ID Date Author Categorydown Type Module Target/Number Subject Text Attachments
  1889   Monday, March 11, 2019, 14:34 chad fisherSouth Hot-CellRepairTM2 Water Block Polishing statusStage 1 polishing (water scale and at least
99% of visual indium removed) has been achieved
on all 2 seal water blocks that will be used
  
  1890   Tuesday, March 12, 2019, 09:13 chad fisherSouth Hot-CellRepairTM2 Water Block Polishing statusStage 1 polish has been achieved on all
single seal water blocks using the single
pad tool run at 75 psi, 2 3 minute cycles
 Blocks_Stage_1_Polish.jpg 
  1891   Thursday, March 14, 2019, 10:25 chad fisherSouth Hot-CellRepairTM2 Water Block Polishing statusPhase 2 (intermediate) and Phase 3 (Final)
polishing is complete on all water blocks
on TM2 (minus ground electrode circuit which
 Blocks_final_polished.jpg 
  1895   Wednesday, March 20, 2019, 11:19 Travis CaveSouth Hot-CellStandard OperationTM2no targetModule move TM#2 has been moved from the conditioning
station to the south hot cell.
  
  1896   Thursday, March 21, 2019, 09:56 chad fisherSouth Hot-CellRepairTM2 Tray insertionThis morning new water block fasteners
and gas line capture nut fasteners were inserted
into the hot cell. Window waterline blank
 20190321_091833.jpg20190321_094625.jpg 
  1897   Monday, March 25, 2019, 10:11 Aaron SchmidtSouth Hot-CellRepairTM2 LP-FEBIAD Test Target (empty) Link to previous target information: https://elog.triumf.ca/TIS/RH-ISAC/1039
 TM2_-_FEBIAD_target_-_Electrical_Test.pdf 
  1900   Tuesday, March 26, 2019, 11:17 Travis CaveSouth Hot-CellStandard OperationTM2no targetElectrical Checks of TM#2 during the source tray change. The four electrical check done on
TM#2 during the source tray change.
 Elecrictal_Check_TM#2_Old_source_Tray_Jan_11_2019.pdfElectrical_Check_TM#2_No_Source_Tray_Feb_25_2019.pdfElectrical_Check_TM#_New_source_Tray_Mar_22_2019.pdfElectrical_Check_TM#2_new_source_tray_Mar_25_2019.pdf 
  1906   Friday, April 12, 2019, 11:44 chad fisherSouth Hot-CellStandard Operation  Pail transferPail transfer was undertaken in the south
hot cell. went very well except near the
end the master tong cable of the right hand
  
  1907   Wednesday, April 17, 2019, 12:03 chad fisherSouth Hot-CellRepair  Manipulator repairBroken handle cable of east manipulator
has been replaced and manipulator is operational
again.
  
  1908   Thursday, April 18, 2019, 10:04 Travis CaveSouth Hot-CellMaintenance Ta#50, SiC#34, Ta#46, Ta#47, and Ta#45Target transfer from old pail to new pail. Targets Ta#50 and SiC#34 have been
transferred from their old pails to new ones.
Ta#50 was done on April 12th 2019 it was
  
  1909   Monday, April 29, 2019, 07:56 chad fisherSouth Hot-CellDevelopment  Pail transfersTwo pail transfers took place April 25th.
Ta#47 transfered from pail 137 to
pail 201. existing plastic bag from 137 showed
 20190425_133750.jpg20190425_134106.jpg 
  1911   Tuesday, April 30, 2019, 08:59 Travis CaveSouth Hot-CellStandard OperationTM4UC#26Module move TM#4 with UC#26 has been moved from
ITE to the south hot cell.
  
  1912   Tuesday, April 30, 2019, 11:19 Travis CaveSouth Hot-CellStandard OperationTM4UC#26Electrical Check Electrical check of TM#4 with UC#26
post beam at the south hot cell. See attached.
 Elec_CHk_UC26_SHC_post_beam.pdf 
  1913   Wednesday, May 01, 2019, 07:49 chad fisherSouth Hot-CellStandard OperationTM4UC#26UC#26 removalUC#26 has been removed from TM4.  20190501_072940[1].jpg 
  1914   Wednesday, May 01, 2019, 09:34 Travis CaveSouth Hot-CellStandard OperationTM4no targetModule move TM#4 has now been moved to the south
west silo.
  
  1915   Wednesday, May 01, 2019, 10:45 Travis CaveSouth Hot-CellStandard OperationTM4no targetElectrical Check Electrical check of the TM#4 with
no target attached at the south hot cell
before being moved to the south west silo.
 TM4_elec_chk_no_tgt_shc_may_1_2019.pdf 
  1917   Wednesday, May 08, 2019, 10:29 Travis CaveSouth Hot-CellStandard Operation  Entrance module move The entrance module has been moved
from the west station to the south hot cell.
  
  1918   Friday, May 10, 2019, 10:23 chad fisherSouth Hot-CellRepair  West Entrance module wire scanner replacementWest entrance module - visible broken or
disconnected wire visible on old/existing
wire scanner. Wire scanner removed, new one
 20190509_085908.jpg20190510_101235.jpg 
  1922   Thursday, May 16, 2019, 12:31 chad fisherSouth Hot-CellStandard OperationTM2Ta#58Ta #58 installedTa #58 has been installed onto TM2. All
new silver plated high current fasteners.
All torqued to 130 in lbs.
  
  1923   Thursday, May 16, 2019, 14:35 Travis CaveSouth Hot-CellStandard OperationTM2Ta#58Electrical Check Results of the electrical check of
TM#2 without target and with the new Ta#58
target.
 Ta#58_TM2_SHC_electrical_chk_May_16_2019.pdfElectrical_Chk_TM2_no_target_May_15_2019_SHC.pdf 