Wednesday, April 23, 2025, 14:08, Adam Newsome, North Hot-Cell, Standard Operation, TM4, , TM4 Module Move
|
TM4 was moved from Safe Module Parking to the North Hot Cell today. |
Thursday, April 24, 2025, 11:13, Frank Song, North Hot-Cell, Standard Operation, TM4, UCx#48, electrical check/leak check
|
TM4 with new target UCx#48 installed was E/L checked on the top of NHC, see attachment uploaded with pls. |
Thursday, April 24, 2025, 12:53, Aaron Tam, North Hot-Cell, Standard Operation, TM4, UC#48, UC#48 IGLIS Install onto TM4 
|
C. Fisher, A. Schmidt, A. Tam
UC#48 Handover satisfactory
Target taken out of glovebox and tested for fit
The left most triplet conductor leg was seen to be slightly misaligned, |
Thursday, May 01, 2025, 09:33, Travis Cave, ITE, Standard Operation, TM4, UC#48, Module move
|
TM#4 with UC#48 went from the conditioning station to the east target station. |
Tuesday, May 06, 2025, 09:18, Frank Song, ITE, Standard Operation, TM4, UCx#48, Module Connection
|
TM4 with first target UC#48 of this year has been connected in ITE. see attachment please. |
Wednesday, May 14, 2025, 09:45, Frank Song, 5 Shielding Blocks, Standard Operation, TM4, UC#48 IGLIS, shielding blocks transfer
|
5 shielding blocks have been transferred to ITE from storage area, the WP#I2025-05-14-2. |
Tuesday, June 17, 2025, 11:32, Adam Newsome, North Hot-Cell, Standard Operation, TM4, UC#48, Module move
|
TM#4 with UC#48 was moved from the East target station to the North Hot Cell for target exchange.
Reading at ITE = 36 mSv/h
Reading at NHC = 133 mSv/h |
Tuesday, June 17, 2025, 11:58, Frank Song, ITE, Standard Operation, TM4, UC#48, module disconnection
|
TM4 with spent target UC#48 was disconnected ang moved from ITE to NHC. see attachment pls. |
Tuesday, June 17, 2025, 12:59, Frank Song, North Hot-Cell, Standard Operation, TM4, C#5, electrical check/leak check
|
TM4 with new target number C#5 installed had been leak/electric checked on NHC flange in TH. see pic attached with pls. |
Wednesday, June 20, 2012, 11:39, Grant Minor, South Hot-Cell, Development, TM3, N/A, TM3 Planned Activites at South Hot Cell Jun 20 to 29 2012
|
Normal
0
false
false
false
EN-CA
X-NONE
X-NONE
|
Thursday, June 21, 2012, 14:00, Travis Cave, South Hot-Cell, Repair, TM3, no target, module move
|
TM#3 has been moved from the south west silo to the south hot cell for the start of its second refurb/repair. The fields of the module when it was lowed
in was 2msv/hr. |
Thursday, June 21, 2012, 14:30, chad fisher, South Hot-Cell, Repair, TM3, N/A, TM3 Refurbishment Start
|
Started refurb of TM3.
Planned activities:
Inspection |
Thursday, June 21, 2012, 14:33, chad fisher, South Hot-Cell, Repair, TM3, N/A, Pictures TM3 June 21st 8x
|
Here are the pictures from today...there is video too but it is not uploaded yet. |
Monday, June 25, 2012, 07:53, chad fisher, South Hot-Cell, Repair, TM3, N/A, TM3 Refurb. Work
|
On Friday, June 22 the following work was carried out.
Further inspection of the source tray.
Testing of existing tray removal and installation tool...it works fine, there was
just a specific method for proper coupling to the target module. There was no documentation for this tool, so it took a little bit of insight with |
Tuesday, June 26, 2012, 14:10, David Wang, South Hot-Cell, Repair, TM3, , TM3 heat shield and window circuits leak check is done.
|
Chad and i did a leak check on TM3 heat shield and window circuits.Both circuits are pumped easily down to the bottom leak rate and base pressure on
the leak detector. There are two VCR caps on heat shield circuit. Chad sprayed helium on both of them ( tested individually,2 seconds every time
) . There is no response on leakdetecor during 45 seconds waiting time. On window circuit there are 2 VCR joints. Chad sprayed helim on these joints(2seconds |
Monday, April 15, 2013, 11:00, chad fisher, South Hot-Cell, Standard Operation, TM3, , Items for TM3 dummy target installation
|
New gaskets and fasteners have been inserted into the south hot cell in preparation for installing the dummy target onto TM3 tomorrow. |
Tuesday, April 16, 2013, 11:10, Travis Cave, South Hot-Cell, Standard Operation, TM3, no target, module move
|
TM#3 has been moved from the NE Silo to the south hot cell, move went well. |
Tuesday, April 16, 2013, 11:20, chad fisher, South Hot-Cell, Repair, TM3, , TM3 Referb. start 
|
Front containment box cover has been removed and heat shield circuit blank offs removed in preparation for installation of dummy target.
image #1 - initail view after front panel removal.
image #2 - Heat shield circuit blank offs removed. |
Wednesday, April 17, 2013, 09:02, chad fisher, South Hot-Cell, Repair, TM3, , TM3 ready for conditioning station
|
The heat shield circuit blank offs have been re-installed and front cover replaced. TM3 is ready to move to the conditioning station for testing. |
Wednesday, April 17, 2013, 09:26, Travis Cave, South Hot-Cell, Standard Operation, TM3, no target, Electrical check 
|
Electrical check was performed on TM#3 with no target nothing was wrong was found, but our megger does not go above 1000 volts so any problems above
this value would not be seen, see attached pdf for details.
Also the 55 pin(top) double 9 pin (bottom) connector was tested as well. When it was meggered to 60kV common more then 50% of the lines failed, |
|