Message ID: 2817     Entry time: Wednesday, June 18, 2025, 11:32
Author: Aaron Tam 
Category: North Hot-Cell 
Type: Standard Operation 
Module: TM4 
Target/Number: C#5 SIS  
Subject: C#5 Installation 

June 17, 2025 - Aaron Tam, Brady Borrmann, David Wang

Target handover 8:30am

  • Checks were made a day prior to insertion to leave time for adjustments
  • Lower conductor leg holes were ovalized and aligned with job
  • Final inspection on the jig was conducted the day of insertion, and brought to the anteroom

Target Insertion 8:50am

  • Target insertion completed without issue
  • This was done before TM4 was moved into North Hot Cell

Removing UC#48 10:20am - 11:35am

  • Details in ELOG# 2816

Target installation 11:40am - 12:45pm

  • Water from UC#48 removal had visually dried out by the time UC#5 was set for installation 
  • Successfully passed leak check and electrical check on first attempt

 

Attachment 1: Target_inserted_onto_pins.jpg  355 kB  | Show | Hide all
Attachment 2: Target_Fully_installed.jpg  332 kB  | Show | Hide all
Attachment 3: Dry_Waterlines.jpg  145 kB  | Show | Hide all
Attachment 4: Dry_Ceramic.jpg  126 kB  | Show | Hide all
Attachment 5: target_tube_conductor_bolt_1.jpg  145 kB  | Show | Hide all
Attachment 6: Target_tube_Conductor_bolt_2.jpg  168 kB  | Show | Hide all
Attachment 7: Transfer_tube_bolts.jpg  179 kB  | Show | Hide all
Attachment 8: VCR_nuts_fully_seated.jpg  143 kB  | Show | Hide all
Attachment 9: containment_box_panel_reattached.jpg  303 kB  | Show | Hide all