ID Date Author Category Type Moduledown Target/Number Subject Text Attachments
  332   Wednesday, May 08, 2013, 10:12 chad fisherSouth Hot-CellRepairTM3 TM3 9 pin wiring removalThe 9 pin wiring has successfully been
removed from TM3.
 IMG_1055[1].JPG 
  333   Wednesday, May 08, 2013, 13:48 chad fisherSouth Hot-CellRepairTM3 IMG wiring checkChecks of the wiring for the IMG are complete
and have passed.
  
  335   Thursday, May 09, 2013, 14:23 chad fisherSouth Hot-CellRepairTM3 Water Block Jig RemovalThe source tray side of the water block
jig has been removed in preparation for moving
the module to the  conditioning station
 IMG_1059[1].JPG 
  336   Friday, May 10, 2013, 09:26 chad fisherSouth Hot-CellRepairTM3 Containment box reinstalledthe containment box has been reinstalled
onto TM3. After electrical checks it is ready
to move to the conditioning station...for
 IMG_1062[1].JPGIMG_1063[1].JPG 
  337   Friday, May 10, 2013, 11:02 Travis CaveSouth Hot-CellStandard OperationTM3no targetmodule moveTM#3 with no target and no source tray
has been moved from the south hot cell to
the conditioning station.
  
  338   Friday, May 10, 2013, 11:11 Travis CaveSouth Hot-CellStandard OperationTM3no targetElectrical checkTM#3 electrical check with no target and
no source tray, see pdf.
 TM#3_elec_chk_no_tgt_no_tray.PDF 
  339   Friday, May 10, 2013, 11:28 Bevan MossConditioning StationStandard OperationTM3No Source TrayRoughing Started Roughing on TM3 was started at 11:26am
today
  
  340   Friday, May 10, 2013, 14:05 Bevan MossConditioning StationStandard OperationTM3No Source TrayTurbo Pumps OnThe turbo pumps are on. TP1 and TP2 once
again timed out and had to be restarted before
they would stay on.
  
  341   Monday, May 13, 2013, 14:59 Bevan MossConditioning StationStandard OperationTM3N/AEL testing

    

       
            
 TM3_EL_39.9kV_23042013.txt 
  342   Monday, May 13, 2013, 15:10 Bevan MossConditioning StationStandard OperationTM3N/AHV Test All common

    

       
            
 TM3_40kV_22042013.xlsx 
  344   Wednesday, May 15, 2013, 10:17 Bevan MossConditioning StationStandard OperationTM3No Source TrayPreliminary Results from HV testing Testing on TM3 without a source tray
was completed on 13/05.2013. All items were
tied to common and the water blocks were
 module_hv_test_0KV.rgaMODULE_hv_test_42kv.rgaTM3_13052013_no_source_tray.xlsx 
  348   Wednesday, May 15, 2013, 16:51 Bevan MossConditioning StationStandard OperationTM3No Source TrayRepeat of HV Test The HV test completed on Monday was
repeated today over a much longer time period.
By taking longer there was slightly less
 150502013_TM3_No_Source_Tray.xlsx 
  349   Wednesday, May 15, 2013, 17:32 Bevan MossConditioning StationStandard OperationTM3 TM3 in place but not connected To confirm that the sparking was
coming from the module rather than the conditioning
station TM3 was grounded and the conditioning
 15052013_TM3_in_place_but_not_connected.xlsx 
  350   Wednesday, May 15, 2013, 18:12 Bevan MossConditioning StationStandard OperationTM3No source trayHV test repeat After discussion with Friedhelm it
was decided to continue trying to condition
the module today before moving it tomorrow.
 15052013_TM3_HV_test_repeat.xlsx 
  352   Friday, May 17, 2013, 12:02 Travis CaveConditioning StationStandard OperationTM3 module moveTM#3 with no target or source trays has
been moved from the conditioning station
to the NE silo.
  
  354   Tuesday, May 21, 2013, 11:52 Bevan MossConditioning StationStandard OperationTM3No Source TrayMay 16th Long HV conditioningOn May 16th 2013 the module was HV conditioned
all day. As a result the maximum stable voltage
has been increased to about 47kV (~4kV more
 16052013_TM3_long_HV_conditioning.xlsx 
  378   Thursday, June 13, 2013, 09:18 chad fisherSouth Hot-CellRepairTM3 Source Tray/Extraction Column RemovalTM3 Rev 2 source tray/extraction column
insertion into its storage was completed
yesterday and it was then removed from the
  
  380   Tuesday, June 18, 2013, 14:00 chad fisherSouth Hot-CellDevelopmentTM3 Mock-up testing / water block connectionsThe testing of the mock-up and tooling
has commenced.
Source tray mock-up has been driven
  
  381   Wednesday, June 19, 2013, 08:15 chad fisherSouth Hot-CellDevelopmentTM3 Mock up water block connectionsAll water block connections on the mock-up
have bben achieved. It is now ready for leak
checking.
 20130619_080806[1].jpg20130619_080808[1].jpg 
  383   Friday, June 21, 2013, 09:26 chad fisherSouth Hot-CellDevelopmentTM3 Mock-up Leak Check ResultsThe Mock-up has been leak tested after
the remote connection of the water blocks
and is leak tight!
  