Monday, October 28, 2019, 12:00, Isaac Earle, Safe Module Parking, Development, , , SMP shielding attenuation measured & compared to theoretical values
|
The attenuation of the SMP shielding was measured as part of SMP commissioning (Document-170404, R1, Section 4, Test #8)
The field on the shutter side of TM3 was measured without any shielding as it was removed from a storage silo. At 0.5m from the edge of the
module the maximum field was 5.00mSv. After installation into the SMP the maximum field outside the SMP shielding at 0.5m from the edge of the module |
Monday, October 28, 2019, 11:50, Travis Cave, Spent Target Vault, Standard Operation, , UC#28, Spent Target Move
|
UC#28 has been moved from the south hot cell to spent target storage. The target was placed in pail number 219 and placed in spot 1C of the vault,
it was 12.6mSv/hr upon removal from the south hot cell. Also the spent target vault is now full and can not currently accept anymore targets. |
Friday, October 25, 2019, 06:43, David Wang, Safe Module Parking, Development, TM3, , SMP vacuum
|
TM3 was moved into SMP Oct 25 morning. After two nights pumping down, SMP CG1 read 30mtorr this morning. The pump is stopped. SMP will be
vented soon for TM3 moving back to silo. |
Thursday, October 24, 2019, 14:11, Travis Cave, ITW, Standard Operation, TM4, UC#29, Module move
|
TM#4 with UC29 has been moved from the south hot cell to the west target station. |
Wednesday, October 23, 2019, 07:58, chad fisher, South Hot-Cell, Standard Operation, TM4, UCx#28, UCx#28 Removed
|
UCx#28 has been removed from TM4. Guard screws on 5(10) pin connector had to be removed to get the connector to un-seat properly for removal. |
Wednesday, October 23, 2019, 06:56, David Wang, ITW, Standard Operation, TM4, UCX 28, TM4 UCx 28 disconnection checklist
|
TM4 was disconnected in ITW. See checklist. |
Tuesday, October 22, 2019, 16:26, Isaac Earle, Safe Module Parking, Development, , , SMP shield box grounding
|
A braided grounding strap was attached to the aluminum gear box support on the SMP shield box structure, and grounded by attaching it to the exterior
of an electrical conduit located in the south-west corner of the B2 area at the top of the silo in that corner. The braiding was also connected to
the stainless steel support structure for the SMP vacuum pump. |
Tuesday, October 22, 2019, 11:19, Adam Newsome, South Hot-Cell, Standard Operation, TM4, UC# 28, TM4 Move
|
TM4 with UC# 28 target has been moved from ITW to the South Hot Cell. Shield plug installed in ITW. |
Thursday, October 17, 2019, 11:49, Travis Cave, Spent Target Vault, Standard Operation, , SiC#31,32 and UC#19,20,21, Loading F-308
|
The targets in the mini storage have been loaded into the F-308. |
Tuesday, October 15, 2019, 16:42, Isaac Earle, Safe Module Parking, Development, , , SMP flange alignment tested using shield plug   
|
As a preliminary test in preparation for SMP commissioning, one of the steel module shield plugs was installed into the SMP to check the positional
and rotational alignment procedures. The following is a summary of the steps performed:
Shield plug lifted with crane and rotated to an arbitrary (non-orthogonal) position
Using the crane pendant the shield |
Thursday, October 10, 2019, 16:17, Adam Newsome, Safe Module Parking, Development, , , SMP Main Panel: Relay Addition for E-Stop Circut 
|
An update was made for the E-stop and power supply system in the SMP main panel. Upon testing remote control, it was determined that the Opto 22 AC module
was not sufficiently rated to handle the current draw of the motor (5A fuse versus motor 5.7A current draw). The design was modified so that the E-stop
chain, which supplies 120 VAC line voltage through the main panel E-stop then the remote module (or local pendant when plugged in), will now activate a |
Wednesday, October 09, 2019, 13:28, Travis Cave, Spent Target Vault, Standard Operation, , UC#27, Spent Target Move
|
The spent target in the south hot cell has been moved to the spent target vault. It was placed in spot 1B of the vault in pail number 218. See
attached for vault details. |
Tuesday, October 08, 2019, 09:02, Travis Cave, South Hot-Cell, Standard Operation, TM4, UC#27 and UC#28, Electrical Check  
|
Results of the electrical check of TM4 without target and with UC27 and 28 |
Monday, October 07, 2019, 14:03, David Wang, ITE, Standard Operation, TM2, Ta 59, TM2 has been connected in ITE.
|
Tm2 with Ta 59 has eben connected in ITE. Turbo pumps are started. See checklist |
Monday, October 07, 2019, 09:56, Adam Newsome, ITE, Standard Operation, TM2, Ta 59, TM2 Move
|
TM2 has been moved from the Conditioning Station to ITE with Ta#59 target. |
Friday, October 04, 2019, 16:50, David Wang, South Hot-Cell, Standard Operation, TM4, , UCx 28 target with TM4 SHC leak check and electrical check.
|
TM4 HS Leak check result is good . No leak. electrical check after target installation: Bias to chassis 550 Mohm. Coils are shorted each other and shorted
to 60 KV bias. ABCD to 60KV bias 500V Megga measurement are 100M at least which is good. EE to bias are OL at 500V. The electrical check result is good.
|
Friday, October 04, 2019, 16:43, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 has been connected at TCS.
|
TM2 has been connected at TCS this morning. helium pressure test on Tm2 HS line is done. No leak. |
Friday, October 04, 2019, 14:53, Travis Cave, South Hot-Cell, Standard Operation, TM4, UC#28, Module move
|
TM#4 with UC#28 has been moved from the south hot cell to the west target station. |
Thursday, October 03, 2019, 10:25, Travis Cave, Spent Target Vault, Standard Operation, , ZrC#8, Spent Target Move
|
The spent ZrC#8 was moved from the south hot cell to the spent target vault. It was placed in pail 217 and the pail was placed in slot 3A of the
vault, it was 205mSv/hr when removed from the hot cell. Also the pail was filled with junk stuff that included
wire, a wire scanner, IMG guage, target bolts and a water block bolts. Also there are only two spots left in the vault. |
Wednesday, October 02, 2019, 08:25, chad fisher, South Hot-Cell, Standard Operation, , ZrC#8, ZrC#8 PIE
|
Heat shield has been removed from ZrC#8. |
|