Tuesday, August 29, 2023, 14:32, Frank Song, North Hot-Cell, Standard Operation, TM4, Ta#65, electrical check/leak check
|
TM4 with new target Ta#65 has been E/L checked at NHCPost. |
Thursday, June 27, 2024, 09:49, David Wang, North Hot-Cell, Standard Operation, , Nb#10, Nb#10target has been remotely transferred from NHC to SHC.
|
Nb#10target has been remotely transferred from NHC to SHC. |
Wednesday, September 11, 2024, 13:38, Adam Newsome, North Hot-Cell, Repair, , , Spare Manipulator - Y-axis motion not functioning
|
Update 2024-09-12: C. Fisher confirms this is actually normal behaviour. The Y-axis motion is inhibited when X and Z
are in a certain configuration, which was true when the manipulator was mounted on the wall in storage position. Non-issue. A note about this has been
made in the operator manual. |
Monday, September 16, 2024, 08:23, chad fisher, North Hot-Cell, Repair, , , Model N Remote end #9352 reapir
|
On Friday, September 6, 2024 Model 'N' remote arm #9352 was removed from the NHC right side installed position to investigate an ongoing issue
with the tong motion circuit (no motion on the remote side when handle on operator side operated).
Inspection revealed that the tong cable on this arm have hopped its cable drum and rapped around the shaft of the cable drum. As well, the tong |
Wednesday, January 29, 2025, 11:39, chad fisher, North Hot-Cell, Repair, , , Model N Remote Arm #9342 Tong Cable
|
Model N remote arm serial #9342 tong cable has been un-jammed from between pulley 3D (see picture) and casting (this is an ongoing issue with #9342 and
9352) and cable restrung and exercised to check motion. Tong system is now functional but exhibits excessive slack. Next step will be to check tension
of the elevation/twist cables and adjust the pulley block if required (this pulley block houses both the elevation twist cable pulleys and the tong cable |
Tuesday, April 01, 2025, 09:47, Frank Song, North Hot-Cell, Repair, , , Two NHC light bulbs replacement    
|
2 broken lights of NHC were replaced in Target Hall. see pics attached. |
Friday, April 11, 2025, 13:34, chad fisher, North Hot-Cell, Repair, , , remote end 9342 installed
|
On March 27 remote end 9342 was installed on the west position (right hand as viewed by operator) and arm 9764 removed and moved to anteroom.
Previous to this installation, arm 9342 received tensioning of the elevation twist pulley block and tightening of the tong cable opening via the
tong cable drum. Tong opening was reduced to roughly 2" to achieve tension in the tong cable such that slack upon release of the system was reduced |
Friday, April 11, 2025, 13:46, chad fisher, North Hot-Cell, Repair, , , Remote end 9**4 repair
|
Tong cable on remote arm 9**4 has be relocated onto its pulleys and tong opening adjusted at the tong cable drum by changing the position of the tong
cable screws by two positions (tightened/closed) such that the air tool will fit in the tong and some of the slack in the tong system has been taking up.
An attempt was made to also adjust the elevation twist pulley block which would also aid in taking up slack in the tong system however, the elevation |
Wednesday, April 23, 2025, 14:08, Adam Newsome, North Hot-Cell, Standard Operation, TM4, , TM4 Module Move
|
TM4 was moved from Safe Module Parking to the North Hot Cell today. |
Thursday, April 24, 2025, 11:13, Frank Song, North Hot-Cell, Standard Operation, TM4, UCx#48, electrical check/leak check
|
TM4 with new target UCx#48 installed was E/L checked on the top of NHC, see attachment uploaded with pls. |
Thursday, April 24, 2025, 12:53, Aaron Tam, North Hot-Cell, Standard Operation, TM4, UC#48, UC#48 IGLIS Install onto TM4 
|
C. Fisher, A. Schmidt, A. Tam
UC#48 Handover satisfactory
Target taken out of glovebox and tested for fit
The left most triplet conductor leg was seen to be slightly misaligned, |
Friday, May 02, 2025, 10:16, Aaron Tam, North Hot-Cell, Maintenance, , , NHC Window Oil Fill 12x
|
Findings
During April 2025 safety walk ID: 2796 , it was noted that the oil level in NHC window oil expansion tank was below the indicator
range.
previous safety walks from July, October, Jan 2024 did not show any issues, but this was not a recorded item, only to check for leaks
|
Monday, May 05, 2025, 09:18, chad fisher, North Hot-Cell, Maintenance, , , Manipulator Remote End Replacement 9352 with 9764
|
Remote end 9352 replaced with end 9764 due to signs of an issue with the tong cable (tong opening excessively large and slack in cable on one side).
Upon replacement tong opening on 9764 also opened larger then the remote end was set to. Everything is operational but this phenomenon indicates the handle
cable system on operator side must be where the excess is coming for. This is further indicted but the position of the locking screw on the handle cable |
Tuesday, May 06, 2025, 14:40, Frank Song, North Hot-Cell, Standard Operation, TM2, UC#49, electrical check/leak check
|
TM2 with new target UC#49 installed is E/L checked on the flange of NHC in TH. see attachment for detail. |
Wednesday, May 07, 2025, 13:41, Aaron Tam, North Hot-Cell, Standard Operation, TM2, UC#49 , UC#49 SIS w/ Gasline Install   
|
May 7th, 2025 - Aaron Schmidt, Aaron Tam
UC#49 Handover - good
April 30th - Initial fit check was performed |
Tuesday, June 17, 2025, 11:32, Adam Newsome, North Hot-Cell, Standard Operation, TM4, UC#48, Module move
|
TM#4 with UC#48 was moved from the East target station to the North Hot Cell for target exchange.
Reading at ITE = 36 mSv/h
Reading at NHC = 133 mSv/h |
Tuesday, June 17, 2025, 12:59, Frank Song, North Hot-Cell, Standard Operation, TM4, C#5, electrical check/leak check
|
TM4 with new target number C#5 installed had been leak/electric checked on NHC flange in TH. see pic attached with pls. |
Wednesday, June 18, 2025, 11:23, Aaron Tam, North Hot-Cell, Standard Operation, TM4, UC#48 Pail#303, UC#48 Removal from TM4, PIE, Spent Target Pail Loading 14x
|
June 17th, 2025 - Aaron Tam, Brady Borrmann, David Wang, Travis Cave
UC#48 Removal 10:20am - 11:35am
Upon loosening of right-side water line, some leakage was observed (photos attached)
As soon as this was noticed, |
Wednesday, June 18, 2025, 11:32, Aaron Tam, North Hot-Cell, Standard Operation, TM4, C#5 SIS , C#5 Installation 9x
|
June 17, 2025 - Aaron Tam, Brady Borrmann, David Wang
Target handover 8:30am
Checks were made a day prior to insertion to leave time for adjustments
Lower conductor leg holes were ovalized and aligned |
Monday, September 16, 2024, 08:48, chad fisher, Manipulator Maintenance, Maintenance, , , CRL Technicain Manipulator Maitenance Trip
|
Over the course of September 9th - September 13, 2024 a CRL manipulator technician carried out the following manipulator maintenance:
NHC operator side arm #9763 (right side installed position) - Inspection and re-tensioning of tong cable prior to re-installation (was a little
too tight). Operational. |
|