|
ID |
Date |
Author |
Category |
Type |
Module |
Target/Number |
Subject |
Text |
|
|
2048
|
Tuesday, January 14, 2020, 10:12 |
David Wang | Conditioning Station | Standard Operation | TM3 | | Helium spray leak check on TCS. | Using a long pole with a probe to spray
helium on TCS vacuum seals and joints which
are installed in TCS service pit. No |
|
|
2049
|
Tuesday, January 14, 2020, 10:19 |
David Wang | Conditioning Station | Standard Operation | TM3 | | TCS vacuum system is switched off. | TM3 TP1 and TP2 work fine in past
4 days. During operation, The current draw
on pumps were 0.7A to 0.8 A. TM3 will be |
|
|
2050
|
Thursday, January 16, 2020, 09:37 |
Travis Cave | Conditioning Station | Standard Operation | TM3 | no target | Module move | TM#3 has been moved from the conditioning
station to the centre east silo. |
|
|
2060
|
Wednesday, February 05, 2020, 10:49 |
David Wang | Conditioning Station | Standard Operation | TM4 | | Remove of TM4 from SHC to TCS. | TM4 has been moved from SHC to TCS. No
target on module. The move is successful.
|
|
|
2061
|
Wednesday, February 05, 2020, 10:54 |
David Wang | Conditioning Station | Standard Operation | TM4 | | Roughing out TM4 at TCS. | TCS MP1 is started to rough out TM4 and
TCS. TCS and TM4 will be under roughing only
today and tomorrow. No plan to start TCS |
|
|
2066
|
Friday, February 14, 2020, 11:25 |
Travis Cave | Conditioning Station | Standard Operation | TM4 | Dummy Target | Module move | TM#4 with dummy target has been moved
from the south hot cell to the conditioning
station. |
|
|
2067
|
Friday, February 14, 2020, 14:06 |
David Wang | Conditioning Station | Standard Operation | TM4 | | TCS vacuum system and water sytem are switched on. | All turbo pumps are started. |
|
|
2070
|
Wednesday, February 26, 2020, 08:45 |
David Wang | Conditioning Station | Standard Operation | TM4 | | Remove of TM4 from TCS to SW silo | TM4 has been moved from TCS to SW silo.
The move is fine. |
|
|
2090
|
Thursday, March 19, 2020, 15:48 |
Anders Mjos | Conditioning Station | Maintenance | | | Filter replacement in water system March 5th | Filters were replaced by Curtis von Cube
on March 5th. See work permit for details
I2020-03-05-5 |
|
|
2098
|
Thursday, June 04, 2020, 10:40 |
David Wang | Conditioning Station | Maintenance | | | Three manual valves are closed on TCS water system | Three manual valves are closed on TCS water
system return line in experimental hall.
See attachments. It is for TCS TK2 water |
|
|
2099
|
Thursday, June 04, 2020, 10:51 |
David Wang | Conditioning Station | Standard Operation | | | TH floor mop up. | Jason Sargeant mopped up TH floor this
morning. The mop head was checked after the
job. There are 1500 counts on it. He think |
|
|
2122
|
Tuesday, July 07, 2020, 09:16 |
Travis Cave | Conditioning Station | Standard Operation | TM3 | no target | Module move | TM#3 has been moved from the silo
to the conditioning station, where David
and Frank will start on the gutting of the |
|
|
2124
|
Monday, July 13, 2020, 10:01 |
Travis Cave | Conditioning Station | Standard Operation | TM3 | no target | Module move | TM#3 has been moved from the conditioning
station to the silo.
|
|
|
2127
|
Friday, July 24, 2020, 09:43 |
Travis Cave | Conditioning Station | Maintenance | TM2 | Graphite #1 | Module move | TM#2 has been moved from the west
station to the conditioning station. ITW
entrance module moved will take place on |
|
|
2134
|
Tuesday, August 18, 2020, 09:57 |
Adam Newsome | Conditioning Station | Standard Operation | TM2 | | TM2 Moved to Conditioning Station | TM2 was moved from ITW to the Conditioning
Station. |
|
|
2139
|
Thursday, August 27, 2020, 08:21 |
David Wang | Conditioning Station | Standard Operation | TM2 | Ta#60 | Helium pressure check on TM2 HS line at TCS. | Helium pressurize on TM2 HS line at TCS
is done. Base LR is 0.0X
E-9 |
|
|
2140
|
Thursday, August 27, 2020, 09:42 |
Anders Mjos | Conditioning Station | Maintenance | TM2 | Ta#60 | Refilled TK2 | Refilled TCS:TK2 from 10 in to 22 in using
the newly installed valve. |
|
|
2142
|
Thursday, August 27, 2020, 13:18 |
Anders Mjos | Conditioning Station | Maintenance | TM2 | | New Power Supply installed for TGHT | Arthur installed a new Magna Power PS for
the TGHT yesterday. The old power supply
has been moved to Evaporator 2. The power |
|
|
2148
|
Thursday, September 24, 2020, 11:25 |
David Wang | Conditioning Station | Standard Operation | TM4 | UC#31 | TM4 HS line leak check at SHC and TCS. | Both helium spray and helium pressurize
on TM4 HS line withUCx31 target are done
at SHC and TCS. No leak. |
|
|
2166
|
Thursday, November 19, 2020, 09:00 |
David Wang | Conditioning Station | Standard Operation | TM2 | Nb#6 | Helium pressure check on TM2 HS line at TCS. | LD 0.0 Xe-9 atm.cc/sec , 70 psi helium
3 minutes. No leak. |
|