Entry  Thursday, June 30, 2022, 14:28, Nadia Jorgenson, Safe Module Parking, Standard Operation, , , Annual Inspection of Safe Module Parking - Electrical  
 
An annual electrical inspection was performed on the SMP today by Travis Cave and
Nadia Jorgenson as per Work Permit I2022-06-30-2. The following items were checked:
Entry  Monday, July 04, 2022, 11:44, Nadia Jorgenson, Safe Module Parking, Standard Operation, , , Annual Inspection of Safe Module Parking - Mechanical  SMP_Missing_Washers_1.jpgSMP_Missing_Washers_2.jpgSMP_Missing_shims.jpg
 
An annual mechanical inspection was performed on the SMP today
by Dan McDonald and Nadia Jorgenson. The following items were checked:
Entry  Tuesday, January 10, 2023, 10:15, Frank Song, Safe Module Parking, Standard Operation, TM2, UCx40 removed, TM2 electrical check with no target attached on SW silo TM2_electrical_check_without_UCx40_on_SW_silo.png
 TM2 with no target on SW silo be electrical checked right after module moving.
Entry  Thursday, May 04, 2023, 07:14, David Wang, Safe Module Parking, Standard Operation, TM4, , SMP vacuum pumpimg down is stopped.  
SMP  vacuum pumping down is stopped. SMP and TM4 venting to atmosphere will be started soon. 
Entry  Wednesday, June 21, 2023, 14:39, Adam Newsome, Safe Module Parking, Maintenance, , , Annual electrical and mechanical inspection of Safe Module Parking PXL_20230621_210144119.MP.jpgPXL_20230621_210546559.jpgPXL_20230621_210146892.jpg
An annual electrical and mechanical inspection was performed on the  SMP today by Adam Newsome, Travis Cave, Eric Lahe, Maico Dalla Valle, Antoniette
Yap, and Jason Zhang as per Work  Permit I2023-06-21-4. The following items were checked:

    Check condition of wiring for physical/radiation/UV damage
    
        OK, no signs of significant damage
    
Entry  Friday, January 26, 2024, 11:53, David Wang, Safe Module Parking, Standard Operation, TM4, , Tm4 has been moved to SMP. 
TM4 has been moved to SMP. The move is smooth. I started SMP vacuum pump. The TM4 and SMP vessel is under vacuum now. 
Entry  Friday, January 26, 2024, 11:57, David Wang, Safe Module Parking, Standard Operation, TM4, , TM4 coil1, 2, and HS electrical check at SMP after module moving. 
TM4 coil1, 2 and HS are all OL at 250V at SMP after module move. This week, Chad and Carl fixed short issue on coil1, 2 and HS by insert dropped ultem
ring back to position at SHC. 
Entry  Wednesday, July 10, 2024, 09:55, Adam Newsome, Safe Module Parking, Maintenance, , , Annual electrical and mechanical inspection of Safe Module Parking  PXL_20240710_160636341.jpgPXL_20240710_160506424.jpg
An annual electrical and mechanical inspection was performed on the   SMP today by Adam Newsome, Travis Cave, Riley Sykes, Maico Dalla Valle, and Jason
Zhang as per Work  Permit  I2024-07-10-1. The  following items were checked:

