ID |
Date |
Author |
Category |
Type |
Module |
Target/Number |
Subject |
|
1236
|
Tuesday, May 17, 2016, 11:47 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | UC#15 | module moved |
TM#1 has been moved from the west target to the south hot cell. The target on TM#1 is UC#15. |
|
1238
|
Wednesday, May 18, 2016, 11:42 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | UC#15 | module moved |
TM#1 with UC#15 has been moved from the west target station to the south hot cell. The target shield plug was also remotely installed as well. |
|
1239
|
Thursday, May 19, 2016, 10:35 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | no target | module moved |
TM#1 has been moved from the south hot cell to the north west silo. |
|
1247
|
Tuesday, May 31, 2016, 09:45 |
Travis Cave | South Hot-Cell | Standard Operation | TM3 | no target | module moved |
TM#3 has been moved from the NE Silo to the south hot cell. |
|
1248
|
Thursday, June 02, 2016, 08:44 |
Travis Cave | South Hot-Cell | Standard Operation | TM3 | no target | Electrical Check |
Electrical check of TM#3 no target at the south hot cell. see attached for results. |
Attachment 1: TM3_elec_chk_no_tgt.PDF
|
|
|
1249
|
Thursday, June 02, 2016, 11:59 |
David Wang | South Hot-Cell | Repair | TM3 | | 5K mega test on TM3 |
I did a 5KV mega test on TM3. Only5Mohm @5kV between coli line PQ and chassis(ground). It confirmed the close gap between P,Q and GE. Other lines are ok. See attachment. |
Attachment 1: 5K_mega_check_on_TM3.pdf
|
|
|
1250
|
Thursday, June 02, 2016, 18:04 |
Aurelia Laxdal | South Hot-Cell | Repair | TM3 | | 5K mega test on TM3 |
David Wang wrote: |
I did a 5KV mega test on TM3. Only5Mohm @5kV between coli line PQ and chassis(ground). It confirmed the close gap between P,Q and GE. Other lines are ok. See attachment.
|
See attachment for sparking signs of the water lines mentioned above (Coil and Ground Electrode lines) in TM3 Source Tray. |
Attachment 1: DSC_0821.JPG
|
|
Attachment 2: DSC_0822.JPG
|
|
|
1251
|
Friday, June 03, 2016, 11:35 |
Travis Cave | South Hot-Cell | Standard Operation | TM3 | no target | module moved |
TM#3 has been moved back to the north east silo. |
|
1252
|
Friday, June 03, 2016, 16:04 |
Aurelia Laxdal | South Hot-Cell | Repair | TM3 | | 5K mega test on TM3 |
Aurelia Laxdal wrote: |
David Wang wrote: |
I did a 5KV mega test on TM3. Only5Mohm @5kV between coli line PQ and chassis(ground). It confirmed the close gap between P,Q and GE. Other lines are ok. See attachment.
|
See attachment for sparking signs of the water lines mentioned above (Coil and Ground Electrode lines) in TM3 Source Tray.
|
PLEASE NOTE: the resistance values for A and B on David's attachment are not correct since these measurements were done after Chad removed the target and the heat-shield bracket was moved, so consequently the water lines were not at their nominal locations. Once they were back in plac,e David took another measurement and the resistance values for A and B showed also 3,000 MOhm (as it was for most of the lines). The only lines that still showed a low resistance were the Coil lines. |
|
1255
|
Tuesday, June 07, 2016, 11:42 |
David Wang | South Hot-Cell | Standard Operation | TM4 | Ta#47 | electrical check on TM4 with old Ta target at SHC. |
I did an electrical check on TM4 with the old target still installed. The number is a little bit low on 500V mega check between chassis and 60KVbias which is 146Mohm. Others are good. See attachment
I wrote all OL to 0 in attachment 1 ohmmeter check. Please See attachment 2 for correction. |
Attachment 1: electrical_check_2016-06-07._TM4_with_old_Lp_Ta_target..pdf
|
|
Attachment 2: electrical_check_2016-06-07._TM4_with_old_Lp_Ta_target..pdf
|
|
|
1273
|
Wednesday, July 06, 2016, 09:16 |
chad fisher | South Hot-Cell | Standard Operation | TM2 | SiC#33 | Ta#48 removed SiC#33 installed |
Ta#48 has been removed from TM2 and SiC#33 installed. |
|
1274
|
Wednesday, July 06, 2016, 09:59 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | Ta#48 and SiC#33 | Electrical Check |
Electrical check done on TM#2 with Ta#48, no target and SiC#33 the short on the coils to 60kV is still present it is on the R-U coil line. See attached PDFs for details. |
Attachment 1: TM2_elechk_Ta48_SHC_postbeam.PDF
|
|
Attachment 2: TM2_elechk_SiC33_SHC.PDF
|
|
Attachment 3: TM2_elechk_notgt_SHC.PDF
|
|
|
1287
|
Monday, July 18, 2016, 13:56 |
Travis Cave | South Hot-Cell | Standard Operation | TM3 | no target | module moved |
TM#3 is now in the south hot cell. |
|
1292
|
Tuesday, July 26, 2016, 11:22 |
chad fisher | South Hot-Cell | Maintenance | | | Soth Hot Cell Waste Storage Vault Tunnel |
The two 45 gal (m) drums of waste removed from the south hot cell in December 2015 and January 2016 were transferred from the north hot cell to the shaft of the east vault tunnel on Monday, July 25th 2016 and subsequently to the east tunnel bunker in the vault tunnel on Tuesday, July 26th, 2016.The first drum (removed from the hot cell in December) containing both activated and contaminated metals was measured at 900 uSv/hr @ .5 m and the second drum (removed from the hot cell in January 2016) containing compressible items such as tank suits and plastic was measured at 150 uSv/hr @ .5 m.
