1781
|
Wednesday, September 12, 2018, 15:30 |
Isaac Earle | North Hot-Cell | Development | | | Installation of NHC operator-level lighting completed | Installation of of operator-level
lighting in the NHC was completed today according
to drawing IRH1801. 2" x 2" |
  |
1782
|
Thursday, September 13, 2018, 16:57 |
Isaac Earle | North Hot-Cell | Development | | | NHC grounding and mili-ohm testing | The
following equipment has been connected to
the building ground located in the Target |
|
1825
|
Thursday, November 22, 2018, 14:38 |
Isaac Earle | North Hot-Cell | Development | | | NHC design approved by High Voltage Engineer | To satisfy RS 101 from the NHC requirements
specification (Document-131915) Tomislav
Hurskovec was consulted regarding high voltage |
|
1826
|
Monday, November 26, 2018, 12:19 |
chad fisher | North Hot-Cell | Repair | | | East Manipulator | In preparation for removing the slave for
replacement I discovered that the timing
screw in the handle cable drum (master side) |
 |
1837
|
Friday, December 07, 2018, 08:47 |
chad fisher | North Hot-Cell | Repair | | | North hot cell spare slave repair | The tong cable on the spare north hot cell
slave has been repaired. Slave came from
the factory with the tong cables straddling |
|
1838
|
Friday, December 07, 2018, 10:37 |
chad fisher | North Hot-Cell | Repair | | | Ariel connector test | Completed testing of connectors for Ariel
using the north hot cell.
Video can be found on docushare; |
|
1839
|
Monday, December 10, 2018, 15:31 |
Isaac Earle | North Hot-Cell | Development | | | NHC remote connection testing with manipulators | The following tests have been successfully
completed using the NHC manipulators:
Ventilation pre-filter |
|
1841
|
Tuesday, December 18, 2018, 11:13 |
Isaac Earle | North Hot-Cell | Development | | | NHC manipulator slave-end swap, RH test, and various other work | The following
North Hot Cell work was completed over the
last week under work permit I2018-12-12-1: |
|
1847
|
Friday, January 04, 2019, 14:38 |
Isaac Earle | North Hot-Cell | Development | | | NHC cameras tested | The NHC module support flange cameras (4
total) as well as the NHCSA camera were tested
today and confirmed to be working properly. |
  |
1859
|
Friday, January 18, 2019, 10:26 |
Isaac Earle | North Hot-Cell | Development | | | NHC sealing improvements and repeat of RH test for LED lights | The following NHC development work was
completed under WP I2019-01-09-4:
Location of RH feature |
|
1860
|
Monday, January 21, 2019, 16:27 |
Isaac Earle | North Hot-Cell | Development | | | NHC in-cell camera wired to right side monitor | The NHC right side monitor has been
wired to display the signal from the in-cell
camera. This was tested using a snake |
|
1864
|
Thursday, January 31, 2019, 14:16 |
Isaac Earle | North Hot-Cell | Development | | | NHC grounding approval | Franco Mammarella was consulted regarding
electrical grounding of the NHC design (RS103
of Document-131915). After discussing |
|
2073
|
Thursday, February 27, 2020, 16:08 |
Anders Mjos | North Hot-Cell | Maintenance | | | Hot Cell Entry | Chad entered the NHC today to tighten set-screws
on both slave side manipulators and re-align
the West side slave. Work took place using |
|
2091
|
Friday, March 27, 2020, 08:45 |
Matthew Gareau | North Hot-Cell | Maintenance | | | Issues with the manipulators | This is a link to all of the issues
with the NHC manipulators that I know of
|
|
2158
|
Tuesday, October 27, 2020, 11:46 |
Matthew Gareau | North Hot-Cell | Repair | | | Ratcheting repair issues with both left and right master |
|
|
2174
|
Thursday, December 24, 2020, 09:00 |
Matthew Gareau | North Hot-Cell | Development | | | NHC USB connection | |
|
2196
|
Thursday, March 04, 2021, 16:30 |
Isaac Earle | North Hot-Cell | Development | | | NHC gas delivery lines leak checked | The North Hot Cell gas delivery lines
(labeled 1, 2, and 3 on the hot and cold
side panels) were leak checked today. |
|
2197
|
Friday, March 05, 2021, 09:12 |
Matthew Gareau | North Hot-Cell | Development | TM3 | | Containment box door removal and swivel arm test | First thing I entered into the NHC to install
to the target kart mounting clip, and remove
excess tools and materials from the hotcell |
|
2217
|
Tuesday, May 25, 2021, 15:59 |
Matthew Gareau | North Hot-Cell | Development | | | Removed boot from left hot manipulator | Myself and Isaac removed the boot
from the left hot manipulator.
- opened the hatch in the TH to get |
7x |
2224
|
Wednesday, June 09, 2021, 09:16 |
Travis Cave | North Hot-Cell | Standard Operation | TM2 | no target | Module move | TM#2 has been moved from the SHC
to the NHC. |
|