Monday, November 05, 2018, 14:27, Anders Mjos, Conditioning Station, Standard Operation, TM2, UC#25, Target module disconnected
|
Frank and Anders disconnected the water and electrical connections this afternoon after the target was conditioned over the weekend. The heater ramping
program ran with the wrong gauge selected, causing the vacuum to go higher than planned. The module will be moved to ITW tomorrow. |
Monday, November 05, 2018, 08:24, Travis Cave, Spent Target Vault, Standard Operation, , nSiC#1, Spent Target Move
|
The spent nSiC#1 target has been moved from the south hot cell to the spent target vault. It was placed in pail #172 and placed in spot 7B. See
attached PDF for vault details. |
Thursday, November 01, 2018, 11:42, David Wang, Conditioning Station, Standard Operation, TM2, UCx 25., TM2 HS line helium pressure test at TCS and helium spray at SHC..
|
Chad and I did leak check on TM2 HS line at SHC yesterday. Base LR 0.0XE-9 atm.cc/sec. No response on LD. during helium spray.
Today , I did helium pressure test at TCS. base LR 0.0xe-9atm.cc/sec. applied 70psi helium for 3 minute. leak rate slowly climbed to2.2 Xe-7 atm.cc/sec
ate stopped there. The result is close to before. |
Wednesday, October 31, 2018, 14:23, Travis Cave, South Hot-Cell, Standard Operation, TM2, nSiC#1 and UC#25, Electrical Check 
|
TM#2 with targets nSiC#1 (old target) and UC#25 (new target) electrical check results. See attached for details. |
Wednesday, October 31, 2018, 14:20, Travis Cave, Conditioning Station, Standard Operation, TM2, UC#25, Module move
|
TM#2 with UC#25 has been moved from the south hot cell to the conditioning station. |
Tuesday, October 30, 2018, 10:50, Travis Cave, ITW, Standard Operation, TM2, nSiC#1, Modules moved
|
Modules were moved, ITW EX2 was moved from the conditioning station to the west target station and TM#2 ,with nSiC#1, was moved from the
west target station to the south hot cell. |
Monday, October 29, 2018, 10:43, David Wang, Conditioning Station, Repair, , , ITW exit 2 leak check at TCS.
|
I did a leak check this morning on exit 2 module at TCS. LD base leak rate is 4.00XE-9atm.cc/sec, Base pressure is 0.00 X E-4 torr. All seals,
bellows, and flanges are checked. The new FC5 bellow is good. There is a big leak up to 2X E-6 atm.c/sec has been found on IG1S side panel . The panel
itself will be replaced this time. Machine shop is working on it.. Two small leaks in E-9 atm.cc/sec range have been found on the o-ring |
Friday, October 26, 2018, 09:44, Travis Cave, Conditioning Station, Standard Operation, , , Exit Module moved
|
The west exit #2 module has been moved from the south hot cell to the conditioning station. |
Thursday, October 25, 2018, 11:03, chad fisher, South Hot-Cell, Repair, , , Exit 2 West 8x
|
Actuator arms, lemos, lemos and banana plug block have been disconnected in preparation for raising of the service tray. Aaron has pictures |
Tuesday, October 23, 2018, 11:32, David Wang, South Hot-Cell, Maintenance, , , ITW RV4S leak check.
|
ITW RV4S (A and B) are leak checked. They are good. |
Tuesday, October 23, 2018, 10:53, chad fisher, South Hot-Cell, Repair, , , Exit 2 East
|
Cover 1 was removed from the exit module. Confirmed with David that the actuator rod that needed to be disconnected was the far left )as viewed by the
hot cell operator). The fastener for this rod was un-accessible from this side. Cover 1 was re-installed (two bolts left loose) and cover 2 was removed.
fastener holding the actuator together was removed and luckily it does have a remote start. |
Tuesday, October 23, 2018, 10:45, David Wang, ITW, Standard Operation, TM2, SiC nano, TM2 was disconnected in ITW.
|
TM2(SiC nano) has been disconnected in ITW. See attachment |
Monday, October 22, 2018, 14:05, Travis Cave, ITW, Repair, , , Module move
|
ITW Exit #2 has been moved from the west station to the south hot cell for a bellows repair. |
Wednesday, October 10, 2018, 10:50, Travis Cave, Conditioning Station, Standard Operation, TM4, Ta#57, Electrical Check  
|
The various electrical check done on TM#4 after the UC run and before the start of the Ta run. |
Wednesday, October 10, 2018, 07:52, David Wang, ITE, Standard Operation, TM4, Ta#57, TM4 has been connected in ITE.
|
TM4 has been connected in ITE. see attachment. |
Tuesday, October 09, 2018, 13:46, Travis Cave, ITE, Standard Operation, TM4, Ta#57, Module move
|
TM#4 with Ta#57 has been moved from the conditioning station to the east target station. |
Tuesday, October 09, 2018, 12:32, David Wang, Conditioning Station, Repair, TM4, , TM4 steers 4 pin feedthrough CF flange
|
TM4 Steers 4 pin feedthrough CF flange is replaced due an inside feed through insulator broken. CF 25 cooper seal is replaced with a new one as well.
Travis did anelectrical check. after replacement. Everything looks fine.
|
Friday, October 05, 2018, 14:41, Travis Cave, Spent Target Vault, Standard Operation, , UC#24, Spent Target Move
|
UC#24 has been moved from the south hot cell to the spent target vault. The target is in pail #171 and placed in spot 4C. See attached PDF for
details. |
Wednesday, October 03, 2018, 14:16, David Wang, South Hot-Cell, Standard Operation, TM4, Ta #57, Leak check TM4 Lp Ta# 57 at SHC.
|
Tried to leak check TM4 Ta57# at TCS. LD failed to pump down properly at fine range. It always tripped at 4 torr. I cheeked all vacuum lines seals and
adapters on top of module to LD. Everything is good. Chad said the VCRs at SHC can not be tightened any more. Discussed with Anders, we decide to move
module TCS and helium pressure test there. The same difficult happened last time on TM4 UCx24# at SHC when leak check. But,it is solved by pressurize |
Tuesday, October 02, 2018, 09:59, Travis Cave, South Hot-Cell, Standard Operation, TM4, UC#24, Module move
|
TM#4 with UC#24 has been moved from the east target station to the south hot cell. |
|