ID Date Authordown Category Type Module Target/Number Subject Text Attachments
  1496   Thursday, April 13, 2017, 11:44 Anders MjosConditioning StationStandard OperationTM2Ta#51Conditioning Ta#51 Thursday, April 13, 2017, 11:43:
Water package started.
  
  1513   Friday, April 28, 2017, 12:04 Anders MjosConditioning StationMaintenance  MP1 problemTCS:MP1 was tripping of intermittently
yesterday. It was found by Dave Morris that
the current sensor was not set correctly
  
  1531   Wednesday, May 10, 2017, 13:42 Anders MjosConditioning StationRepair  Leaky gauge at TCS:TS2 (e-fault: 9609) Neil Wong will fix this leak tomorrow
Friday.  See attached schematics for
location.
 IRH1056_-_Leaky_Gauge.pdf 
  1532   Wednesday, May 10, 2017, 14:00 Anders MjosSouth Hot-CellDevelopment ITE-Ta-LP-FEBIADTest target examinationChad and Anders inspected the test target
in the hot cell today. The lid had been previously
removed.
  
  1572   Wednesday, June 28, 2017, 16:43 Anders MjosConditioning StationStandard OperationTM4Ta#52Conditioning Ta#52NEW HV cable for BIAS installed earlier
this week.
Wednesday, June 28, 2017, 16:42:
 Ta#52.docx 
  1573   Thursday, June 29, 2017, 11:12 Anders MjosSouth Hot-CellStandard OperationTM4UC#20Post Irradiation Examination (PIE)The target was inspected by Chad and Anders.
Photos are available on DocuShare.
It was noticed that the target tube heater
  
  1576   Wednesday, July 05, 2017, 11:18 Anders MjosConditioning StationMaintenanceTM4Ta#52Changed electrical configuration to cathode bias John Chow configured TCS to cathode
bias mode (IRH1538). The anode P/S is in
positive mode.
  
  1582   Wednesday, July 12, 2017, 11:05 Anders MjosConditioning StationMaintenance  Testing of new high voltage cableThe target hall has been locked-out as
per Document-70039.
Forced IG1, IG1S and IG2 to switch
 2017-07-12_HV_Cable_Test.xlsx 
  1584   Monday, July 17, 2017, 16:28 Anders MjosConditioning StationDevelopmentTM3No targetConditioning TM350 kV stable with less than 1 spark/h during
the weekend by RIB obs.
Today 57 kV reached, but observed
 TM3_HV_conditioning_2017-07-17.docx 
  1587   Tuesday, July 18, 2017, 16:53 Anders MjosConditioning StationDevelopmentTM3No targetConditioning TM3Conditioning continues today with resistors
removed from the HV cable
Tuesday, July 18, 2017, 16:53: BIAS
  
  1594   Thursday, August 03, 2017, 17:08 Anders MjosConditioning StationRepairTM2 Power bump Thursday, August 03, 2017, 17:08:
Restarting vacuum and water system
  
  1597   Tuesday, August 15, 2017, 09:27 Anders MjosSouth Hot-CellStandard OperationTM2SiC#36Electrical Check of target in SHC

    

       
            
  
  1598   Tuesday, August 15, 2017, 09:30 Anders MjosITWStandard OperationTM2Ta#53TM2 radiation fields

    

       
            
  
  1601   Friday, August 25, 2017, 16:33 Anders MjosConditioning StationRepair  Testing HV after cooling line repair The BIAS voltage was brought up to
70 kV today and held there for 1h. No sparking
observed.
 2017-08-25_HV_Water_Line_Test.xlsx 
  1622   Thursday, September 21, 2017, 16:26 Anders MjosSouth Hot-CellStandard OperationTM2 Inspection of Source TrayChad and Anders inspected the Source Tray
today using the camera in the hot cell. A
dark spot was observed on one of the four
 TM2_Source_Tray_EE_Insulator.pdf 
  1631   Thursday, September 28, 2017, 15:34 Anders MjosConditioning StationDevelopmentTM2 Changes to MP3 startup Due to problems with the regulating
valve WPV1, the VFD (Variable Frequency Drive)
for the pump has been programmed to do a
  
  1632   Thursday, September 28, 2017, 17:44 Anders MjosConditioning StationStandard OperationTM2Ta#54Conditioning Ta#54Thursday, September 28, 2017
Cooling water not yet connected to
TM.
 Ta#54.docxTa#54_BIAS_current_vs_voltage.xlsx 
  1634   Thursday, October 05, 2017, 11:04 Anders MjosITWMaintenance  Installation of new valve for module move ventilationDavid installed the new ball valve and
connections for the SAS project module move
ventilation. SASP0482. Drawing reference
  
  1637   Friday, October 06, 2017, 13:25 Anders MjosConditioning StationRepair  HV Test HV was brought up to 70 kV for 1
h without sparks to test the new water installation.
 2017-10-06_HV_Water_Line_Test.xlsx 
  1646   Wednesday, October 18, 2017, 14:54 Anders MjosAssembly/Bench TestStandard Operation  Source tray assembly electrical checkSource tray meggered today by Anders and
Keith
GND - MSP OL @ 1000V
 Steerer_Connections_2017-10-18.pdf 