1359
|
Friday, September 23, 2016, 07:49 |
David Wang | Conditioning Station | Standard Operation | TM4 | | TM4 has been moved and connected at TCS | All TCS and TM4 turbo-pumps were started
yesterday. Overnight pumping down is good
so far. |
|
|
1360
|
Friday, September 23, 2016, 08:55 |
Travis Cave | Conditioning Station | Standard Operation | TM4 | SiC#34 | Electrical Checks | The bundle of electrical checks, first
one is the Iglis that failed, the second
is the everything passed at the hot cell |
|
|
1361
|
Saturday, September 24, 2016, 11:23 |
Anders Mjos | Conditioning Station | Standard Operation | TM4 | SiC#34 | Conditioning SiC#34 | Conditioning by ISAC operations
Saturday, September 24, 2016, 11:15:
RGA on for heater conditioning. (kept off |
|
|
1363
|
Tuesday, September 27, 2016, 07:30 |
David Wang | Conditioning Station | Standard Operation | TM4 | | TM4 has been disconnected at TCS | TCS water system and vacuum system are
turned off this morning. The TCS and
TM4 are vented. |
|
|
1366
|
Wednesday, September 28, 2016, 13:47 |
David Wang | Conditioning Station | Standard Operation | | | TCS pumping down during mini-shut down. | A steel plate is covered on TCS.
TCS roughing pump is started now. The
TCS will be pumping down during mini-shut |
|
|
1367
|
Friday, September 30, 2016, 14:34 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall schedule for beam schedule 131(Sep-Dec, 2016) | Weekly update TH schedule for beam schedule
131. See attachments 1,2 |
|
|
1371
|
Wednesday, October 12, 2016, 10:01 |
David Wang | Conditioning Station | Standard Operation | | | TCS pumps are stopped | Argon venting is started |
|
|
1384
|
Wednesday, October 26, 2016, 12:33 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Target Hall schedule for beam schedule 131(Sep-Dec, 2016) | Update TH schedule after job delay on TM2
Febiad target. Everything should be back
to schedule on last two targets. See attachments. |
|
|
1388
|
Wednesday, November 02, 2016, 09:12 |
Travis Cave | Conditioning Station | Standard Operation | TM4 | Ta#50 | module moved | TM#4 with Ta#50 has been moved from the
south hot cell to the conditioning station. |
|
|
1389
|
Wednesday, November 02, 2016, 13:41 |
David Wang | Conditioning Station | Standard Operation | TM4 | | TM4 has been connected at TCS. | All turbo-pumps are started. The pumping
down is good so far. |
|
|
1390
|
Thursday, November 03, 2016, 08:57 |
David Wang | Conditioning Station | Standard Operation | TM4 | | Helium pressure test on TM4 HS line at TCS | 70 psi helium ,2minutes to TM4 HS
line. LD base leak rate 0.0xE-9 atm.cc/sec.
No leak. |
|
|
1391
|
Thursday, November 03, 2016, 09:01 |
David Wang | Conditioning Station | Standard Operation | TM4 | | TCS water system has been started for TM4. | The system works fine. All water signals
to TM4 at TCS are normal. HV cover is installed
on to TM4 at TCS. |
|
|
1393
|
Tuesday, November 08, 2016, 07:47 |
David Wang | Conditioning Station | Standard Operation | TM4 | | TCS water and vacuum pumps are switched off | TCS is vented. TM4 is disconnected and
TCS. |
|
|
1397
|
Tuesday, November 15, 2016, 07:53 |
David Wang | Conditioning Station | Standard Operation | TM4 | | Target Hall schedule for beam schedule 131(Sep-Dec, 2016) | Update TH schedules . See attachments |
|
|
1400
|
Tuesday, November 22, 2016, 14:26 |
David Wang | Conditioning Station | Standard Operation | | | TCS vacuum pumps are switched off | TCS will be vented tomorrow morning for
TM2 moving. |
|
|
1401
|
Wednesday, November 23, 2016, 14:21 |
Travis Cave | Conditioning Station | Standard Operation | TM2 | UC#18 | module moved | TM#2 with UC#18 has been moved from the
south hot cell to the conditioning station. |
|
|
1404
|
Wednesday, November 23, 2016, 16:21 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 and TCS vacuum system has been connected. | All vacuum pumps have been started. Air
ballast 50seconds on roughing pump. Everything
is good so far. |
|
|
1405
|
Thursday, November 24, 2016, 09:33 |
Anders Mjos | Conditioning Station | Standard Operation | TM2 | UC#18 | Conditioning UC#18 | Thursday, November 24, 2016, 09:33: Water
package on
Thursday, November 24, 2016, 09:43: |
|
|
1406
|
Thursday, November 24, 2016, 10:30 |
David Wang | Conditioning Station | Standard Operation | TM2 | | HV cover is installed on TM2 at TCS | Interlock key are returned back to
B2 level.TM2 is ready for HV conditioning
and heating up at TCS. |
|
|
1408
|
Tuesday, November 29, 2016, 06:27 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TCS water pumps are stopped | Argon venting on TCS and TM2 is processing |
|