Thursday, June 20, 2019, 15:09, Isaac Earle, Safe Module Parking, Development, , , SMP motor wiring inspected by electrician
|
The AC wiring for the SMP motor was inspected by Randy Boehm (TRIUMF electrician) as recommended by Franco Mammarella (TRIUMF electrical engineer).
After inspecting the system Randy required the following changes:
AC wiring inside the control panel be increased to 16awg minimum (14awg preferred)
Wiring between the control panel and |
Thursday, July 04, 2019, 08:57, Isaac Earle, Safe Module Parking, Development, , , SMP vacuum system installed
|
July 3:
- Assembled exhaust line flexible hose and fittings as per ISK0529 Rev D then leak checked: 1.4E-1 Torr test port pressure, 1.1E-7 atm-cc/s leak
rate, no response to helium spray at both ends of flexible line (all vacuum fittings purchased from Kurt Lesker under Requisition #1046936)
- |
Friday, July 26, 2019, 15:43, Isaac Earle, Safe Module Parking, Development, , , SMP vacuum control system completed
|
The SMP vacuum control system has been wired and setup to be controlled from EPICS. Backing valve control (SMP:BV1) was tested by connecting
to the turbo pump solenoid on TM3 located in the silo directly north of the SMP. The SMP pump (SMP:MP1) was turned on and off through the EPICS interface
and responded as expected. Both convectron gauges (SMP:CG1 and SMP:CG2) responded as expected when the pump was turned on. The readings from |
Friday, August 23, 2019, 14:27, Isaac Earle, Safe Module Parking, Development, , , SMP camera video cabling installed and tested
|
Installation of the video lines for the SMP cameras was completed yesterday according to IRH1670 Rev B. All four cameras were confirmed to
be displaying properly in the crane control room. The cameras are powered from an outlet wired to circuit 35/37 on Panel #443 (located in the NHCSA).
This is independent from the power supply for other existing camera systems in the Target Hall. The SMP turntable was rotated through the full range |
Tuesday, August 27, 2019, 13:12, Adam Newsome, Safe Module Parking, Development, , , SMP Remote Control Wiring Inspection
|
The wiring for the SMP remote control module was inspected by Joel Semilla (TRIUMF electrician). The module was plugged in to verify there were no
issues. No changes were suggested, and then wiring was approved. |
Tuesday, September 10, 2019, 14:04, David Wang, ITW, Standard Operation, , , ITW water interlock check.
|
ITW water interlock check is finished. Everything is good. |
Wednesday, September 18, 2019, 14:28, Travis Cave, Spent Target Vault, Standard Operation, , , Repacking of the targets.
|
Three of the five targets in the mini storage have been repackaged into the stronger pail. |
Thursday, September 19, 2019, 10:11, Travis Cave, Spent Target Vault, Standard Operation, , , Repacking of the targets.
|
Another target in the mini storage has been repackaged into the new pails. With one remaining to do which will be done on Monday. |
Monday, September 23, 2019, 13:21, Travis Cave, Spent Target Vault, Standard Operation, , , Repacking of the targets.
|
All targets in the mini vault have been repackaged and are now ready to be loaded into F-308s. All the target pails have new numbers see attached
sheet for details. |
Monday, September 30, 2019, 11:27, Isaac Earle, Safe Module Parking, Development, , , SMP vacuum vessel modifications completed
|
The SMP vacuum vessel welds were reinforced to match the specifications on IRH1710 Rev D. In addition a tube stub was added on the side of the
vessel for installation of a PRV. The relief valve installed was Accu-Glass 113150, with 2psi setpoint (not the MDC 420036 model specified on IRH1710
Rev D). The drawing will be updated to reflect this. |
Wednesday, October 02, 2019, 08:25, chad fisher, South Hot-Cell, Standard Operation, , ZrC#8, ZrC#8 PIE
|
Heat shield has been removed from ZrC#8. |
Thursday, October 03, 2019, 10:25, Travis Cave, Spent Target Vault, Standard Operation, , ZrC#8, Spent Target Move
|
The spent ZrC#8 was moved from the south hot cell to the spent target vault. It was placed in pail 217 and the pail was placed in slot 3A of the
vault, it was 205mSv/hr when removed from the hot cell. Also the pail was filled with junk stuff that included
wire, a wire scanner, IMG guage, target bolts and a water block bolts. Also there are only two spots left in the vault. |
Wednesday, October 09, 2019, 13:28, Travis Cave, Spent Target Vault, Standard Operation, , UC#27, Spent Target Move
|
The spent target in the south hot cell has been moved to the spent target vault. It was placed in spot 1B of the vault in pail number 218. See
attached for vault details. |
Thursday, October 10, 2019, 16:17, Adam Newsome, Safe Module Parking, Development, , , SMP Main Panel: Relay Addition for E-Stop Circut
|
An update was made for the E-stop and power supply system in the SMP main panel. Upon testing remote control, it was determined that the Opto 22 AC module
was not sufficiently rated to handle the current draw of the motor (5A fuse versus motor 5.7A current draw). The design was modified so that the E-stop
chain, which supplies 120 VAC line voltage through the main panel E-stop then the remote module (or local pendant when plugged in), will now activate a |
Tuesday, October 15, 2019, 16:42, Isaac Earle, Safe Module Parking, Development, , , SMP flange alignment tested using shield plug
|
As a preliminary test in preparation for SMP commissioning, one of the steel module shield plugs was installed into the SMP to check the positional
and rotational alignment procedures. The following is a summary of the steps performed:
Shield plug lifted with crane and rotated to an arbitrary (non-orthogonal) position
Using the crane pendant the shield |
Thursday, October 17, 2019, 11:49, Travis Cave, Spent Target Vault, Standard Operation, , SiC#31,32 and UC#19,20,21, Loading F-308
|
The targets in the mini storage have been loaded into the F-308. |
Tuesday, October 22, 2019, 16:26, Isaac Earle, Safe Module Parking, Development, , , SMP shield box grounding
|
A braided grounding strap was attached to the aluminum gear box support on the SMP shield box structure, and grounded by attaching it to the exterior
of an electrical conduit located in the south-west corner of the B2 area at the top of the silo in that corner. The braiding was also connected to
the stainless steel support structure for the SMP vacuum pump. |
Monday, October 28, 2019, 11:50, Travis Cave, Spent Target Vault, Standard Operation, , UC#28, Spent Target Move
|
UC#28 has been moved from the south hot cell to spent target storage. The target was placed in pail number 219 and placed in spot 1C of the vault,
it was 12.6mSv/hr upon removal from the south hot cell. Also the spent target vault is now full and can not currently accept anymore targets. |
Monday, October 28, 2019, 12:00, Isaac Earle, Safe Module Parking, Development, , , SMP shielding attenuation measured & compared to theoretical values
|
The attenuation of the SMP shielding was measured as part of SMP commissioning (Document-170404, R1, Section 4, Test #8)
The field on the shutter side of TM3 was measured without any shielding as it was removed from a storage silo. At 0.5m from the edge of the
module the maximum field was 5.00mSv. After installation into the SMP the maximum field outside the SMP shielding at 0.5m from the edge of the module |
Tuesday, October 29, 2019, 10:00, Adam Newsome, Safe Module Parking, Development, , , SMP Updates to E-stop circuit and feedback signals
|
The SMP main control panel and remote control module were updated in order to implement the following items which were deemed desirable during commissioning:
24 VDC line added to E-stop circuit: |
|