  1768   Monday, August 20, 2018, 09:55 Travis CaveSouth Hot-CellStandard OperationTM2Ta#56 and UC#23Electrical Check

 Electrical Checks of the last two targets Ta#56 and UC#23

  1767   Tuesday, August 14, 2018, 10:27 Travis CaveITWStandard OperationTM2UC#23Module move

 Both the West Entrance and TM#2 with UC#23 have been moved back into their places in the west target station. The Entrance module move wasn't completely smooth as it did suffer a little bumpiness when the shield plug part was installed, I was lifted back out again and no visible damage was observed on the delicate items.

  1766   Tuesday, August 07, 2018, 10:44 Travis CaveSouth Hot-CellMaintenance  Entrance module move

 The west entrance module has been moved from the west target station to the south hot cell, for a bellows replacement.

  1765   Thursday, August 02, 2018, 14:12 Travis CaveSpent Target VaultStandard Operation Nb#8Spent Target Move

 The spent Nb#8 target was moved from the south hot cell to the spent target vault. It was placed in pail #168 and place in spot 2A in the vault. See the attached pdf for vault details.

  1764   Thursday, August 02, 2018, 07:57 David WangConditioning StationStandard Operation  Leak check on TM2 UCx #23 @ TCS and SHC.

I did a helium pressure test on TM2 HS line at TCS. At 70psi helium, the leak rate is 2.5 xE-7 atm.cc/sec. I think this is the number that close to result before which is 1.7xE-9 atm.cc/sec. WE know there is a small leak on this water block seal. Chad  and I did helium  spray check yesterday at SHC. It was good at bottom scale.  No much worry on this low E-7 range leak.

  1763   Wednesday, August 01, 2018, 15:12 Anders MjosSouth Hot-CellStandard OperationTM2UC#23Target mounted - water leak on HS line

The heat shield water lines were not purged ahead of target exchange in the hot cell. This resulted in water leaking onto the new target assembly (heat shield) when the cooling lines were opened at top and bottom (for connecting leak detector). Excess water was wiped up with paper towels.

  1762   Wednesday, August 01, 2018, 14:48 Travis CaveConditioning StationStandard OperationTM2UC#23Spent Target Move

 TM#2 with UC#23 has been moved from the south hot cell to the conditioning station.

  1761   Wednesday, August 01, 2018, 09:47 Isaac EarleNorth Hot-CellDevelopment  NHC diagnostic signals and control panel tested

 On July 30th the NHC diagnostic signals were tested:

- 9 pin CPC: a shorting plug was installed on the hot side - continuity check results were as expected

- 4 pin CPCs:  snake camera installed in both hot side connectors with portable monitor on cold side - both connectors worked as expected

- USB: laptop connected on hot side, USB mouse connected on cold side - worked as expected

- Ethernet: laptop connected on hot side, cold side connected to building ethernet port - connection to network worked as expected

- SHV: a shunt was installed on the hot side - a short circuit was measured from the cold side as expected
            with no shunt installed the line was Megger tested: 1.63 G-ohms recorded @ 1000V

 

The control panel switches for the in-cell receptacles were also tested.  Each switch (a - d) worked as expected.

 

On July 31st the gas supply solenoid valves were tested.  60psi air was hooked to each solenoid inlet.  With the valve closed there was no air flow.  When each push-button or switch was activated air flow was observed through the correct solenoid.

  1760   Tuesday, July 31, 2018, 11:16 Travis CaveSpent Target VaultStandard Operation UC#22Spent Target Move

 Yesterday the spent UC#22 target was moved from the south hot cell to the spent target vault. It was placed in pail #167 and placed in spot 4A see attached PDF for details.

  1759   Tuesday, July 31, 2018, 10:20 Travis CaveSouth Hot-CellStandard OperationTM2Nb#8Module move

 TM#2 with Nb#8 has been moved from ITW to the south hot cell.

  1758   Wednesday, July 25, 2018, 13:21 Anders MjosITWRepairTM2Nb#8Leak check of ITW

ITW Entrance Module was leak checked yesterday with the support of Vacuum Group (Dimo & Edi). The leak detector was connected to primary backing vacuum line. A leak response was found near the bellow for the beam profile monitor on top of the Entrance Module. It could be confirmed today by actuating the monitor, that the leak was indeed at that location. The plan is to move the TM and Entrance Module out for target exchange and repair, respectively. Drawings of the device available on ITA0200and ITA5128

  1757   Monday, July 23, 2018, 10:31 Travis CaveITEStandard OperationTM4Ta#56Module move

 TM#4 with Ta#56 has been moved from the conditioning station to the east target station.

