ID Date Author Category Type Module Target/Number Subject
  7   Tuesday, July 19, 2011, 12:02 Travis CaveSouth Hot-CellStandard OperationTM4Ta#36Electrical check

See attached PDF for the details.

Attachment 1: TM#4_SIS_Elec_Check2.pdf
TM#4_SIS_Elec_Check2.pdf
  6   Tuesday, July 19, 2011, 11:52 chad fisherSouth Hot-CellStandard OperationTM4Ta#36New target Ta#36 Installed on TM4

Ta#36 has been installed on TM4 and is awaiting leak and electrical check.

A small piece of the standard top insulator ITA3376 broke off during removal of Ta#35 (indicated with a blue circle on attached pictures).

"JP's connector, ITA2493 showed the usual and as yet undiagnosed "arc" mark (picture to follow).

The plastic retainers on the new torqtite gaskets showed rad damage.

Attachment 1: DSC_0897.JPG
DSC_0897.JPG
Attachment 2: DSC_0899.JPG
DSC_0899.JPG
Attachment 3: DSC_0901.JPG
DSC_0901.JPG
Attachment 4: DSC_0905.JPG
DSC_0905.JPG
  5   Tuesday, July 19, 2011, 11:17 Travis CaveSouth Hot-CellStandard OperationTM4Ta#35Move of TM#4 from East target station to south hot cell.

Move went well no problems readings at East Target Station were very high at 500mSv/hr.

  4   Thursday, June 30, 2011, 16:04 Pierre BricaultConditioning StationRepairTM1 TM1 status

Friday June 24 2011

The target module has been moved to the Conditioning Station (CS)

Pumping overnight

Saturday June 25 2011

Pressure Service Cap (SC) 3E-6 T

Pressure Containment Box (CB) 6.6E-6 T

High voltage test to 40 kV, unfortunately, the pressure is not great so we stop at 40 kV

Pressure at the end of the day: 1650H was, P SC 2.6E-6T

P CB 6.6E-6 T

Sunday June 26 2011

Pressure P SC 1.6E-6T

P CB 6.6E-6 T

It seems we have a leak. The pressure does not drop in the CB over one day.

Today June 27 2011

 Pressure P SC 1.2E-6T

P CB 6.6E-6 T

We leak check the target module and found two leaks, one on the ground electrode and one on the mounting plate cooling circuit.

This is a new one. We had test this line three times before and it was ok.

Action for tomorrow.

After CS vent, 

Move TM1 to SHC

Survey 

Connect LD to Mounting plate cooling circuit

Open Side panel and leak check.

Meeting at 0830H