Entry  Tuesday, November 04, 2014, 13:17, chad fisher, South Hot-Cell, Standard Operation, TM1, ThO#1, TM1 w/ ThO#1 ready 

Tm1 with ThO#1 is buttoned up and ready for transport.

Entry  Wednesday, November 05, 2014, 10:20, Travis Cave, South Hot-Cell, Standard Operation, TM1, ThO#1, module move 

TM#1 with ThO#1 has been moved from the south hot cell to the west target station.

Entry  Monday, November 17, 2014, 13:45, chad fisher, South Hot-Cell, Repair, , , Jig for roof install of target Target_roof_install_20141117_01.jpgTarget_Roof_install_Jig_20141117_02.jpgTarget_roof_install_20141117_03.jpgTarget_roof_install_20141117_04.jpg

Jig for installation of target through hot cell roof has been assembled and placed in the target hall.

Entry  Tuesday, November 18, 2014, 10:28, Travis Cave, South Hot-Cell, Standard Operation, TM4, Ta#44, module move 

TM#4 with Ta#44 has been moved from the east target station to the south hot cell.

Entry  Tuesday, November 18, 2014, 11:14, David Wang, South Hot-Cell, Standard Operation, , UCx11, crane down UCx 11 target into SHC from TH 

I craned down UCx11 target from TH into SHC. Chad was in SHC service area watching on it. The source tray moving jig was installed on the crane for this moving.

Entry  Wednesday, November 19, 2014, 08:49, chad fisher, South Hot-Cell, Standard Operation, TM4, UCx#11, Ta#44 Removed Ucx#11 Installed 

Ta#44 has been removed from TM4 and UCx#11 has been installed and is ready for testing.

New fasteners were installed for all mounting and current connections.

High current fasteners were torqued to 130in lbs.

Entry  Wednesday, November 19, 2014, 09:18, Travis Cave, South Hot-Cell, Standard Operation, TM4, UC#11, Electrical check TM4_elec_check_UC11_SHC.PDF

TM#4 with UC#11 electrical check done. See attached PDF for the results.

Entry  Tuesday, November 25, 2014, 11:33, David Wang, South Hot-Cell, Development, , , Remove UCX 11 target transfer stand from SHC back to TH. 

The stand was used for transferring UCX11 targte from TH to SHC. The stand wit target was craned down from TH into SHC last week and stayed there over weekend. Chad and I removed the stand out of SHC yesterday. It was heavily contaminated. RPG and I spent more than 3 hours to clean this stand. See the emails I pasted below for  detail information.

Thanks, David, for letting me know about this. Here are survey results after my afternoon in Target Hall:

I spent 1.5 hours on additional decon of the stand, crane hook, and area around where David was doing the decon, finding up to 10k cpm (44-2) on some parts at first. Danka came to help after a bit (THANK YOU, DANKA) and we left the items covered in plastic and surveyed the area. Contamination survey results are as follows, numbers are units of cpm on the 44-2/RM14:

Tacky mats inside TMH door: 6000/2000

Tacky mats in hall before TMH door: 200/0

Tacky mats at boot box: 8000/4000

My booties: 50/0

Air sample at the decon area: 50/60 (also 100 cpm on alpha probe)

Floor swipes post-decon of floor: 0/0

Early results from a 10 min assay of the tacky mats shows predominantly Kr-85, Be-7, Sr-85, Rb-83, and Sr-82. A longer assay is underway.

The following measurements were made using the checking cave at the boot box (units of cpm):

David's respirator cartridges: 160

David's respirator: 0

Davids tank suit and booties: 1200

My suit: 100

My respirator: 0

The rags used for the decon work were contained in a bag and left behind the silos by the DST. This bag measured 240 uSv/h OC and 2 uSv/h at 0.5m

Thanks,

Andrew

 

On 11/24/2014 12:57 PM, David Wang wrote:

Hi all, The UCx#11 target transferring stand is moved back from SHC to TH. However, the stand was heavily contaminated. On the first Windex clean up towel, the counts directly shoot over the 500K counts which is the maximum scales on both RM14 and 44-2. After almost 2 hours, more than 20 times cleaning up with Windex spray and paper towel wipe , the counts dropped below 300 now. It is extremely difficult to clean up this stand.  I dont think we should move the target this way again unless we have a solution on the contamination clean up. The stand is still hanging  on the crane, and waiting for RPG checking.                        Thanks    David

Entry  Friday, November 28, 2014, 13:06, Travis Cave, South Hot-Cell, Standard Operation, TM2, no target, module move 

TM#2 with no target or source tray has been moved from the north east silo to the south hot cell.

Entry  Monday, December 01, 2014, 14:06, chad fisher, South Hot-Cell, Repair, TM2, , TM2 REFURB. WATER LOOP TEST TM2_20141201_01.JPGTM2_20141201_02.JPGTM2_20141201_03.JPGTM2_20141201_04.JPGTM2_20141201_05AC.jpg

Some issues with the turntable and having to wait for a decision on whether to remove TM2 from the hot cell so that TM4 with dead UCx target could be put in this morning.

Progress on TM2:

  • Containment box has been removed from TM2.
  • Water block jig has been installed.
  • Existing blank off has been removed.
  • Sealing surfaces have been inspected.
  • First stage of sealing surface cleaning has been performed.

Tomorrow:

  • Polish of sealing surfaces.
  • Installation of loop.
  • Vacuum/helium leak check of loop.

TM2_20141201_03 - sealing surfaces before cleaning...kind of dirty

TM2_20141201_05AC - sealing surfaces after cleaning...looks good!

