1889
|
Monday, March 11, 2019, 14:34 |
chad fisher | South Hot-Cell | Repair | TM2 | | Water Block Polishing status | Stage 1 polishing (water scale and at least
99% of visual indium removed) has been achieved
on all 2 seal water blocks that will be used |
|
|
1890
|
Tuesday, March 12, 2019, 09:13 |
chad fisher | South Hot-Cell | Repair | TM2 | | Water Block Polishing status | Stage 1 polish has been achieved on all
single seal water blocks using the single
pad tool run at 75 psi, 2 3 minute cycles |
|
|
1891
|
Thursday, March 14, 2019, 10:25 |
chad fisher | South Hot-Cell | Repair | TM2 | | Water Block Polishing status | Phase 2 (intermediate) and Phase 3 (Final)
polishing is complete on all water blocks
on TM2 (minus ground electrode circuit which |
|
|
1895
|
Wednesday, March 20, 2019, 11:19 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | no target | Module move | TM#2 has been moved from the conditioning
station to the south hot cell. |
|
|
1896
|
Thursday, March 21, 2019, 09:56 |
chad fisher | South Hot-Cell | Repair | TM2 | | Tray insertion | This morning new water block fasteners
and gas line capture nut fasteners were inserted
into the hot cell. Window waterline blank |
|
|
1897
|
Monday, March 25, 2019, 10:11 |
Aaron Schmidt | South Hot-Cell | Repair | TM2 | | LP-FEBIAD Test Target (empty) | Link to previous target information: https://elog.triumf.ca/TIS/RH-ISAC/1039
|
|
|
1900
|
Tuesday, March 26, 2019, 11:17 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | no target | Electrical Checks of TM#2 during the source tray change. | The four electrical check done on
TM#2 during the source tray change. |
|
|
1906
|
Friday, April 12, 2019, 11:44 |
chad fisher | South Hot-Cell | Standard Operation | | | Pail transfer | Pail transfer was undertaken in the south
hot cell. went very well except near the
end the master tong cable of the right hand |
|
|
1907
|
Wednesday, April 17, 2019, 12:03 |
chad fisher | South Hot-Cell | Repair | | | Manipulator repair | Broken handle cable of east manipulator
has been replaced and manipulator is operational
again. |
|
|
1908
|
Thursday, April 18, 2019, 10:04 |
Travis Cave | South Hot-Cell | Maintenance | | Ta#50, SiC#34, Ta#46, Ta#47, and Ta#45 | Target transfer from old pail to new pail. | Targets Ta#50 and SiC#34 have been
transferred from their old pails to new ones.
Ta#50 was done on April 12th 2019 it was |
|
|
1909
|
Monday, April 29, 2019, 07:56 |
chad fisher | South Hot-Cell | Development | | | Pail transfers | Two pail transfers took place April 25th.
Ta#47 transfered from pail 137 to
pail 201. existing plastic bag from 137 showed |
|
|
1911
|
Tuesday, April 30, 2019, 08:59 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | UC#26 | Module move | TM#4 with UC#26 has been moved from
ITE to the south hot cell. |
|
|
1912
|
Tuesday, April 30, 2019, 11:19 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | UC#26 | Electrical Check | Electrical check of TM#4 with UC#26
post beam at the south hot cell. See attached. |
|
|
1913
|
Wednesday, May 01, 2019, 07:49 |
chad fisher | South Hot-Cell | Standard Operation | TM4 | UC#26 | UC#26 removal | UC#26 has been removed from TM4. |
|
|
1914
|
Wednesday, May 01, 2019, 09:34 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | no target | Module move | TM#4 has now been moved to the south
west silo. |
|
|
1915
|
Wednesday, May 01, 2019, 10:45 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | no target | Electrical Check | Electrical check of the TM#4 with
no target attached at the south hot cell
before being moved to the south west silo. |
|
|
1917
|
Wednesday, May 08, 2019, 10:29 |
Travis Cave | South Hot-Cell | Standard Operation | | | Entrance module move | The entrance module has been moved
from the west station to the south hot cell. |
|
|
1918
|
Friday, May 10, 2019, 10:23 |
chad fisher | South Hot-Cell | Repair | | | West Entrance module wire scanner replacement | West entrance module - visible broken or
disconnected wire visible on old/existing
wire scanner. Wire scanner removed, new one |
|
|
1922
|
Thursday, May 16, 2019, 12:31 |
chad fisher | South Hot-Cell | Standard Operation | TM2 | Ta#58 | Ta #58 installed | Ta #58 has been installed onto TM2. All
new silver plated high current fasteners.
All torqued to 130 in lbs. |
|
|
1923
|
Thursday, May 16, 2019, 14:35 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | Ta#58 | Electrical Check | Results of the electrical check of
TM#2 without target and with the new Ta#58
target. |
|