2454
|
Monday, June 12, 2023, 07:36 |
David Wang | Conditioning Station | Standard Operation | | | TCS water filters annual change. | Plant group changed TCS water filters last
Friday. 4 filters on resin can inet /outlet
sides and filters(4 in one cartridge house)on |
|
2475
|
Wednesday, August 09, 2023, 13:13 |
David Wang | Conditioning Station | Standard Operation | TM2 | Nb#10 | Tm2 Nb#10 has been connect at TCS. | TM2 Nb#10 has been connect at TCS. TCS
water system and vacuum system have been
started. Everything looks ok so far. TCS |
|
2510
|
Friday, December 15, 2023, 11:07 |
Adam Newsome | Conditioning Station | Standard Operation | TM3 | | TM3 Move - SHC to TCS | TM3 was moved from the SHC to the TCS (no
target installed). |
|
2513
|
Tuesday, January 02, 2024, 16:01 |
Carla Babcock | Conditioning Station | Development | TM3 | | TM3 service tray HV testing and conditioning | Tuesday, January 02, 2024, 15:58 :
Started HV ramp up on TM3 service
tray about 3pm today. Had to bypass TCS:BIAS |
 |
2520
|
Thursday, January 11, 2024, 13:54 |
David Wang | Conditioning Station | Development | TM3 | | TM3 servic cap air to vacumm seals leak check. | After Tm3 service tray and service cap
installation, TM3 service cap air to vacuum
seals leak check has been done at TCS. TCS:IG1 |
|
2563
|
Tuesday, April 16, 2024, 12:33 |
David Wang | Conditioning Station | Standard Operation | | | test TCS water system chillers stage in/out. | Monday and Tuesday, I started TCS water
system and enabled the TCS chillers auto
stage in/out. I saw chiller 2 in/out three |
|
2567
|
Wednesday, April 24, 2024, 10:15 |
David Wang | Conditioning Station | Standard Operation | TM3 | | TM3 has been moved from SHC to TCS. | TM3 has been moved from SHC to TCS.
The move is smooth. |
|
2568
|
Friday, April 26, 2024, 08:56 |
David Wang | Conditioning Station | Development | TM3 | | TM3 module top helium spray leak test. | TM3 module top helium spray leak test was
done yesterday. No leak on TM3 module
top @ LD base leak rate 0.0 x E-9 atm.cc/sec. |
|
2569
|
Friday, April 26, 2024, 08:59 |
David Wang | Conditioning Station | Development | TM3 | | TM3 helium pressure test and electrical check with new source tray at TCS. | TM3 helium pressure test and electrical
check with new source tray at TCS were done
yesterday. The results are excellent. See |
|
2571
|
Saturday, April 27, 2024, 09:35 |
Carla Babcock; Alexander Shkuratoff | Conditioning Station | Development | TM3 | | TM3 source and service tray testing | Saturday, April 27, 2024, 09:35 :
Started ramping up HV, EE and EL
together. First small spark at 20.5kV on |
|
2578
|
Thursday, May 02, 2024, 14:54 |
David Wang | Conditioning Station | Standard Operation | TM3 | UCx#44 | TM3 has been moved from SHC to TCS. | TM3 has been moved from SHC to TCS
by David and Frank. The move is smooth. |
|
2585
|
Wednesday, May 08, 2024, 12:36 |
David Wang | Conditioning Station | Standard Operation | TM3 | UCx#44 | TCS was argon vented this morning between 7:00 to 8:30 am. | TCS was argon vented this morning between
7:00 to 8:30 am before module was moved to
ITE. |
|
2600
|
Tuesday, May 28, 2024, 07:45 |
David Wang | Conditioning Station | Standard Operation | TM4 | UCx#45 | TCS was argon vented this morning between 6:00 and 7:30am. | TCS was argon vented this morning between
6:00 and 7:30am for TM4 moving to ITW. |
|
2603
|
Thursday, May 30, 2024, 11:08 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 was moved from silo to TCS yesterday morning. | TM2 was moved from silo to TCS yesterday
morning. The move is smooth.
TCS vacuum system was started after. TCS |
|
2605
|
Wednesday, June 05, 2024, 11:25 |
David Wang | Conditioning Station | Standard Operation | | | refilled TCS:TK2 to 27.4 inches. | refilled TCS:TK2 to 27.4 inches to compensate
water lost during THC filters change. |
|
2606
|
Wednesday, June 05, 2024, 11:32 |
David Wang | Conditioning Station | Standard Operation | | | TCS water system filters have been changed. | TCS water system five filters were
changed yesterday by plant group Dan.T. Service
labels on filters are updated. No water |
|
2608
|
Wednesday, June 12, 2024, 10:18 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 is moved from TCS to silo this morning | TM2 is moved from TCS to silo this morning.
The move is smooth. |
|
2609
|
Thursday, June 13, 2024, 11:44 |
David Wang | Conditioning Station | Repair | TM2 | | Replaced several o ring seals on TM2 service cap. | couple of E-8 to low E-7 atm.cc/sec
leak were found on TM2 service cap top air
to vacuum o rings. Replaced these |
|
2626
|
Wednesday, June 26, 2024, 13:49 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Tm2 has been moved from SW silo to TCS. | Tm2 has been successfully moved from SW
silo to TCS. |
|
2629
|
Wednesday, July 03, 2024, 14:01 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Tm2 has been moved from TCS to SW silo. | Tm2 has been moved from TCS to SW silo.
the move is smooth. |
|