2074
|
Friday, February 28, 2020, 09:36 |
David Wang | ITE | Repair | | | Entrance module TP1S broken piesces clean up. |
Using the camera, Frank and I inspected the broken blades in vacuum duct bending section. We are pretty sure some of the broken parts are fallen into bottom of entrance module and vacuum vessel since the broken pars are over on the edge of bending section. The blades rotated at high speed. Basically, They were shoot to the duct opening when they were broken from the pump. Frank and I carefully swiped all broken parts from the edges back to center of duct first. Then, We use vacuum cleaner sucked all broken parts out of the entrance module. We can see lots aluminum dust during the clean up. This kind of aluminum dust also could fallen down to bottom of module and vessel. After clean up, We inspected duct with camera. We can see all broken pieces and dust are cleaned out. The removed broken pieces will be stored with broken pump when the vessel bottom clean up is done. |
2075
|
Wednesday, March 04, 2020, 11:52 |
David Wang | ITE | Standard Operation | | | ITE HV test without module |
ITE bias test is done to 48KV. No spark. We can not raise bias above 48KV. It looks like we have a current limit issue on control system when testing above 48KV. John Cow checked current limit on PS locally. It is set to 8mA which is much higher than the test current. Isac operator issued an e-fault to control group.
John Chow did a local test on PS. Everything works fine.The problem is on control system. We have a 48KV voltage limit problem on control system. We decide to end the test now. 48KV is good enough before this year mini-shut down. |
2076
|
Wednesday, March 04, 2020, 14:30 |
David Wang | Safe Module Parking | Standard Operation | TM2 | | Remove of TM2 from SMP to SHC. |
Frank and I removed TM2 from SMP to SHC. The move is successful. |
2079
|
Friday, March 06, 2020, 09:51 |
David Wang | South Hot-Cell | Standard Operation | TM2 | | TM2 was moved from SHC to SMP yesterday. |
TM2 was moved from SHC to SMP yesterday. The move is successful. TM2 is located at SMP. There is no hot target on module so SMP vacuum is not started. |
2080
|
Monday, March 09, 2020, 14:31 |
David Wang | ITE/ITW | Standard Operation | | | TH emergency exit test. |
Frank and I did the test. The emergency exit hatch on roof was opened and closed twice. Everything works fine. |
2081
|
Wednesday, March 11, 2020, 10:39 |
Travis Cave | ITE | Maintenance | | | Entrance module move |
The entrance module has been moved to the east station to the south hot cell for inspection from the turbo pump explosion. |
2082
|
Thursday, March 12, 2020, 13:42 |
David Wang | ITE/ITW | Development | | | New ITE IGLIS cables installation |
New IGLIS cables installation is done. Two bundle of new cables are pulled from ITE to electrical room. They are in one PVC conduit. The old cables are not removed yet. I will pull old cables out when new cables are installed onto device in ITE Faraday cage. |
2083
|
Thursday, March 12, 2020, 13:48 |
David Wang | ITE | Repair | | | Entrance module TP1S broken piesces clean up. |
The broken pieces in ITE entrance vacuum pit are vacuumed out. At SHC, There are 4 pieces on module collimator block top, wiring scanner top. Chad removed them out at SHC. Electrical check at module top is done by diagnostics group. Everything works fine. |
2084
|
Friday, March 13, 2020, 09:24 |
Travis Cave | ITE | Standard Operation | | | Entrance module move |
The east entrance module has been moved from the south hot cell back to the east target station. |
2087
|
Tuesday, March 17, 2020, 12:58 |
David Wang | South Hot-Cell | Development | TM4 | | P2N target electrical check and leak check at SHC. |
See attachment. Everything looks good. |
Attachment 1: P2N_target_electrical_chek_at_SHC.pdf
|
|
2089
|
Wednesday, March 18, 2020, 10:40 |
David Wang | ITE | Development | TM4 | | TM4 P2N target connection checklist. |
TM4 has been connected in ITE. See checklist. |
