  2014   Friday, October 25, 2019, 06:43 David WangSafe Module ParkingDevelopmentTM3 SMP vacuumTM3 was moved into SMP Oct 25 morning. 
After two nights pumping down, SMP CG1 read
30mtorr this morning.  The pump is stopped.
  
  2016   Monday, October 28, 2019, 12:00 Isaac EarleSafe Module ParkingDevelopment  SMP shielding attenuation measured & compared to theoretical valuesThe attenuation of the SMP shielding was
measured as part of SMP commissioning (Document-170404,
R1, Section 4, Test #8)
  
  2017   Tuesday, October 29, 2019, 10:00 Adam NewsomeSafe Module ParkingDevelopment  SMP Updates to E-stop circuit and feedback signalsThe SMP main control panel and remote control
module were updated in  order to implement
the following items which were deemed desirable
  
  2019   Thursday, October 31, 2019, 08:49 Anders MjosConditioning StationRepair  Water leak on non-active cooling water circuitYesterday a leak was discovered in the
ISAC-I experimental hall. The leak appears
to be at the connection between the evaporator
  
  2020   Thursday, October 31, 2019, 10:17 David WangAssembly/Bench TestMaintenanceTM2 Febiad target gas line leak check.Feibiad gas line for ITE and its adapter
fittings for TM2 are tested today by installing
them on a dummy water stem. No leak on VCO
  
  2037   Thursday, December 12, 2019, 14:39 Isaac EarleSafe Module ParkingDevelopment  SMP assembly shifted 1.0" northThe SMP assembly was shifted approximately
1.0" north today by pushing it, braced
against the south wall, using a 100 Ton capacity
  
  2038   Thursday, January 02, 2020, 09:55 David WangCoolingStandard Operation  I turned on HALC water pump MP2.HALCW MP2 is switched onnow. There is a
small amount of air trapped in system. The
pump works fine.  Water level and system
  
  2039   Thursday, January 02, 2020, 10:10 David WangCraneStandard Operation  TH crane issue.Target hall crane does not work properly
after TH crane main power is switched off
during  Christmas time in control room. I
  
  2040   Friday, January 03, 2020, 13:15 Adam NewsomeCraneRepair  Target Hall Crane PLC Module/Battery ReplacementThe Target Hall Crane bridge and trolley motion
was lost after a period of the crane having
power disconnected over winter holidays.
  
  2041   Tuesday, January 07, 2020, 08:02 David WangCoolingStandard Operation  Switch on HALCW MP2HALCW MP2 is switched on this morning after
yesterday cooling tower maintenance. LALCW
P5 and P6 pumps are started by isac operator 
  
  2042   Tuesday, January 07, 2020, 09:37 David WangITWStandard Operation  5 shielding blocks are moved out of ITW top.5 shielding blocks are moved out of itw
top. 
  
  2043   Wednesday, January 08, 2020, 10:34 David WangAssembly/Bench TestDevelopment  Module lifting assembly ITA0490The second module lifting assembly ITA0490
is moved into TH and installed onto TM3 .
It will stay with TM3. I adjusted the 
  
  2045   Thursday, January 09, 2020, 14:14 David WangConditioning StationStandard OperationTM3 Start of TCS roughing pump for TM3.I started TCS roughing pump. TM3 TP1 and
TP2 will be started tomorrow morning. 
  
  2046   Friday, January 10, 2020, 10:26 David WangITEStandard Operation  ITE water signal inerlock check.ITE water  signal interlock  
check is done.  Everything is good.
It is a annual check we do in winter shut
  
  2048   Tuesday, January 14, 2020, 10:12 David WangConditioning StationStandard OperationTM3 Helium spray leak check on TCS.Using a long pole with a probe to spray
helium on TCS vacuum seals and joints which
are installed in  TCS service pit. No
  
  2049   Tuesday, January 14, 2020, 10:19 David WangConditioning StationStandard OperationTM3 TCS vacuum system is switched off. TM3 TP1 and TP2 work  fine in past
4 days. During operation, The current draw
on pumps were 0.7A to 0.8 A. TM3 will be
  
  2051   Friday, January 24, 2020, 08:19 David WangITWStandard OperationTM4 ITW water signal interlock check.ITW water signal interlock check is done.
Everything works fine. ITW 2A2 tank water
signal is broken and is not ok on XT2A2 
  
  2052   Monday, January 27, 2020, 10:40 David WangCoolingMaintenance  ITE/ITW supply water presuure on dump circuits. With both stations in operation,ITE dump
supply gauge reading is 27 psi. ITW is 20
Psi.  I adjusted ITW dump pressure to
  
  2053   Wednesday, January 29, 2020, 12:37 David WangITEStandard OperationTM2 ITE primary/secondary vacuum vessel leak check.Leak check on ITE vacuum vessel is done.
LD base leak rate 0.0XE-9atm.cc/sec. base
pressure 0.0Xe-4torr. Sprayed helium on all
  
  2054   Thursday, January 30, 2020, 10:22 David WangITWStandard OperationTM4  TM4 water lines helium pressure leak check.   TM4 internal water lines helium
pressure leak check at ITW : 70psi helium
5 minutes on  each circuits. Base leak
  