    Check condition of wiring for physical/radiation/UV damage
    
        OK, no signs of significant damage
    
Entry  Friday, July 12, 2024, 08:51, Riley Sykes, Safe Module Parking, Maintenance, , , SMP chain guard 
 SS washers were added to all slotted holes on SMP chainguard cover plate
Entry  Thursday, January 09, 2025, 11:46, David Wang, Safe Module Parking, Standard Operation, TM4, No target, SMP is under vacuum for TM4 storage during shut down.  
 SMP:MP1 is started with SMP BV1 is opened. SMP is under vacuum for TM4 storage during shut down.
Entry  Wednesday, December 18, 2024, 14:17, Adam Newsome, Pail Handling Tool, Maintenance, , , Pail Handling Tool - Inspection ISAC_Pail_Handling_Tool_Inspection_Record_-_2024.pdf
An informal inspection of the main Pail Handling Tool was performed today as the final one for the year. Note that the main formal annual inspection
was performed June 18, 2024 for this year.
The attachment to this e-log serves as a record of all inspections for this tool throughout 2024.
Entry  Wednesday, May 04, 2016, 11:14, Isaac Earle, North Hot-Cell, Development, , , North Hot Cell Scope Decision 
A meeting was held on May 4, 2016 to determine the scope of the North Hot Cell project.  The following was agreed upon by those in attendance:
The NHC will be a designated target change hot cell.  It will be capable of performing all routine target operations (target removal/installation,
leak check, electrical check, video inspection, post irradiation examination, target waste packaging and removal) using the same method currently used
Entry  Friday, July 29, 2016, 14:27, Isaac Earle, North Hot-Cell, Development, , , North Hot Cell Measurements & Cleanup 
 The North Hot Cell was accessed today via the Ante Room for inspection, measurements,
and clean-up.  There were no modules in the SHC or TCS, and no spent targets in the SHC.  Under these conditions the maximum field in the NHC
was approximately 2μSv/hr.  The inside of the cell was cleaned and swept, followed
Entry  Friday, August 05, 2016, 14:13, Isaac Earle, North Hot-Cell, Development, , , Preparations for NHC Ventilation Test 
A hole was drilled in the NHC exhaust duct in the east end of the target hall above the hatch to the Ante Room.  This will be used for measuring
NHC exhaust flow rate with a thermal anemometer.  The hole was tapped and plugged with an NPT tap.
Flow was measured in the existing hole in the SHC exhaust duct in approximately the same location.  Flow velocity was measured to be 1415
Entry  Wednesday, August 10, 2016, 14:38, Isaac Earle, North Hot-Cell, Development, , , North Hot Cell Ventilation Test Results 
Testing was performed on August 9th on the ISAC nuclear ventilation system to determine if the existing ventilation system can achieve the required cell
depressions for both SHC and NHC under all expected configurations and if a proposed modification to the DDC control system can provide acceptable stability
and response time for the system.  The proposed control system observes the lower of the SHC depression or the NHC depression + 10% (to avoid stability
Entry  Wednesday, September 07, 2016, 11:39, Isaac Earle, North Hot-Cell, Development, , , NHC North / South Wall Gap Measurements 
 Measurements were taken today of the NHC north/south wall gap at the location where the NHC/TCS partition wall will be installed (43.375"
from the NHC west wall).  A HILTI PD40 laser range meter was used for the measurements.  They were taken at 10", 34", 62", 90",
118", and 142" from the floor which matches the top of each cross-beam.  The results are below:
Entry  Thursday, September 15, 2016, 11:05, Isaac Earle, North Hot-Cell, Development, , , NHC / SHC feedthrough panel removed original_panel.JPGpanel_removed.JPGtemp_panel.JPG
The sheet metal panel covering the NHC/SHC feedthrough port was removed today using a slide-hammer to pull out the concrete anchors (this oversized panel
would have interfered with the NHC partition wall).  50cpm was found on the inside of the panel, 100cpm on the NHC side lip of the feedthrough, and
350cpm on the face of the shielding bricks in the feedthrough.  Various dimensional measurements of the feedthrough were taken which will be added
Entry  Tuesday, November 08, 2016, 14:04, Isaac Earle, North Hot-Cell, Development, , , Interference check with TCS turbo pump and proposed NHC duct routing IMG_7577.JPGIMG_7583.JPGIMG_7582.JPG
David Wang and I accessed the NHC today to check if the proposed duct routing (IRH1618) will interfere with servicing or replacement of the TCS turbo
pump.  A piece of plywood was placed in the future position of the NHC/TCS partition wall (IRH1609), and a ducting elbow was placed at the approximate
position of the nearest elbow to the turbo pump.
Entry  Friday, December 09, 2016, 14:58, Isaac Earle, North Hot-Cell, Development, , , NHC service area floor and top of roof block painted NHC_SA_before_and_after.jpgNHC_roof_before_and_after.jpg
 The concrete floor in the North Hot Cell service area and the top of the NHC roof block in the target hall have been painted with Macropoxy 646
oil based epoxy paint, colour Flint Grey.  Two coats were used for the NHC roof, and one for the service area floor.
 
Entry  Tuesday, January 17, 2017, 13:45, Isaac Earle, North Hot-Cell, Development, , , NHC ducting installed IMG_7688.JPGIMG_7716.JPGIMG_7723.JPGIMG_7721.JPG
 The new ducting section connecting the existing duct termination in the TCS space to the NHC partition wall has been installed by Smith Sheet Metal
contractors.  The installation drawing is IRH1618.  There was not enough clearance between the duct pipe and the TCS vessel to butt weld the
new ductwork as originally intended.  Instead a flange was welded to the existing pipe and also to the new section and the two were bolted together.