ID |
Date |
Author |
Category |
Type |
Module |
Target/Number |
Subject |
Text |
|
2372
|
Monday, October 03, 2022, 14:58 |
Matthew Gareau | North Hot-Cell | Repair | TM4 | SiC#43 and C#4 | Loose multipin guide pin | Today while I was removing the SiC#43
it was noticed that the multipin guide pin
was loose. |
|
2373
|
Tuesday, October 04, 2022, 07:19 |
Frank Song | North Hot-Cell | Standard Operation | TM4 | C#4 | electrical check | an electrical was done for TM4 with
target C#4 installed on NHC. |
|
2374
|
Wednesday, October 05, 2022, 09:31 |
David Wang | Conditioning Station | Standard Operation | TM4 | C#4 | HS line helium pressure test. TM4 with C#4 at TCS. | TM4 HS line helium pressure test is done.
70psi helium pressure@ 3XE-8 atm.cc/sec .
No leak. |
|
2376
|
Tuesday, October 11, 2022, 12:39 |
Frank Song | ITE | Standard Operation | TM4 | C#4 | Module Connection | TM4 with Target C#4 was connected
in ITE. |
|
2378
|
Monday, October 17, 2022, 08:07 |
David Wang | ITE/ITW | Repair | TM4 | | A small leak on target station secondaryvacuum back up line by ITH MP1S. |
A small leak in target station |
|
2379
|
Wednesday, October 19, 2022, 12:00 |
Carla Babcock | North Hot-Cell | Standard Operation | TM4 | SiC#44 | PIE on SiC#44 | Conducted PIE on SiC#44, which failed online.
It had a cathode short, a target short and
an anode short by the time we called the |
|
2388
|
Tuesday, November 22, 2022, 09:44 |
Frank Song | ITE | Standard Operation | TM4 | C#4 | module disconnection | TM4 with C#4 was disconnected in ITE |
|
2389
|
Tuesday, November 22, 2022, 10:37 |
Adam Newsome | North Hot-Cell | Standard Operation | TM4 | | TM4 Move - ITE to NHC | TM4 was moved from ITE to NHC with C#4.
|
|
2390
|
Tuesday, November 22, 2022, 12:41 |
Frank Song | North Hot-Cell | Standard Operation | TM4 | C#4 | electrical check | TM4 with C#4 is checked on NHC
right after moving from ITE. |
|
2391
|
Tuesday, November 22, 2022, 14:53 |
Carla Babcock | North Hot-Cell | Maintenance | TM4 | | Multipin connector alignment pin on TM4 module loose | The pin on TM4 has become loose again,
making it very difficult to remove the multipin
connector with the last target, C#4. For |
|
2392
|
Wednesday, November 23, 2022, 11:27 |
Frank Song | North Hot-Cell | Standard Operation | TM4 | UCx#41 | electric and leak check after new target installed | an electric check and leak check
done on NHC, TM4 with new target UCx#41 is
ready moving to TCS. |
|
2393
|
Wednesday, November 23, 2022, 12:10 |
Adam Newsome | Conditioning Station | Standard Operation | TM4 | UCx#41 | TM4 Move - NHC to TCS | TM4 was moved from the North Hot Cell to
the Target Conditioning Station with UCx#41.
|
|
2394
|
Thursday, November 24, 2022, 11:32 |
Adam Newsome | Spent Target Vault | Standard Operation | TM4 | C#4 | C#4 Spent Target Moved to Storage Vault | C#4 spent target was moved to the storage
vault, in pail 277. Dose rate at approximately
1 m when leaving the hot cell was 164 mSv/h. |
|
2395
|
Tuesday, November 29, 2022, 11:03 |
Adam Newsome | ITE | Standard Operation | TM4 | C#4 | TM4 Move - TCS to ITE | TM4 was moved from the Conditioning Station
to the East Target Station with C#4. |
|
2396
|
Thursday, December 01, 2022, 08:20 |
Frank Song | ITE | Standard Operation | TM4 | UCx#41 | Module Connection | TM4 with UCx#41 was connected in
ITE on Tuesday (2022-11-29) |
|
2397
|
Thursday, December 01, 2022, 13:45 |
Carla Babcock | North Hot-Cell | Standard Operation | TM4 | C#4 | Post irradiation inspection C#4 | Post irradiation inspection of C#4 which
was running in TM4/ITE was conducted at the
NHC on Nov. 22 2022. |
|
2405
|
Tuesday, January 24, 2023, 07:17 |
David Wang | ITE | Standard Operation | TM4 | UCx#41 | TM4 water lines helium pressure test 2023. | TM4 water lines helium pressure test was
done yesterday at ITE. All water lines were
air purged one day ahead for the test. |
|
2408
|
Tuesday, January 24, 2023, 08:46 |
David Wang | ITE | Standard Operation | TM4 | UCx#41 | TM4 has been disconnected in ITE. | TM 4 has been disconnected in ITE.
See attachment for disconnection checklist. |
|
2409
|
Tuesday, January 24, 2023, 14:22 |
David Wang | South Hot-Cell | Standard Operation | TM4 | UCx#41 | TM4 electrical check with and without target at SHC | TM4 electrical check with UCX41target and
without target at SHC. The results
are good. See attachment. |
|
2410
|
Wednesday, January 25, 2023, 06:52 |
David Wang | ITE | Standard Operation | TM4 | UCx#41 | ITE primary and secondary vacuum vessel air to vacuum seals leak check. | ITE primary and secondary vacuum vessel
air to vacuum seals leak check was done this
week. One leak has been found on IG1S feed |
|