210
|
Thursday, November 08, 2012, 09:37 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | Nb#7 | Nb#7 Autopsy | Nb#7 was dismantled and ready for inspection. |
|
|
221
|
Tuesday, December 04, 2012, 14:20 |
chad fisher | South Hot-Cell | Standard Operation | TM4 | UCx#5 | UCx#5 Removal | UCx #5 has been removed from TM4. The left
oven leg is indeed broken.
Target has been placed in a pail |
|
|
233
|
Thursday, January 17, 2013, 10:06 |
chad fisher | South Hot-Cell | Standard Operation | | | SiC Test Target for TM4/CS | I have inserted the test target for TM4
and the CS into the hot cell.
I had some concerns about the condition |
16x |
|
256
|
Tuesday, March 12, 2013, 09:18 |
chad fisher | South Hot-Cell | Repair | TM4 | | Ground Electrode Leak | On Monday, March 11 the containment box
was removed from TM4 and a vacuum leak check
preformed in an attempt to locate the leak |
|
|
257
|
Wednesday, March 13, 2013, 07:22 |
chad fisher | South Hot-Cell | Repair | TM4 | | Ground Electrode Leak / Inspection Results | Further attempts to localize the leak were
unsucessful. The circuit was pressurized
with 60 psi air and snoop solution was applied |
|
|
258
|
Wednesday, March 13, 2013, 11:23 |
chad fisher | South Hot-Cell | Repair | TM4 | | Ground Electrode Leak | The containment box has been re-installed
and the window waterlines reconnected and
leak checked. |
|
|
282
|
Tuesday, April 02, 2013, 10:07 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | Ta#39 | Ta#39 inserted into hot cell | Ta#39 has been inserted into the hot cell
in preparation for TM1 target change. |
|
|
285
|
Wednesday, April 03, 2013, 13:28 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | Ta#39 | Ta#39 installed | Ta#39 has been installed onto TM1. |
|
|
297
|
Monday, April 15, 2013, 11:00 |
chad fisher | South Hot-Cell | Standard Operation | TM3 | | Items for TM3 dummy target installation | New gaskets and fasteners have been inserted
into the south hot cell in preparation for
installing the dummy target onto TM3 tomorrow. |
|
|
299
|
Tuesday, April 16, 2013, 11:20 |
chad fisher | South Hot-Cell | Repair | TM3 | | TM3 Referb. start | Front containment box cover has been removed
and heat shield circuit blank offs removed
in preparation for installation of dummy |
|
|
300
|
Wednesday, April 17, 2013, 09:02 |
chad fisher | South Hot-Cell | Repair | TM3 | | TM3 ready for conditioning station | The heat shield circuit blank offs have
been re-installed and front cover replaced.
TM3 is ready to move to the conditioning |
|
|
321
|
Wednesday, April 24, 2013, 11:48 |
chad fisher | South Hot-Cell | Repair | TM3 | | TM3 Source Tray Removal | Work on TM3 source tray removal started
at 10:40 am today.
The containment box has been removed, |
|
|
322
|
Wednesday, April 24, 2013, 14:09 |
chad fisher | South Hot-Cell | Repair | TM3 | | TM3 Refurbishment E.O.D. | Optics tray has been removed from module.
Waterblock jig installation has commenced.
Of note, jig installation on TM3 has proven |
|
|
323
|
Friday, April 26, 2013, 11:20 |
chad fisher | South Hot-Cell | Repair | TM3 | | Water Block Jig (back half) | The back half of the water block jig (services
tray side) has been sucessfully located onto
the module. |
|
|
324
|
Friday, April 26, 2013, 14:31 |
chad fisher | South Hot-Cell | Repair | TM3 | | TM3 refurb E.O.D. | Service tray side of the waterblock jig
is installed and all locking tabs enagaed
save the heat shield circuit. Locking tab |
|
|
326
|
Tuesday, April 30, 2013, 07:47 |
chad fisher | South Hot-Cell | Repair | TM3 | | TM3 Source Tray Removal | The source tray has sucessfully been removed
from TM3.
I will put a report in the TM3 rev |
|
|
327
|
Tuesday, April 30, 2013, 07:51 |
chad fisher | South Hot-Cell | Repair | TM3 | | Coil line flow check | David and I checked circuits p and q (the
water cooled coil ciruit) for flow this morning
as, with the source tray still in the module, |
|
|
328
|
Thursday, May 02, 2013, 10:09 |
chad fisher | South Hot-Cell | Repair | TM3 | | Service tray water block leak check | David and I preformed a helium leak check
on the service tray waterblocks and verify
that no damage had been done during jig installation. |
|
|
329
|
Friday, May 03, 2013, 09:53 |
chad fisher | South Hot-Cell | Repair | TM3 | | 9 pin connector wiring | With the aid of nic new manipulator snap
fingers made by Maico the peek cable ties
restraining the 9 pin connector wiring to |
|
|
332
|
Wednesday, May 08, 2013, 10:12 |
chad fisher | South Hot-Cell | Repair | TM3 | | TM3 9 pin wiring removal | The 9 pin wiring has successfully been
removed from TM3. |
|