  1756   Thursday, July 19, 2018, 14:22 Isaac EarleNorth Hot-CellDevelopment  NHC diagnostic signals - connector and wiring details

Installation of the diagnostic connections between the NHC hot and cold sides has been completed.  The cable bundle was prepared by Travis Cave in the electronics workshop with connectors attached at one end only.  Metal fish tape was first ran through the conduit from the cold side to hot side, the non-terminated end of the cable bundle was attached to the fish tape inside the cell, cable pulling lubricant was applied, then the cable bundle was pulled through the conduit to the cold side, and the cold side terminations were then made.  For future replacement of the cables and connectors the same method should be used, and a minimum of 6m of cable length.  Connector details can be found on drawings IRH1765 (hot side) and IRH1767 (cold side).  Conduit is 1" trade size PVC type (PO#3041531). Wiring details for each connector are attached below:

 

9 pin CPC connector:

Pin 1: Brown
Pin 2: Red
Pin 3: Orange
Pin 4: Yellow
Pin 5: Green
Pin 6: Blue
Pin 7: Violet
Pin 8: Black
Pin 9: No connection

All wires 14 gauge. 
Connector PN: Amp 211768-1
Cap PN: 208652-1

 

4 pin CPC connectors:

Pin 1: Coax RG-179
Pin 2: Red (18 gauge)
Pin 3: Black (18 gauge)
Pin 4: No connection

Connector PN: Amp 206430-1
Cap PN: 208800-1

 

SHV:

Connector: IRH1769 (customized "Kings 1709-1" connector)

 

USB:

5m long powered USB 3.0 cable
Connector: IRH1770 (customized "TE Connectivity PC4B0100-15NY-1-C" connector)
Cap PN: USBFTV 2 N

 

Ethernet:

Wires installed in the following order when viewing the back side of connector with PN lettering right-side-up:

Blue Blue/White   Orange/White   Orange  
Green/White   Green Brown/White Brown

Connector PN: Tyco 1546877
Cap PN: 208652-1

 


 

  1755   Thursday, July 19, 2018, 09:17 chad fisherSouth Hot-CellRepairTM4 New Optics Tray Modification

The waterline loop bracket has been installed onto the new loop holding bracket and both installed onto the new source tray.

  1754   Wednesday, July 18, 2018, 14:20 chad fisherSouth Hot-CellStandard OperationTM4Ta#56Ta#56 Installed

Ta#56 has been installed onto TM4 with new fasteners. High current fasteners torqued to 130 in lbs.

RIB "shield" has been removed in  preparation for insertion of new optics tray.

  1753   Monday, July 16, 2018, 17:41 Anders MjosITEStandard OperationTM4UC#22Target module disconnected

The water and electrical connections were disconnected today as protons remained off after power interruption during the weekend. Vacuum is still connected and operating.

 The vacuum system are disconnected 2018-07-17.  See attachment .

  1752   Wednesday, July 11, 2018, 15:09 Anders MjosITWMaintenanceTM2Nb#8Uncovered ITW to toubleshoot 2A2M19

The 2A2M19 beam profile monitor did not work and was e-faulted. After initial troubleshooting 2 blocks were removed form ITW to inspect the entrance module where the beam monitor is installed. The cable was found not to be connected and was quickly fixed. Blocks reinstalled. The work was done by Maico, Travis and Anders

  1751   Wednesday, July 11, 2018, 15:06 Anders MjosITWStandard OperationTM2Nb#8Block move

Maico and Travis moved blocks from ITE to ITW yesterday

  1750   Tuesday, July 03, 2018, 14:42 David WangITWStandard OperationTM2Nb#8TM2 has been connected to ITW.

TM2 has been connected to ITW. All turbo pumps are started. See attachment for connection checklist.

  1749   Tuesday, July 03, 2018, 14:38 David WangITWStandard Operation  ITW water signals interlock check.

Annual ITW water signals interlock check are done. Everything works good.