Entry  Tuesday, December 02, 2014, 10:15, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Reburb. Loop Install TM2_20141202_01.jpg20141203_142215.jpg20141203_143530.jpg

Final polish, clean with methanol and clean compressed air.

Loop installed and torqued to 90 in lbs.

Minimum of approximately 1"  between loop and containment box at closest point.

Entry  Tuesday, December 02, 2014, 13:33, David Wang, South Hot-Cell, Development, TM2, , Leak check on TM2 tube heater +(D) at SHC 2014-12-02_003.JPG2014-12-02_001.JPG2014-12-02_004.JPG

Chad and I leak checked TM2 tube heater+(D) circuit at SHC with water bypass loop and new seals installed on the water block. The LD base LR 0.0xE-9 atm.cc/sec,base pressure0.0xE-4 torr. Chad sprayed helium on the leak check area in SHC for 5 seconds. No any response has been found on LD during 1minutes waiting time. The test was repeated again and the result is same. NO LEAK at this stage!  After the TM2 is moved to CS , The D line will be pressured with 80 psi helium for helium pressure leak test before any hot water is circuited through it.  

Entry  Thursday, December 04, 2014, 09:54, Travis Cave, South Hot-Cell, Standard Operation, TM2, no target, Electrical check TM2_elec_check_no_source_traySHC.PDF

Results of electrical check of TM#2 with no source tray and no containment box attached. See PDF for results.

Entry  Thursday, January 08, 2015, 10:34, chad fisher, South Hot-Cell, Standard Operation, , , TM2 Tray Build Status and Problems TM2_Tray_20150108_09.jpgTM2_Tray_20150108_10.jpgTM2_Tray_20150108_11.jpgTM2_Tray_20150108_12.jpg

Final assembly of the source tray for TM2 was started this morning.

Sliding tray was received from keensert installation and cleaned.

Mounting plate/ionizer tube location jig was rechecked against assembly ITA3136...Mounting plate was loosened, jigs for centering the ceramic shields installed and fasteners re-torqued to 57 in lbs.

Upon attempted assemble of ITA3536 and 3537 (support frames) it was noticed that the countersinks were not deep enough...the heads of the screws protrude and would interfere with/damage the support insulators. These items have been given to Dan to have the counterbores adjusted...drawing should be changed to insure a small gap.

Also, one of the support frames has marks on its side that may be a high voltage issue.

Upon inspection of the components in question (ITA3540 & 3538) it was found that they have been made to spec and model; however the spec& model does not allow for adequate theoretical clearance given tolerances. Countersinks will be adjusted and changes documented.

"Pitting" will attempt to be lapped.

 

Entry  Monday, January 12, 2015, 14:29, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Tray Build Status TM2_Tray_20150112_01.jpg

Countersink problem with supports has been remedied. Scratches, dings, and pitting has been buffed out and supports re-cleaned and re-assembled.

Friedhelm was consulted regarding the appearance of fine scratches on the main stand-off insulators...the best two matching ones were chosen and assembly continued.

Alignment will start tomorrow.

 

 

Entry  Tuesday, January 20, 2015, 13:45, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Tray Alignment TM2Alignment_Target_Front_Jan_20.jpgTM2_Alignment_Target_Rear_Jan_20.jpg

TM2 Tray Alignment is complete except for verification with alignment tray.

First attempt results were:

Front Target: Low 0.011, Left 0.011

Rear Target: Low 0.013, Left 0.002

Final iteration:

Front Target: Vertical 0, Horizontal 0

Rear target: Vertical - 0.003 low, Horizontal 0

Pictures were very hard to get but are below...camera is impossible to get square to lens so pictures are not entirely representative of looking through transit.

 

Entry  Monday, January 26, 2015, 09:36, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Tray Alignment TM2_Tray_20150126_090448.jpg

TM2 tray alignment was confirmed with the alignment tray this morning:

Front target 0.000 vertically, 0.000 horizontally.

Back target 0.003 low, 0.000 horizontally

Also, the master target jig was installed and measurements taken:

Front master target - 0.007 high, 0.000 left/right

Rear Master Target - 0.007 high, 0.000 left/right

Rear tray target - 0.003 low

 

Entry  Thursday, January 29, 2015, 11:31, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Tray Build TM2_Tray_20150126_112232.jpg

On Tuesday morning I attempted to complete assembly of the source tray for TM2 however discovered that 3 1/4-20 x 0.25 titanium helicoils had not been installed into the mounting plate as they should have been. Checked and asked around for them but to no avail. I have ordered some, they should have been here yesterday.

Also, I have noticed that the threaded portion of the target pins ITA0328A appear to be too long and as such may be (are indeed) touching the supports. I am going to remove 1/32" or appropriate to remedy this problem (drawing shows 0.035 clearance).

Entry  Monday, February 02, 2015, 09:59, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Tray Build 

Missing heli coils installed this morning.

Threads had to be chased with tap for 1/4-20 heli coil and missing countersinks hand applied to allow for installation. Care was taken to ensure no "swarf" was spread and operation was super clean. Chased holes blown out with canned air and a vacuum placed on the other side.

Final assembly can and will now continue.

Entry  Monday, February 02, 2015, 14:06, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Tray build TM2_Tray_20150202_134752.jpgTM2_Tray_20150202_134759.jpg

Master target jig installed to locate attachment bracket ITA3389 as well as conductor insulator block b (aluminum / for soldering version) and oven conductor blocks (ITD0353 and 03356). 

There were NO ITA6145 fasteners or TGN0076 either. Standard 1/4-20 x 1" fasteners have been used in there place for now. Keith is following up with getting the missing fasteners into the shop.

Oven conductor blocks will have to be lapped before lines are attached as they both have dents on the high current mating surfaces.

 

 

 