Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  RH-ISAC, Page 22 of 138  Not logged in ELOG logo
ID Date Author Categorydown Type Module Target/Number Subject Text Attachments
  524   Thursday, October 24, 2013, 11:32 Travis CaveSouth Hot-CellStandard OperationTM4no targetmodule moveTM#4 with no target has been moved from
the conditioning station to the south hot
cell.
  
  525   Thursday, October 24, 2013, 15:43 Anders MjosSouth Hot-CellStandard OperationTM4Ta#41Target conductanceThe conductance check on the electrical
check was found to be outside of accepted
values for the TBHT at 7.0 mOhm. A successful
 Ta#41_electrical_measurement_TGHT_in_SHC.pdf 
  526   Thursday, October 24, 2013, 15:54 Grant MinorSouth Hot-CellStandard OperationTM4Ta#41Target conductance

    

       
            
  
  527   Friday, October 25, 2013, 06:58 David WangSouth Hot-CellStandard OperationTM4 Leak check on TM4 target heat shieldMaico and I leak checked HS circuit after
Chad installed the target. The circuit was
a little bit difficult o pump down because
  
  530   Friday, October 25, 2013, 14:09 Travis CaveSouth Hot-CellStandard OperationTM4Ta#41Target conductance

    

       
            
 TM#4_Ta#41_elec_test_SHC.PDF 
  533   Friday, November 01, 2013, 09:08 Travis CaveSouth Hot-CellStandard OperationTM2no targetmodule moveTM#2 has been moved from the north west
silo to the south hot cell. The module has
a field of about 3.1mSv/hr when it was lowered
  
  534   Monday, November 04, 2013, 10:46 chad fisherSouth Hot-CellRepairTM2 TM2 ExplorationTM2 is now in the hot cell with the containment
box off for inspection and eventual blank
off off the water blocks.
 TM2_20131104.jpg 
  535   Tuesday, November 05, 2013, 10:37 chad fisherSouth Hot-CellRepairTM2 Thermocouple wire removalThe old thermocouple wire has been sucessfully
removed from the module.
Thanks Bevan, Travis and David.
  
  536   Wednesday, November 06, 2013, 10:41 David WangSouth Hot-CellRepairTM2 Installed 2 turbopumps on TM2Bevan and I installed 2 turbo pumps on
TM2. The o- ring flanges on TM2 had been
cleaned before the installation.
  
  538   Tuesday, November 12, 2013, 10:59 Bevan MossSouth Hot-CellStandard OperationTM2 Electrical Test Don Jackson and Myself completed
started an electrical test on TM2. All lines
passed the with OL to ground. When testing
 tm2_elec_test.pdf 
  543   Thursday, November 14, 2013, 08:08 chad fisherSouth Hot-CellRepairTM2 TM2 Blank off and jig removalFirday, November 8 all water blocks (excluding
I and K) were blanked off and vacuum leak
checked. No responses were found. (First
 TM2_20131108.jpgTM2_20131112.jpg 
  548   Tuesday, November 19, 2013, 10:52 Travis CaveSouth Hot-CellStandard OperationTM3NiO#2module moveTM#3 with NiO#2 moved from ITE to the south
hot cell.
  
  551   Wednesday, November 20, 2013, 08:50 chad fisherSouth Hot-CellStandard OperationTM3NiO#2NiO#2 removedNiO#2 has been removed from TM3  TM3_20131120.jpgTM3_20131120_2.jpg 
  552   Wednesday, November 20, 2013, 09:52 Travis CaveSouth Hot-CellStandard OperationTM3no targetmodule moveTM#3 with no target has been moved from
the south hot cell to the north east silo.
  
  554   Thursday, November 21, 2013, 12:12 Anders MjosSouth Hot-CellStandard OperationTM3NiO#2End of beam target inspection - ANODE does not hold 250VThe target was inspected by Chad and Anders
in the Hot Cell. Electrical megger tests
were done during the assembly. It was found
  
  556   Monday, November 25, 2013, 11:48 Travis CaveSouth Hot-CellStandard OperationTM3no targetmodule moveTM#3 with no target has been moved from
the north east silo to the south hot cell.
  
  558   Wednesday, November 27, 2013, 12:50 Bevan MossSouth Hot-CellStandard OperationTM3 Ground devices wiring check Travis and I completed an electrical
check on the wiring harness for the devices
on the ground plane. All lines passed 500V
  
  559   Wednesday, November 27, 2013, 15:24 Bevan MossSouth Hot-CellMaintenanceTM3 Wiring Harness Electrical Test Maico removed the containment box
today allow Travis and I to further test
the wiring harness. I disconnected the junction
 IMG_1269.JPG 
  560   Friday, November 29, 2013, 11:54 chad fisherSouth Hot-CellRepairTM3 Steerer short investegationUsing in cell camera and transit the suspect
line on the steerers was inspected as best
as possible. An existing photo of the complete
 TM3_20131129_Steerer_1.jpgTM3_20131129_Steerer_2.jpgTM3_20131129_Steerer_3.jpg 
  561   Friday, November 29, 2013, 11:57 Bevan MossSouth Hot-CellRepairTM3 Steerer short investegation

    

       
            
  
ELOG V2.9.2-2455