ID Date Authordown Category Type Module Target/Number Subject Text Attachments
  1872   Wednesday, February 20, 2019, 09:07 chad fisherSouth Hot-CellRepairTM2 Module side waterblock jigI have installed the module side water
block jig.
  
  1874   Friday, February 22, 2019, 10:31 chad fisherSouth Hot-CellRepairTM2 TM2 Source tray removalThe source tray has been removed from TM2.  6x 
  1875   Monday, February 25, 2019, 09:44 chad fisherSouth Hot-CellRepairTM2 Water block jigmodule side water block jig has been removed
in preparation for electrical checks.
  
  1876   Tuesday, February 26, 2019, 08:51 chad fisherSouth Hot-CellRepairTM2 TM2 containment boxThe containment box has been reinstalled
onto TM2 in prepatation for testing in the
conditioning station.
  
  1879   Friday, March 01, 2019, 09:57 chad fisherSouth Hot-CellRepairTM2 TM2 Source tray removalTM4 optics tray was installed onto the
old TM2 source tray yesterday and tray filled
with non-active metal scrap. Tray inserted
 20190228_095131.jpg20190228_143718.jpg20190301_074849.jpg20190301_092907.jpg 
  1882   Tuesday, March 05, 2019, 09:38 chad fisherSouth Hot-CellRepair  Transfer Fixture RepairTransfer fixture has been remotely disassembled
to the point where the ball nut lock plate
assembly can be inserted into the tool port
 20190305_092228.jpg20190305_092231.jpg20190305_092326.jpg20190305_092558.jpg 
  1883   Tuesday, March 05, 2019, 14:29 chad fisherSouth Hot-CellRepair  Tray Transfer Fixture Repair CompleteRepair of the tray transfer fixture is
complete (minus testing).
A distorted ball nut lock plate was
 20190305_130312.jpg20190305_132303.jpg20190305_133800.jpg20190305_141346.jpg 
  1885   Thursday, March 07, 2019, 12:02 chad fisherSouth Hot-CellRepairTM2 Box Off water block jig onThe containment box has been removed from
TM2 and the water block jig installed in
preparation for water block polishing.
 20190307_113548.jpg 
  1886   Thursday, March 07, 2019, 12:20 chad fisherSouth Hot-CellRepairTM2 Pre-polishing picturesPictures of the water blocks before polishing
can be found on docushare, collection 24400
  
  1887   Thursday, March 07, 2019, 13:59 chad fisherSouth Hot-CellRepairTM2 PolishingPolishing of the water block sealing surfaces
has commenced. First attempt was on block
B with low nap brown polishing pad (the least
  
  1888   Friday, March 08, 2019, 14:10 chad fisherSouth Hot-CellRepairTM2 Water block polishingAfter trials with 2000 grid wet paper I
have moved up to "red" scotch brite.
This seems to have worked the best so far
 B_after_SB_(2).jpg 
  1889   Monday, March 11, 2019, 14:34 chad fisherSouth Hot-CellRepairTM2 Water Block Polishing statusStage 1 polishing (water scale and at least
99% of visual indium removed) has been achieved
on all 2 seal water blocks that will be used
  
  1890   Tuesday, March 12, 2019, 09:13 chad fisherSouth Hot-CellRepairTM2 Water Block Polishing statusStage 1 polish has been achieved on all
single seal water blocks using the single
pad tool run at 75 psi, 2 3 minute cycles
 Blocks_Stage_1_Polish.jpg 
  1891   Thursday, March 14, 2019, 10:25 chad fisherSouth Hot-CellRepairTM2 Water Block Polishing statusPhase 2 (intermediate) and Phase 3 (Final)
polishing is complete on all water blocks
on TM2 (minus ground electrode circuit which
 Blocks_final_polished.jpg 
  1896   Thursday, March 21, 2019, 09:56 chad fisherSouth Hot-CellRepairTM2 Tray insertionThis morning new water block fasteners
and gas line capture nut fasteners were inserted
into the hot cell. Window waterline blank
 20190321_091833.jpg20190321_094625.jpg 
  1905   Friday, April 05, 2019, 13:44 chad fisherSpent Target VaultDevelopment  2019 Pail drop tests
    Drop test performed January
8, 2019 with 25 lb target, UN pail and lug
cover. Drop failed. Lug cover half removed.
  
  1906   Friday, April 12, 2019, 11:44 chad fisherSouth Hot-CellStandard Operation  Pail transferPail transfer was undertaken in the south
hot cell. went very well except near the
end the master tong cable of the right hand
  
  1907   Wednesday, April 17, 2019, 12:03 chad fisherSouth Hot-CellRepair  Manipulator repairBroken handle cable of east manipulator
has been replaced and manipulator is operational
again.
  
  1909   Monday, April 29, 2019, 07:56 chad fisherSouth Hot-CellDevelopment  Pail transfersTwo pail transfers took place April 25th.
Ta#47 transfered from pail 137 to
pail 201. existing plastic bag from 137 showed
 20190425_133750.jpg20190425_134106.jpg 
  1913   Wednesday, May 01, 2019, 07:49 chad fisherSouth Hot-CellStandard OperationTM4UC#26UC#26 removalUC#26 has been removed from TM4.  20190501_072940[1].jpg 