Friday, September 23, 2016, 07:49, David Wang, Conditioning Station, Standard Operation, TM4, , TM4 has been moved and connected at TCS
|
All TCS and TM4 turbo-pumps were started yesterday. Overnight pumping down is good so far. |
Friday, September 23, 2016, 08:55, Travis Cave, Conditioning Station, Standard Operation, TM4, SiC#34, Electrical Checks
|
The bundle of electrical checks, first one is the Iglis that failed, the second is the everything passed at the hot cell and the third is a the conditioning station under vacuum. |
Saturday, September 24, 2016, 11:23, Anders Mjos, Conditioning Station, Standard Operation, TM4, SiC#34, Conditioning SiC#34
|
Conditioning by ISAC operations
Saturday, September 24, 2016, 11:15: RGA on for heater conditioning. (kept off during HV conditioning)
Sunday, September 25, 2016, 07:44: TGHT and TBHT voltage jumps during heater ramping. Likely contact between target and heat shield. Contacted ISAC operations and asked to abort ramping at current values. TGHT/TBHT 500 /270 A
Monday, September 26, 2016, 08:22: ISAC operations resuming ramping to 550 A. Corrected TGHT voltage at ISAC TS was ~6.2 V at 580 A. Expected voltage at TCS would then be 6.2 + (3.4+2.9)E-3*580 = 9.9 V. Limit set at 9.5 V.
Monday, September 26, 2016, 09:09: Increased TGHT voltage limit to 9.6 V to allow it to reach 550 A.
Monday, September 26, 2016, 10:17: Voltage limit increased to 10.2 V which allowed the current to go to 575 A
Tuesday, September 27, 2016, 08:08: Conditioning complete. Ran at 575 / 270 A and 47 kV for about 1 hour. Conditioned cold to 49 kV. |
Tuesday, September 27, 2016, 07:30, David Wang, Conditioning Station, Standard Operation, TM4, , TM4 has been disconnected at TCS
|
TCS water system and vacuum system are turned off this morning. The TCS and TM4 are vented. |
Wednesday, September 28, 2016, 13:47, David Wang, Conditioning Station, Standard Operation, , , TCS pumping down during mini-shut down.
|
A steel plate is covered on TCS. TCS roughing pump is started now. The TCS will be pumping down during mini-shut down. |
Friday, September 30, 2016, 14:34, David Wang, Conditioning Station, Standard Operation, , , Target Hall schedule for beam schedule 131(Sep-Dec, 2016)
|
Weekly update TH schedule for beam schedule 131. See attachments 1,2 |
Wednesday, October 12, 2016, 10:01, David Wang, Conditioning Station, Standard Operation, , , TCS pumps are stopped
|
Argon venting is started |
Wednesday, October 26, 2016, 12:33, David Wang, Conditioning Station, Standard Operation, TM2, , Target Hall schedule for beam schedule 131(Sep-Dec, 2016)
|
Update TH schedule after job delay on TM2 Febiad target. Everything should be back to schedule on last two targets. See attachments. |
Wednesday, November 02, 2016, 09:12, Travis Cave, Conditioning Station, Standard Operation, TM4, Ta#50, module moved
|
TM#4 with Ta#50 has been moved from the south hot cell to the conditioning station. |
Wednesday, November 02, 2016, 13:41, David Wang, Conditioning Station, Standard Operation, TM4, , TM4 has been connected at TCS.
|
All turbo-pumps are started. The pumping down is good so far. |
Thursday, November 03, 2016, 08:57, David Wang, Conditioning Station, Standard Operation, TM4, , Helium pressure test on TM4 HS line at TCS
|
70 psi helium ,2minutes to TM4 HS line. LD base leak rate 0.0xE-9 atm.cc/sec. No leak. |
Thursday, November 03, 2016, 09:01, David Wang, Conditioning Station, Standard Operation, TM4, , TCS water system has been started for TM4.
|
The system works fine. All water signals to TM4 at TCS are normal. HV cover is installed on to TM4 at TCS. |
Tuesday, November 08, 2016, 07:47, David Wang, Conditioning Station, Standard Operation, TM4, , TCS water and vacuum pumps are switched off
|
TCS is vented. TM4 is disconnected and TCS. |
Tuesday, November 15, 2016, 07:53, David Wang, Conditioning Station, Standard Operation, TM4, , Target Hall schedule for beam schedule 131(Sep-Dec, 2016)
|
Update TH schedules . See attachments |
Tuesday, November 22, 2016, 14:26, David Wang, Conditioning Station, Standard Operation, , , TCS vacuum pumps are switched off
|
TCS will be vented tomorrow morning for TM2 moving. |
Wednesday, November 23, 2016, 14:21, Travis Cave, Conditioning Station, Standard Operation, TM2, UC#18, module moved
|
TM#2 with UC#18 has been moved from the south hot cell to the conditioning station. |
Wednesday, November 23, 2016, 16:21, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 and TCS vacuum system has been connected.
|
All vacuum pumps have been started. Air ballast 50seconds on roughing pump. Everything is good so far. |
Thursday, November 24, 2016, 09:33, Anders Mjos, Conditioning Station, Standard Operation, TM2, UC#18, Conditioning UC#18
|
Thursday, November 24, 2016, 09:33: Water package on
Thursday, November 24, 2016, 09:43: TCS:WPV1 shows only 12% open. A visual inspection confirms the valve is fully opened. Controls will be contacted to troubleshoot
|
Thursday, November 24, 2016, 10:30, David Wang, Conditioning Station, Standard Operation, TM2, , HV cover is installed on TM2 at TCS
|
Interlock key are returned back to B2 level.TM2 is ready for HV conditioning and heating up at TCS. |
Tuesday, November 29, 2016, 06:27, David Wang, Conditioning Station, Standard Operation, TM2, , TCS water pumps are stopped
|
Argon venting on TCS and TM2 is processing |
|