1075
|
Tuesday, September 22, 2015, 13:15 |
David Wang | South Hot-Cell | Standard Operation | | Ta#46 | Leak check on TM4 HS water line with new Ta#46 target. at SHC | Chad and I leak checked the HS line at
SHC. No leak. Leak rate 0.0xE-9atm.cc/sec. |
|
|
1083
|
Friday, September 25, 2015, 08:21 |
Travis Cave | South Hot-Cell | Standard Operation | | UC#13 | Spent Target move | The spent UC#13 target has been moved from
the south hot cell to the ISAC spent target
vault. It was placed pail #128 and in tray |
|
|
1087
|
Wednesday, September 30, 2015, 08:50 |
Travis Cave | South Hot-Cell | Maintenance | TM3 | no target | Module moved | TM#3 is in the south hot cell it was moved
from the north west silo. |
|
|
1088
|
Wednesday, September 30, 2015, 11:14 |
Travis Cave | South Hot-Cell | Repair | TM3 | no target | Electrical Check | TM#3 electrical check at the south hot
cell, no target, all value are done at 1000Volts.
See the attached PDF for the results. |
|
|
1095
|
Tuesday, October 06, 2015, 21:12 |
Aurelia Laxdal | South Hot-Cell | Repair | TM3 | | TM3 service cap inspection in target hall | David Wang and I did the service cap inspection
in target hall: see WP I2015-10-06-10.<br>
Signs of sparking were seen underneath |
|
|
1096
|
Thursday, October 08, 2015, 14:08 |
David Wang | South Hot-Cell | Standard Operation | TM3 | Dummy target febiad. | TM3 has been moved from SHC to NW silo | Bill and I moved TM3 from SHC to NW silo
with a dummy febiad target installed on it.
The move is smooth. |
|
|
1100
|
Wednesday, October 14, 2015, 12:48 |
David Wang | South Hot-Cell | Standard Operation | TM2 | ZrC#7 | TM2 ZrC#7 after run electrical check at SHC. | I did an electrical check on TM2 with ZrC
#7 on it. The EE is short to 60KV bias. See
attachment |
|
|
1101
|
Wednesday, October 14, 2015, 14:03 |
chad fisher | South Hot-Cell | Standard Operation | TM2 | ZrC#7 | ZrC#7 removed | ZrC#7 has been removed from TM2. Everything
looks good. |
|
|
1102
|
Wednesday, October 14, 2015, 14:49 |
David Wang | South Hot-Cell | Standard Operation | TM2 | | Install new high current cables to TM2 | I installed a set of new high current cables
for TM2 Febiad run. The top of TM2
is configured to Febiad mode. See attachments |
|
|
1103
|
Thursday, October 15, 2015, 08:07 |
David Wang | South Hot-Cell | Standard Operation | TM2 | no target | TM2 no target electrical check at SHC. | I did a TM2 no target electrical check
at SHC this morning. A to RU at 500v
is 250K which is low. anode- |
|
|
1104
|
Thursday, October 15, 2015, 14:17 |
chad fisher | South Hot-Cell | Repair | TM2 | | Anode Connector Install and adjustment | The TM2 containment box was removed this
morning for installation of the 9 pin connector...connection.
The 9 pin connector copper tube connection |
|
|
1105
|
Monday, October 19, 2015, 11:53 |
chad fisher | South Hot-Cell | Standard Operation | TM2 | SiC#32 | SiC#32 installed on TM2 | SiC#32 has been installed on TM2. High
current fasteners torqued to 130 in lbs. |
|
|
1106
|
Monday, October 19, 2015, 15:52 |
Anders Mjos | South Hot-Cell | Standard Operation | TM2 | SiC#32 | Electrical and leak check | An electrical check was completed
by Travis C and Anders M. Note ~250 kOhm
between Target and 60 kV common. Leak check |
|
|
1109
|
Tuesday, October 20, 2015, 13:52 |
chad fisher | South Hot-Cell | Maintenance | | | TM4 Febiad coil line disposal | The febiad coil line removed from TM4 has
been cut into pieces small enough to be disposed
of in a 5 gal pal. The line was cut with |
|
|
1110
|
Wednesday, October 21, 2015, 09:49 |
chad fisher | South Hot-Cell | Repair | | | Manipulator handle repair | Rebuild handle of manipulator serial 7986
(currently in the east position) and replaced
broken snap ring 5555-18h on west side of |
|
|
1111
|
Wednesday, October 21, 2015, 11:58 |
Anders Mjos | South Hot-Cell | Development | TM2 | ZrC#7 | Extraction Electrode inspection | The failed extraction electrode was inspected
in the hot cell this morning by Anders and
Chad. The following electrical measurements |
|
|
1113
|
Friday, October 23, 2015, 11:30 |
chad fisher | South Hot-Cell | Standard Operation | | ZrC#7 | ZrC#7 Spent Move and Febiad Coil | ZrC#7 was transfered to a spent target
disposal pail today and removed from the
hot cell. The "hot" end of the |
|
|
1129
|
Tuesday, November 24, 2015, 13:54 |
chad fisher | South Hot-Cell | Repair | | | Cell Decon | Decon/removal of large solid waste was
performed on Wednesday November 18th."Hot"
activated items included containment box |
|
|
1130
|
Tuesday, November 24, 2015, 14:00 |
chad fisher | South Hot-Cell | Repair | | | Compressible waste sorting. | Residual fields from the remaining compressible
waste were still too high (as far as I'm
concerned) so I have unpacked all compressible |
|
|
1131
|
Tuesday, November 24, 2015, 14:02 |
chad fisher | South Hot-Cell | Repair | | | Left Manip repair | electronics package on left manip died
completely yesterday (it has been going for
a while). |
|