Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  RH-ISAC, Page 131 of 140  Not logged in ELOG logo
Entry  Monday, January 29, 2018, 06:51, David Wang, Conditioning Station, Maintenance, TM1, , TCS and TM1 vacuum pumps switched off 

TCS and Tm1 vacuum pumps are switched off this morning. TM1 TP1and TP2 work fine during this test period. Tm1 will be moved back to silo this morning.

TM1 IG1 stopped work during the test period. It could be broken. We will only replace this gauge if TM1 is used in ITW again.

Entry  Tuesday, May 15, 2018, 07:44, Travis Cave, Conditioning Station, Standard Operation, TM4, no target, Module move 

 TM#4 was moved to the conditioning station from the south hot cell. The module was moved with out the containment box.

Entry  Tuesday, May 15, 2018, 10:21, David Wang, Conditioning Station, Standard Operation, TM4, , Tm4 water circles helium pressur test result  

  Helium pressure test on TM4  water lines is done this morning. 70 psi helim , 1 minutes time to each circle. The result:

A(oven+): 0.00xE-9 atm.cc/sec

B(Oven -): 8.1Xe-7 atm.cc/sec

C(tube -): 0.00xE-9 atm.cc/sec

D(tube+): 1.0xE-5 atm.cc/sec

PQ(coil 2): capped on top. water lines were removed because of leak

RU(Coil1): 0.00xE-9 atm.cc/sec

EE: 0.00xE-9 atm.cc/sec

MSP: 0.00xE-9 atm.cc/sec

HS: No target, capped on top. It was fine on last target check in 2017 Oct.

window: Capped on top. Containment box is not installed.

The leak check on D line caused the IG1 small response during test.

B and D circle are double checked. The reasults are same.

D line leak is in E-5 atm.cc/sec range. It is possible to locate it by using helium spray method in SHC. The containment box is not on so it should be easy to do it.

Switch on IGA gauge at TCS and apply helium and water at certain psi to check the IGA response may give us more information on these leaks.

 All lines were test in last year shut down. They were good.

 

Entry  Thursday, May 17, 2018, 11:30, Anders Mjos, Conditioning Station, Maintenance, TM4, , HV test/conditioning of damaged source tray TM4_2018-05-18_Water_Leak.docx

BIAS only. Water lines looped on top. Containment box off.

Thursday, May 17, 2018, 11:20: Vacuum 7.2E-7 Torr

Thursday, May 17, 2018, 11:30: 10 kV

Thursday, May 17, 2018, 11:42: 20 kV

Thursday, May 17, 2018, 12:14: 25 kV

Thursday, May 17, 2018, 12:35: 30 kV

Thursday, May 17, 2018, 16:13: 35 kV

Thursday, May 17, 2018, 17:339: 37.5 kV

Thursday, May 17, 2018, 17:40: vacuum 6.8E-7 Torr

Thursday, May 17, 2018, 18:13: BIAS off.

Entry  Friday, May 18, 2018, 09:34, David Wang, Conditioning Station, Repair, TM4, , water leak on TM4 Tube heater - B line confirmed. TM4_2018-05-18_Water_Leak.docx

At 8:50 AM today, I applied water to TM4 tube heater - (B) line at TCS. All high vacuum gauges got response on this action. Water is leaking through B line on TM4.

It should be D line . David 2018-06-05

Entry  Tuesday, May 22, 2018, 10:02, Anders Mjos, Conditioning Station, Repair, , , Water leak from TK1 over the weekend 2018-05-22_TCS_TK1_water_leak.pngBroken_Valve.jpg2018-05-22_TCS_TK1_water_leak_archiver.png

Link to e-log,

Link to efault

Tank level down from 76 to 55 in on TK1

Valve replaced by Curtis today

Entry  Wednesday, May 30, 2018, 09:51, David Wang, Conditioning Station, Repair, TM2, , TM2 water lines helium pressure test at TCS. 

I did a helium pressure test on TM2 water lines at TCS. We will remove the TM2 source tray soon so this test is a reference check for future new source. The result:

Helium 70 psi, 2 minutes to each circiut. Leak detector  base LR.0.0x e-9atm.cc/sec, base pressure  0.0x e-4torr

Ta+(A)  0.0x e-9atm.cc/sec

Ta-(B)  0.0x e-9atm.cc/sec

Tu-(C) 7.8x e-7 atm.cc/sec

Tu+(D) 3.5x e-7 atm.cc/sec

Coil 2(PU) 0.0x e-9atm.cc/sec

Coil 1(RU) 0.0x e-9atm.cc/sec

EE 8.2 x e-9atm.cc/sec

MSP 0.0x e-9atm.cc/sec

Containment box window  0.0 xe-9atm.cc/sec

HS  no target and opened. No test.

