ID Date Author Categorydown Type Module Target/Number Subject Text Attachments
  776   Monday, November 03, 2014, 11:16 chad fisherSouth Hot-CellStandard OperationTM1ThO#1ThO#1 InstalledThO#1 has been installed onto TM1 and is
ready for leak and electrical checking. High
current fasteners torqued to 130 in lbs.
  
  777   Monday, November 03, 2014, 13:47 Travis CaveSouth Hot-CellStandard OperationTM1ThO#1Electrical checkTM#1 with ThO#1 electrical check see attatched
PDF for details.
 TM1_elec_check_ThO1_SHC.PDF 
  778   Tuesday, November 04, 2014, 11:05 David WangSouth Hot-CellStandard OperationTM1ThO#1Leak check on TM1 HS water line withThO#1 installed.Chad and I leak checked HS line on TM1
with ThO#1 target installed. The LD pumped
down to base leak rate 0.0xE-9 atm.cc/sec,
  
  779   Tuesday, November 04, 2014, 13:17 chad fisherSouth Hot-CellStandard OperationTM1ThO#1TM1 w/ ThO#1 readyTm1 with ThO#1 is buttoned up and ready
for transport.
  
  780   Wednesday, November 05, 2014, 10:20 Travis CaveSouth Hot-CellStandard OperationTM1ThO#1module moveTM#1 with ThO#1 has been moved from the
south hot cell to the west target station.
  
  789   Monday, November 17, 2014, 13:45 chad fisherSouth Hot-CellRepair  Jig for roof install of targetJig for installation of target through
hot cell roof has been assembled and placed
in the target hall.
 Target_roof_install_20141117_01.jpgTarget_Roof_install_Jig_20141117_02.jpgTarget_roof_install_20141117_03.jpgTarget_roof_install_20141117_04.jpg 
  790   Tuesday, November 18, 2014, 10:28 Travis CaveSouth Hot-CellStandard OperationTM4Ta#44module moveTM#4 with Ta#44 has been moved from the
east target station to the south hot cell.
  
  791   Tuesday, November 18, 2014, 11:14 David WangSouth Hot-CellStandard Operation UCx11crane down UCx 11 target into SHC from THI craned down UCx11 target from TH into
SHC. Chad was in SHC service area watching
on it. The source tray moving jig was installed
  
  793   Wednesday, November 19, 2014, 08:49 chad fisherSouth Hot-CellStandard OperationTM4UCx#11Ta#44 Removed Ucx#11 InstalledTa#44 has been removed from TM4 and UCx#11
has been installed and is ready for testing.
New fasteners were installed for
  
  794   Wednesday, November 19, 2014, 09:18 Travis CaveSouth Hot-CellStandard OperationTM4UC#11Electrical checkTM#4 with UC#11 electrical check done.
See attached PDF for the results.
 TM4_elec_check_UC11_SHC.PDF 
  800   Tuesday, November 25, 2014, 11:33 David WangSouth Hot-CellDevelopment  Remove UCX 11 target transfer stand from SHC back to TH.The stand was used for transferring UCX11
targte from TH to SHC. The stand wit target
was craned down from TH into SHC last week
  
  803   Friday, November 28, 2014, 13:06 Travis CaveSouth Hot-CellStandard OperationTM2no targetmodule moveTM#2 with no target or source tray has
been moved from the north east silo to the
south hot cell.
  
  805   Monday, December 01, 2014, 14:06 chad fisherSouth Hot-CellRepairTM2 TM2 REFURB. WATER LOOP TESTSome issues with the turntable and having
to wait for a decision on whether to remove
TM2 from the hot cell so that TM4 with dead
 TM2_20141201_01.JPGTM2_20141201_02.JPGTM2_20141201_03.JPGTM2_20141201_04.JPGTM2_20141201_05AC.jpg 
  807   Tuesday, December 02, 2014, 10:15 chad fisherSouth Hot-CellRepairTM2 TM2 Reburb. Loop InstallFinal polish, clean with methanol and clean
compressed air.
Loop installed and torqued to 90
 TM2_20141202_01.jpg20141203_142215.jpg20141203_143530.jpg 
  808   Tuesday, December 02, 2014, 13:33 David WangSouth Hot-CellDevelopmentTM2 Leak check on TM2 tube heater +(D) at SHCChad and I leak checked TM2 tube heater+(D)
circuit at SHC with water bypass loop and
new seals installed on the water block. The
 2014-12-02_003.JPG2014-12-02_001.JPG2014-12-02_004.JPG 
  810   Thursday, December 04, 2014, 09:54 Travis CaveSouth Hot-CellStandard OperationTM2no targetElectrical checkResults of electrical check of TM#2 with
no source tray and no containment box attached.
See PDF for results.
 TM2_elec_check_no_source_traySHC.PDF 
  831   Thursday, January 08, 2015, 10:34 chad fisherSouth Hot-CellStandard Operation  TM2 Tray Build Status and ProblemsFinal assembly of the source tray for TM2
was started this morning.
Sliding tray was received from keensert
 TM2_Tray_20150108_09.jpgTM2_Tray_20150108_10.jpgTM2_Tray_20150108_11.jpgTM2_Tray_20150108_12.jpg 
  833   Monday, January 12, 2015, 14:29 chad fisherSouth Hot-CellRepairTM2 TM2 Tray Build StatusCountersink problem with supports has been
remedied. Scratches, dings, and pitting has
been buffed out and supports re-cleaned and
 TM2_Tray_20150112_01.jpg 
  834   Tuesday, January 20, 2015, 13:45 chad fisherSouth Hot-CellRepairTM2 TM2 Tray AlignmentTM2 Tray Alignment is complete except for
verification with alignment tray.
First attempt results were:
 TM2Alignment_Target_Front_Jan_20.jpgTM2_Alignment_Target_Rear_Jan_20.jpg 
  835   Monday, January 26, 2015, 09:36 chad fisherSouth Hot-CellRepairTM2 TM2 Tray AlignmentTM2 tray alignment was confirmed with the
alignment tray this morning:
Front target 0.000 vertically, 0.000
 TM2_Tray_20150126_090448.jpg 