Entry  Monday, September 30, 2019, 11:27, Isaac Earle, Safe Module Parking, Development, , , SMP vacuum vessel modifications completed 

The SMP vacuum vessel welds were reinforced to match the specifications on IRH1710 Rev D.  In addition a tube stub was added on the side of the vessel for installation of a PRV.  The relief valve installed was Accu-Glass 113150, with 2psi setpoint (not the MDC 420036 model specified on IRH1710 Rev D).  The drawing will be updated to reflect this.

Welding was performed in the TRIUMF machine shop.  A larger capacity forklift was rented to move the vessel back and forth between the shop and the Meson Hall loading bay where the main crane was used to flip the vessel between welds.

After welding the vessel was leak checked using a blank-off plate (helium leak tight).  The vessel was then returned to the Target Hall, the top flange IRH1755 was re-installed, and the TCS shield plug was installed on the flange.  The vessel was pumped down over the weekend using the SMP vacuum pump, and reached 8mTorr by Monday morning.  A helium leak check was performed in the Target Hall:  baseline leak rate 0.0E-9 atm-cc/sec, 0.0E-4Torr port pressure, no response to generous helium spray on PRV and around both seal locations for the top flange.

Remaining re-assembly of the SMP will now proceed.

Entry  Monday, September 23, 2019, 13:21, Travis Cave, Spent Target Vault, Standard Operation, , , Repacking of the targets. Target_Index_2019-09-23_Mini_Vault.pdf

 All targets in the mini vault have been repackaged and are now ready to be loaded into F-308s. All the target pails have new numbers see attached sheet for details.

Entry  Thursday, September 19, 2019, 10:11, Travis Cave, Spent Target Vault, Standard Operation, , , Repacking of the targets. 

 Another target in the mini storage has been repackaged into the new pails. With one remaining to do which will be done on Monday.

Entry  Wednesday, September 18, 2019, 14:28, Travis Cave, Spent Target Vault, Standard Operation, , , Repacking of the targets. 

 Three of the five targets in the mini storage have been repackaged into the stronger pail.

Entry  Tuesday, September 17, 2019, 07:37, Carla Babcock, ITE, Development, TM2, ZrC#8, end of run HV investigations HVtests_TM2_Sept172019.xlsx

Ramping up HV to ~30kV, encountered problems and had to drop back to 28kV. No response on IG1 or anything else during sparks. Lots of charging-type behaviour on the bias current. Protons at 55uA

Tuesday, September 17, 2019, 02:02 : 15 mins with only 1 spark at 30kV so increased the bias

Tuesday, September 17, 2019, 02:31 : 32kV. Current unstable

Tuesday, September 17, 2019, 02:41 : Current continues extremely unstable but not much sparking....

Tuesday, September 17, 2019, 02:53 : Proton beam trip initially settled the bias current down, but then current began climbing pretty steeply with protons still off

Tuesday, September 17, 2019, 03:28 : Protons dropped to 40uA from 55uA, Bias current is much more stable and no sparks for 25mins

Tuesday, September 17, 2019, 03:36 : Raising voltage easy to about 33.5kV then instability and sparking similar to around 31kV at 55uA p+

Tuesday, September 17, 2019, 04:45 : Lowered protons to 25uA and no sparks though the current is not stable

More things but forgot to write them down. Spreadsheet attached.

Entry  Friday, September 13, 2019, 13:36, David Wang, ITW, Standard Operation, TM4, UCX27, TM4 conenction in ITW checklist TM4_UCx27_connection_checklist.pdf

TM4 was connected in ITW this Tuesday. See attachment for checklist.

Entry  Thursday, September 12, 2019, 09:26, David Wang, ITW, Repair, TM4, , ITW bad vacuum issue and trouble shoot. 

ITW secondary vacuum was bad in last two days after TM4 was connected in ITW. Today when check the exit 2 module, I found a small needle valve on exit 2 module top was slightly opened for some reason in past months. The valve is closed . ITW vacuum is returned to normal status.

Entry  Tuesday, September 10, 2019, 14:04, David Wang, ITW, Standard Operation, , , ITW water interlock check. 

ITW water interlock check is finished. Everything is good.

Entry  Tuesday, September 10, 2019, 10:10, Adam Newsome, ITW, Standard Operation, TM4, UC#27, TM4 Move 

TM4 has been moved from the Conditioning Station to ITW with UC#27 target.

Entry  Tuesday, September 10, 2019, 08:25, David Wang, Conditioning Station, Standard Operation, TM4, UCx27, Argan vent TCS. 

TCS is argon vented. TM4 is disconnected at TCS.

Entry  Monday, September 09, 2019, 06:38, David Wang, Conditioning Station, Standard Operation, TM4, UCx27, HS and window line leak check. 

TM4 HS and window line are helium pressure checked at TCS. 70 psi helium 5 minutes. No response @1.2XE-8 atm.cc/sec. They are leak free.

Entry  Thursday, September 05, 2019, 14:26, Travis Cave, South Hot-Cell, Standard Operation, TM4, UC#27, Electrical Check TM4_elec_chk_with_UC27_at_SHC_Sept_5_2019.pdf

 The results of the electrical check of TM#4 with UC#27 attached to it.

Entry  Thursday, September 05, 2019, 14:26, Travis Cave, South Hot-Cell, Standard Operation, TM4, UC#27, Electrical Check TM4_elec_chk_with_UC27_at_SHC_Sept_5_2019.pdf

 The results of the electrical check of TM#4 with UC#27 attached to it.

Entry  Thursday, September 05, 2019, 14:18, Adam Newsome, South Hot-Cell, Standard Operation, TM4, UCx#27, TM4 Move 

TM4 with UCx#27 target has been moved from the South Hot-Cell to the Conditioning Station.

Entry  Thursday, September 05, 2019, 11:37, chad fisher, South Hot-Cell, Standard Operation, TM4, UCx#27, UCx#27 install 

Dummy Ta target has been removed from TM4 and UCx#27 installed

Entry  Wednesday, September 04, 2019, 13:53, chad fisher, South Hot-Cell, Repair, TM4, , TM3 CB to TM4 

The TM3 containment box has been installed onto TM4. No issues, leak checked ok.

 

Entry  Tuesday, September 03, 2019, 10:49, Adam Newsome, South Hot-Cell, Standard Operation, TM4, , TM4 Move 

TM4 has been moved from the Conditioning Station to the South Hot-Cell.

Entry  Tuesday, September 03, 2019, 10:48, Adam Newsome, South Hot-Cell, Standard Operation, TM3, , TM3 Move 

TM3 has been moved from the South Hot-Cell to the Middle-East silo.

Entry  Thursday, August 29, 2019, 12:54, Adam Newsome, South Hot-Cell, Standard Operation, TM3, , TM3 Move 

TM3 has been moved from the Middle-East silo to the South Hot Cell.

Entry  Tuesday, August 27, 2019, 13:12, Adam Newsome, Safe Module Parking, Development, , , SMP Remote Control Wiring Inspection 

The wiring for the SMP remote control module was inspected by Joel Semilla (TRIUMF electrician). The module was plugged in to verify there were no issues. No changes were suggested, and then wiring was approved.