All water lines on module side in TM2  should be in good condition according to this test . The leak response we found on B and C lines are from water block seals mostly.           

Entry  Wednesday, May 30, 2018, 09:55, David Wang, Conditioning Station, Repair, TM2, , TM2 and TCS vacuum pumps are switched off. 

I switched off TM2 and TCS vacuum pumps. The TCS and TM2 will be under vacuum without pumping.

Entry  Monday, June 25, 2018, 16:42, Anders Mjos, Conditioning Station, Development, , , Testing new high current connectors 

Shorted TGHT with new high current connector assembly and heated to 600 A. Temperature measured on half way point on cable ~ 70 deg C and on connector ~60 deg C at 600 A, 45 / 40 deg C at 400 A. Target Hall locked out during test

Entry  Wednesday, August 01, 2018, 14:48, Travis Cave, Conditioning Station, Standard Operation, TM2, UC#23, Spent Target Move 

 TM#2 with UC#23 has been moved from the south hot cell to the conditioning station.

Entry  Thursday, August 02, 2018, 07:57, David Wang, Conditioning Station, Standard Operation, , , Leak check on TM2 UCx #23 @ TCS and SHC. 

I did a helium pressure test on TM2 HS line at TCS. At 70psi helium, the leak rate is 2.5 xE-7 atm.cc/sec. I think this is the number that close to result before which is 1.7xE-9 atm.cc/sec. WE know there is a small leak on this water block seal. Chad  and I did helium  spray check yesterday at SHC. It was good at bottom scale.  No much worry on this low E-7 range leak.

Entry  Thursday, August 30, 2018, 07:42, David Wang, Conditioning Station, Standard Operation, TM4, , TM4 has been connected to TCS. 

TM4 has been connected to TCS. vacuum system and water system are started. Everything looks fine.

Entry  Thursday, August 30, 2018, 07:46, David Wang, Conditioning Station, Standard Operation, TM4, , TM4 HS line leak check at TCS and SHC. 

Chad and I leak checked TM4 HS line after UCx 24 is installed. No leak at 5xE-9atm.cc/sec.  Today, I did helium pressure test on HS line at TCS. No leak at 70 psi helium 0.0xE-9 atm.cc/sec.

Entry  Tuesday, September 04, 2018, 08:18, David Wang, Conditioning Station, Standard Operation, TM4, UCx 24#, Stppped TM4 and TCS vacuum and water system at TCS. 

I stopped TM4 and TCS vacuum system at TCS. TCS and TM4 is venting with argon now.

Entry  Tuesday, September 04, 2018, 09:57, Travis Cave, Conditioning Station, Standard Operation, TM4, UC#24, Module move 

 TM#4 with UC#24 has been moved from the conditioning station to the east target station.

Entry  Friday, September 14, 2018, 09:39, Travis Cave, Conditioning Station, Standard Operation, TM3, no target, Module move 

 TM#3 with no target has been moved from the north east silo to the conditioning station.

Entry  Tuesday, September 25, 2018, 07:54, David Wang, Conditioning Station, Repair, TM3, , TM3 is connected for HV test at TCS. 

water loops are by passed on top. All bias, EE, and  EL are tied together. Started water system.

Entry  Wednesday, September 26, 2018, 07:14, David Wang, Conditioning Station, Repair, TM3, , TM3 HV test at TCS. 

I did a HV test on TM3 at TCS yesterday. HV Ramp up speed: 1KV per 5 minutes when below 30KV,1KV per 10 minutes from 30-36KV. There is no major spark below36 KV .  I could see  lots small and big vacuum response on IG1 and PNG2 when conditioning from 30-36 KV, especially when closing to 36 KV.  However, At 36.4 KV, There is a big continuous spark occurred. It could not be stopped until I lowed the HV to 14KV. I have to ramp up from 14 KV again.  This behavior on TM3 HV test is same as before we saw. The module can not pass 36KV at present condition.  During the test., EL is tied to 60KV bias. The HV cover on TM3 top is installed. And, Service tray  cover plate is installed on TM3.

Entry  Thursday, September 27, 2018, 13:58, Travis Cave, Conditioning Station, Standard Operation, TM3, no target, Module move 

 TM#3 has been moved from the conditioning station to the centre east silo. This will be its new home after the silo switcher-roo.

Entry  Tuesday, October 09, 2018, 12:32, David Wang, Conditioning Station, Repair, TM4, , TM4 steers 4 pin feedthrough CF flange 

TM4 Steers 4 pin feedthrough CF flange is replaced due an inside feed through insulator broken. CF 25 cooper seal is replaced with a new one as well. Travis did anelectrical check. after replacement. Everything looks fine.

 

Note only a megger check was performed on the affected steering lines. Open load was measured on all lines. (Travis Cave)

ELOG V2.9.2-2455