1 has been moved from the North West silo to the conditioning station.

  1477   Tuesday, April 04, 2017, 14:40 David WangITEStandard OperationTM4 TM4 has been connected in ITE

all turbo-pumps are started. Everything looks fine so far.

  1476   Tuesday, April 04, 2017, 14:39 David WangCraneStandard Operation  Crane check main hoist on jogging with shielding plug lifted.

Today, I checked TH crane main hoist  when shielding plug is installed into ITE pit. I did  some jogging actions on main hoist during the operation. Everything looks fine. No burning smell, no strange noise. An outside crane expert suggest that jogging is the worst working situation for crane. We have to use jogging actions during our crane operation. But, we could try to use less jogging when operate the crane.

  1475   Tuesday, April 04, 2017, 10:24 David WangConditioning StationStandard OperationTM4 Stopped TCS pumps this morning

 Argon vented TCS and TM4 after pumps are stopped.

  1474   Tuesday, April 04, 2017, 10:23 David WangConditioning StationStandard OperationTM4 Helium pressure leak check on TM4 Ta(-) water lines

This morning, The helium pressure leak check on TM4 Ta(-) is done after TM4 finished conditioning yesterday.  LD base LR:8.0XE-9 atm.cc/sec, base pressure: 0.0XE-4 torr. Applied 70 psi helium to TM4 TA(-) water line. The LR slowly climbed to 2.2XE-7 atm.cc/sec, and stopped there. Waited for 5 minutes and change at 2.2 X E-7 atm.cc/sec.