Items were filed for storage/disposal with RPG under item number 1395 on the radioactive storage form.
Drums were transported to the vault tunnel using the 500 Mev Shield Flask (Drawing E-7097) with some minor modifications, namely a 1/4" thick Aluminum plate with four holes that line up with the holes in the bottom flange of the flask. This plate provided a bottom for the flask so that a drum could be contained within the flask during craning. Holes in the plate where countersunk for a 1/2" flat head bolt. Four bolts were also modified to accept 3/16 hair pins. 3 plates with clearances holes for the bolts were also manufactured to act as washers.
Procedure was as follows: With plate, washers and pins installed onto the flask, a modified drum dolly (5" spacers added to the casters) was placed inside the flask. Drum was craned into the flask using the automatic drum lifter. Flask with drum loaded was moved to the Meson Hall loading bay then craned to the B2 level of the Meson hall. Hair pins were pulled from the flask and the flask was then craned up leaving the drum (which was on the dolly firstly installed into the flask) and the plate. Drum on dolly was rolled to vault access shaft where it was craned off the modified dolly using the automatic drum lifter and down the access shaft to the vault tunnel level. A second drum dolly was waiting at the bottom level and drum lowered onto it. Procedure was repeated for the second drum
Was vault was open , drums were wheeled into the vault tunnel and into a bunker that had been modified to accept these drums. Drums were lifted off dollies and put in place in bunker which had blocks installed to cover the entrance provided for installation.
Pictures can be found on docushare http://documents.triumf.ca/docushare/dsweb/View/Collection-18072 (collection 18072)
|
|
1296
|
Tuesday, August 02, 2016, 13:32 |
chad fisher | South Hot-Cell | Standard Operation | TM4 | UC#16 | UC#16 Removed #17 installed |
UCx#16 has been removed from TM$ and UCx#17 installed, high current conductors toqued to 130 in lbs.
UCx#16 did not show the standard arcing marks on the 9 pin connector.
In regards to the 9 pin connector on number 17, it was by far the best fitting TM4 target with 9 pin as it required no "fiddling" during installation. |
|
1297
|
Tuesday, August 02, 2016, 14:52 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | UC#17 | module moved |
TM#4 with UC#17 is now in the conditioning station. |
|
1300
|
Wednesday, August 03, 2016, 09:15 |
chad fisher | South Hot-Cell | Repair | | | Manipulator |
East manipulator on the south hot cell is showing signs of eminent wrist/tong cable failure. Some slight slippage was noted yesterday and confirmed by a snapping sound and more slippage tomorrow. |
|
1304
|
Wednesday, August 03, 2016, 10:02 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | UC#17 | Electrical Check |
The result of yesterdays electrical check on TM#4 with UC#17. |
Attachment 1: TM4_elechk_UC17_SHC.PDF
|
|
|
1306
|
Friday, August 05, 2016, 13:50 |
chad fisher | South Hot-Cell | Maintenance | | | Anteroom clean out |
Some items have been removed from the anteroom in preparation for painting. Items have been placed on plastic in the south hot cell service area. No contamination found so far. |
|
1308
|
Monday, August 08, 2016, 11:24 |
chad fisher | South Hot-Cell | Maintenance | | | Anteroom Clean-up - Waveguide |
The wave guide from TM3 has been surveyed, swiped and removed from the anteroom and transported to rad waste for disposal. The wave guide has been stored in the anteroom since its removal. |