Monday, January 28, 2013, 12:26, Travis Cave, Conditioning Station, Development, , , Switches connected
|
the switches and the solenoid are all wire up to 24VDC, when you open either of the little doors the solenoid switches this is also true if there is
a power loss. currently the solenoid is powered. |
Thursday, January 24, 2013, 13:30, David Wang, ITW, Standard Operation, TM1, , ITW-TM1 2013 winter shut down leak check.
|
2013 winter shut down ITW-TM1 primary vacuum vessel, secondary vacuum vessel, and water lines leak check: connected leak detector to TP2(primary and
water lines) and TP4S (secondary). base leak rate 0.0xE-9atm.cc/sec,base pressure 0.0XE-4torr. Sprayed helium to all primary vacuum seal and there is no
response on leak detector. Helium pressurized all water lines(except HS) at 70psi ,3mins.Tube heat(+) no response, tube heater(-)1.6xe-9atm.cc/sec, target |
Friday, January 18, 2013, 17:01, Grant Minor, Conditioning Station, Development, TM4, , Photos of the CS with TM4 (after the no-module HV test, only vacuum connected)
|
Attached are some photos of TM4 in the Conditioning Station after the no-module HV test completion. Only vacuum services are connected. |
Friday, January 18, 2013, 16:56, Grant Minor, Conditioning Station, Standard Operation, TM4, , VAT valve btwn roughing and nuc. vent. closed
|
Bevan attempted to start pumping down on TM4 today remotely but there was an issue. He will report on Monday.
I went into the Target Hall this afternoon while on the phone with Bevan and performed the following:
- Checked the knurled vent valves on the side of each turbo, both were found to be in the tightened position (all the way clockwise) |
Friday, January 18, 2013, 11:17, David Wang, South Hot-Cell, Standard Operation, TM4, dummy target, TM4 heat shield circuit leak check with dummy target on.
|
Chad and i did a leak check on TM4 heat shield circuit with installed dummy target at SHC today. The leak detector is pumped to 0.0xE-9atm.cc/sec.Chad
sprayed helium twice on each VCR joints .There is no any response had been found on the leak detector during each 45 seconds waiting time. The TM4
heat shield circuit with dummy target is leak tight so far. |
Friday, January 18, 2013, 11:15, Travis Cave, Conditioning Station, Standard Operation, TM4, CS Test Target #1, module move
|
TM#4 with the test target #1 is now in the conditioning station, move went well. |
Friday, January 18, 2013, 09:10, Travis Cave, South Hot-Cell, Standard Operation, TM4, CS Test Target #1, Electrical check
|
Electrical check performed on the CS Test Target #1 at the south hot cell. See PDF for details. |
Thursday, January 17, 2013, 11:18, Travis Cave, South Hot-Cell, Standard Operation, TM4, , module move
|
TM#4 has been moved from the SW silo to the south hot cell, move went well. |
Thursday, January 17, 2013, 10:06, chad fisher, South Hot-Cell, Standard Operation, , , SiC Test Target for TM4/CS 16x
|
I have inserted the test target for TM4 and the CS into the hot cell.
I had some concerns about the condition of the target which I have discussed with Pierre and he has cleared. Pictures are attached. |
Tuesday, January 15, 2013, 14:37, Travis Cave, Spent Target Vault, Standard Operation, , TiC#3, Spent target move
|
TiC #3 was moved from the south hot cell in to the vault storage today, it was placed in slot 4B and was in pail #104, it had a reading of 98.7mSv/hr
upon removal from the south hot cell. See attached PDF for vault details. |
Tuesday, January 15, 2013, 10:49, David Wang, ITW, Standard Operation, TM1, no target, TM1 vacuum system connection in ITW
|
I connected TM 1 vacuum system in ITW. The TM1 and ITW will be pumped out for shut down routine leak check. |
Monday, January 14, 2013, 14:09, Travis Cave, ITW, Standard Operation, TM1, no target, module move
|
TM#1 has been moved from the south hot hell to the west target station, move went well. |
Thursday, January 10, 2013, 10:40, David Wang, ITW, Maintenance, , , Replaced all high active water system magnetic pedal wheels in ITW and ITE.
|
I replaced all high active water system magnetic pedal wheels in ITW and ITE. This is a preventive maintenance job we planned for this winter shut down. |
Tuesday, January 08, 2013, 14:18, Travis Cave, South Hot-Cell, Standard Operation, TM1, no target, Electrical check
|
TM#1 was electrically check with out a target see attached PDF for results. |
Tuesday, January 08, 2013, 08:48, Travis Cave, South Hot-Cell, Standard Operation, TM1, TiC#3, Electrical check
|
TM#1 with TiC #3 post beam. See attached PDF for results. |
Thursday, January 03, 2013, 10:05, David Wang, ITW, Standard Operation, TM1, , Disconnected TM1 in ITW.
|
TM1 has been disconnected in ITW. All water lines had been purged. Travis was with me during the job. |
Wednesday, January 02, 2013, 12:11, David Wang, ITW, Standard Operation, TM1, , I moved 5 shielding blocks from ITW to block storage area
|
I moved 5 shielding blocks from ITW to block storage area for preparing the TM1 disconnection. Air sampled and swiped blocks and ITW and everything
is fine.Fiona was with me all the time during the moving. |
Thursday, December 06, 2012, 08:57, Travis Cave, Spent Target Vault, Standard Operation, , UCx#5, Spent target move
|
UCx #5 has been moved from the south hot cell to the storage vault. It is in Pail 102, in spot 2A of the vault and had a field of 32.6mSv/hr upon extraction
from the south hot cell. See attached PDF for vault details. |
Wednesday, December 05, 2012, 15:53, Anders Mjos, South Hot-Cell, Standard Operation, , UCx#5, Target inspection - target tube broken
|
The target was inspected today.
It was found that the target tube had broken on both sides of the centre block in the region that contain target material. The Ta-foil heat shield
was removed from the let side tube to allow inspection. |
Wednesday, December 05, 2012, 13:26, Grant Minor, South Hot-Cell, Standard Operation, TM4, N/A, TM4 moved from SHC to South West Silo
|
TM4 was successfully moved from the South Hot Cell to the South-West Silo remotely by Grant Minor, with help from David Wang and Don Jackson. The
move was without problems. See ISAC Work Permit 2012-12-04-1. |
|