Attachment 1: P2N_TM4_connection_checklist.pdf
|
|
2090
|
Thursday, March 19, 2020, 15:48 |
Anders Mjos | Conditioning Station | Maintenance | | | Filter replacement in water system March 5th |
Filters were replaced by Curtis von Cube on March 5th. See work permit for details I2020-03-05-5 |
2091
|
Friday, March 27, 2020, 08:45 |
Matthew Gareau | North Hot-Cell | Maintenance | | | Issues with the manipulators |
This is a link to all of the issues with the NHC manipulators that I know of
https://documents.triumf.ca/docushare/dsweb/View/Collection-27663/Document-180176
|
2092
|
Wednesday, May 20, 2020, 13:08 |
David Wang | Cooling | Standard Operation | | | Start of HALCW sysytem |
High active water pump is started. The system resistance is recovering now. Everything works fine so far. Check ITW and ITE water leak after pump is started. Tiny very slow seep on two small ball valves pack seal. No big concern. |
2093
|
Wednesday, May 20, 2020, 13:19 |
David Wang | ITE | Maintenance | | | Restart of ITE turbo pumps. |
PLC6 drop out in weekend caused the ITH MP1 and MP1s stopped. ITE turbo pumps were running still after that. Without back up pump, TPs started to trip off later . I found TP1,TP3, and TP4 were tripped off this morning. And , The rest pumps ran with high current draw. Jon Aoki restarted back up pumps and ITE turbo pumps. The ITE vacuum system works fine now. |
2094
|
Wednesday, May 20, 2020, 13:30 |
David Wang | Safe Module Parking | Maintenance | | | Silo area radio active waste clean up. |
Sorted and packed one 55 gallon drum with low contamination and active stuffs which are placed around silo area in the past. They include old poly water cooling lines replaced from ITE, ITW and TCS, contaminated paper rags , gloves, and plastic bags,air cooling fans for turbo pumps, EE resistor packaged used on module top before, flow meters and cables used in ITW, etc. After packing, The field outside the drum on contact is less than 10 usv/hr. |
2095
|
Friday, May 22, 2020, 13:26 |
David Wang | ITW | Repair | | | ITW water leak. |
A water leak was found on a fitting connecting ITW dump return line pressure gauge on top of exit module. TM tank flange, o-ring slot and o-ring were contaminated by water and water rust. Frank and I cleaned the flange and o-ring slot . We changed a new TM tank o-ring, vacuumed around other 3 module flanges. The leak fittings with pressure gauges were removed . I put a blind cap on removed fitting spot.. Water are switched back to ITW. No leak on blind cap. |
Attachment 1: itw_water_leak_001.JPG
|
|
Attachment 2: itw_water_leak_005.JPG
|
|
Attachment 3: itw_water_leak_009.JPG
|
|
Attachment 4: itw_water_leak_013.JPG
|
|
2096
|
Monday, June 01, 2020, 12:40 |
David Wang | Crane | Maintenance | | | TH crane festoon cable maintenance |
Tom Kauss corrected the TH crane festoon cable loops. He lubricated festoon cable wheels as well. The maintenance is done. |
2097
|
Monday, June 01, 2020, 12:46 |
David Wang | ITE | Maintenance | | | ITH:CM6 ,CM6S and ITM:CM3 calibration. |
Edi calibrated ITH:CM6, CM6S and ITM:CM3. By the same time, ITH:MP1 and MP2 lubricate oil level are checked. Everything looks fine. No oil leak on both pumps. |
2098
|
Thursday, June 04, 2020, 10:40 |
David Wang | Conditioning Station | Maintenance | | | Three manual valves are closed on TCS water system |
Three manual valves are closed on TCS water system return line in experimental hall. See attachments. It is for TCS TK2 water level slow drop trouble shooting. These valves will be opened again right after troubleshooting.
TCS TK2 water level no change(11.1 inches) in this week after valves are closed. I will keep these three valves closed for one more week.
I opened these valves. In two week times, The TK2 level dropped 0.1 inches. The water level change could be a result of evaporation of water in system. We will keep watching on it. |
Attachment 1: TCS_return_line_closed_valves_001.JPG
|
|
Attachment 2: TCS_return_line_closed_valves_002.JPG
|
|