  1753   Monday, July 16, 2018, 17:41 Anders MjosITEStandard OperationTM4UC#22Target module disconnectedThe water and electrical connections were
disconnected today as protons remained off
after power interruption during the weekend.
 TM4_UCx_22#__disconnection_check_list_1.pdfTM4_UCx_22#__disconnection_check_list_2.pdf 
  1752   Wednesday, July 11, 2018, 15:09 Anders MjosITWMaintenanceTM2Nb#8Uncovered ITW to toubleshoot 2A2M19The 2A2M19 beam profile monitor did not
work and was e-faulted.
After initial troubleshooting 2 blocks were
  
  1751   Wednesday, July 11, 2018, 15:06 Anders MjosITWStandard OperationTM2Nb#8Block moveMaico and Travis moved blocks from ITE
to ITW yesterday
  
  1750   Tuesday, July 03, 2018, 14:42 David WangITWStandard OperationTM2Nb#8TM2 has been connected to ITW.TM2 has been connected to ITW. All turbo
pumps are started. See attachment for connection
checklist.
 Nb#4_Module_connection_checklist.pdf 
  1749   Tuesday, July 03, 2018, 14:38 David WangITWStandard Operation  ITW water signals interlock check.Annual ITW water signals interlock check
are done. Everything works good.
  
  1748   Tuesday, July 03, 2018, 09:57 Travis CaveITWStandard OperationTM2Nb#8Module move TM#2 with Nb#8 has been moved from
the south hot cell to the west target station.
  
  1747   Friday, June 29, 2018, 13:36 Travis CaveSouth Hot-CellStandard OperationTM2Nb#8Electrical Check The results of the various electrical
checks performed on the TM#2 with and without
the Nb#8 target attached.
 TM2_elec_chk_steerers_and_lens_062818.pdfTM2_Nb8_elec_chk_shc.pdfTM2_notgt_elec_chk_shc_062918.pdf 
  1746   Friday, June 29, 2018, 10:27 chad fisherSouth Hot-CellMaintenance  South Hot Cell Filter ChangeAt the end of manipulator repair Thursday
the ventilation pre-filter in the hot cell
was changed. Old filter remains in the hot
  
  1745   Friday, June 29, 2018, 10:15 chad fisherSouth Hot-CellStandard OperationTM2 TM2 work and target installOn Thursday, June 29th the containment
box of TM2 was removed and the optics tray
re-installed and reconnected. The box was
  
  1744   Friday, June 29, 2018, 10:12 chad fisherSouth Hot-CellMaintenance  Manipulator Tong Cable ReplacementTuesday, June 26 the broken tong cable
was replaced on the west manipulator in the
south hot cell. Wednesday the tong cable
  
  1743   Wednesday, June 27, 2018, 14:56 Travis CaveSouth Hot-CellStandard OperationTM2no targetModule move TM2 has been moved from the silo
to the south hot cell.
  
  1742   Tuesday, June 26, 2018, 08:56 chad fisherSouth Hot-CellStandard Operation  South Hot Cell Fieldshot items have been moved and shielded
as much as possible. Field at left manipulator
has been reduced from 560 uSv/h to 85 uSv/h.
  
  1741   Monday, June 25, 2018, 16:42 Anders MjosConditioning StationDevelopment  Testing new high current connectorsShorted TGHT with new high current connector
assembly and heated to 600 A. Temperature
measured on half way point on cable ~ 70
  
  1740   Monday, June 25, 2018, 11:31 chad fisherSouth Hot-CellStandard Operation  Fields at Al coverThe shield door has been opened and fields
measured at 77 uSv/h on contact at the AL.
panel.
  
  1739   Friday, June 22, 2018, 13:59 chad fisherSouth Hot-CellRepair  Soth Hot Cell FieldsField measurements have been taken to determine
the level before entry for repair of manipulators.
Field on contact at manipulator is
  
  1738   Thursday, June 21, 2018, 17:15 Isaac EarleNorth Hot-CellDevelopment  Motorla CP200 radio with throat mic tested in NHC A Motorla CP200 portable two-way
radio was tested today for use inside the
ISAC hot cells.  A High Technology Communications
  
  1737   Thursday, June 14, 2018, 11:37 David WangITEStandard OperationTM4UC#22TM4 UC 22# checklist.See attachments  TM4_UCx_22#_check_list.pdf 
  1736   Tuesday, June 12, 2018, 11:26 chad fisherSouth Hot-CellRepairTM2 TM4 Optics TrayI have "slung" the TM4 optics
tray in preparation for its removal.
 fh.jpg 
  1735   Monday, June 11, 2018, 11:30 chad fisherSouth Hot-CellRepairTM2 TM2 containment box onTm2 containment box has been re-installed
onto TM2.
  
  1734   Friday, June 08, 2018, 14:24 Travis CaveSouth Hot-CellStandard OperationTM2no targetModule move TM#2 has been moved from the conditioning
station to the south hot cell.
  