ID Date Authordown Category Type Module Target/Number Subject Text Attachments
  520   Tuesday, October 22, 2013, 17:07 Bevan MossConditioning StationStandard Operation  services shut down The turbo pump, roughing pump, have
been turned off and the valves for venting
opened. The cooling package has also been
  
  538   Tuesday, November 12, 2013, 10:59 Bevan MossSouth Hot-CellStandard OperationTM2 Electrical Test Don Jackson and Myself completed
started an electrical test on TM2. All lines
passed the with OL to ground. When testing
 tm2_elec_test.pdf 
  539   Tuesday, November 12, 2013, 12:43 Bevan MossConditioning StationStandard OperationTM2 TM2 moved from SHC to TCS TM2 was moved by myself and David
from the SHC to the TCS. Move went well.
Curiously the fields on the module were measured
  
  540   Tuesday, November 12, 2013, 14:31 Bevan MossConditioning StationStandard OperationTM2 Turbo pumps started The turbo pumps have been started
on TM2 and the conditioning station.
  
  541   Tuesday, November 12, 2013, 14:33 Bevan MossConditioning StationRepair  Cooling manifold returned The cooling manifold for the conditioning
station high power water cooled lines has
been returned. The cooling package can once
  
  544   Friday, November 15, 2013, 16:48 Bevan MossConditioning StationStandard OperationTM2 HV Testing High voltage testing was started
on TM2 with no source tray today. The maximum
stable for 1 minute voltage reached was 47.5kV
 TM2_conditioning_15112013.JPG15112013_TM2_No_source_tray_HV_test.txt 
  545   Monday, November 18, 2013, 11:54 Bevan MossConditioning StationRepairTM2 Fault on TCS Chill This morning when I went to start
HV conditioning CP2 and CP3 both had faults
and the temperature of the water was ~27C.
  
  546   Monday, November 18, 2013, 16:42 Bevan MossConditioning StationStandard OperationTM2 HV Testing The Glory of TM2 continues 100V at
a time. Today I brought the module to 46kV
and left it there for 1 hour. During this
 the_glory_of_TM2.JPG18112013_TM2_No_source_tray_HV_Test.txt 
  547   Monday, November 18, 2013, 16:44 Bevan MossConditioning StationStandard Operation  Testing of cooling package I have tested all of the compressors
for TCS. All are operational and cycled as
they should. 
  
  550   Tuesday, November 19, 2013, 16:55 Bevan MossConditioning StationStandard OperationTM2 HV conditioning HV conditioning of TM2 continued
today. At ~53.5kV the module started to spark
externally to the HV cover. This is the first
 external_sparking.JPG19112013_HV_conditioning_TM2.JPG19112013_TM2_No_source_tray_HV_Test_no_cover.txt19112013_TM2_No_source_tray_HV_Test.txt 
  553   Wednesday, November 20, 2013, 13:52 Bevan MossConditioning StationStandard OperationTM2 HV testing of TM2 HV testing without the cover continued
today. With the EINZEL lens at 30kV the target
module was able to achieve 58.7kV. At this
 20112013_HV_conditioning_TM2.JPG20112013_TM2_No_source_tray_HV_Test_no_cover.txt 
  558   Wednesday, November 27, 2013, 12:50 Bevan MossSouth Hot-CellStandard OperationTM3 Ground devices wiring check Travis and I completed an electrical
check on the wiring harness for the devices
on the ground plane. All lines passed 500V
  
  559   Wednesday, November 27, 2013, 15:24 Bevan MossSouth Hot-CellMaintenanceTM3 Wiring Harness Electrical Test Maico removed the containment box
today allow Travis and I to further test
the wiring harness. I disconnected the junction
 IMG_1269.JPG 
  561   Friday, November 29, 2013, 11:57 Bevan MossSouth Hot-CellRepairTM3 Steerer short investegation

    

       
            
  
  565   Tuesday, December 03, 2013, 14:14 Bevan MossConditioning StationStandard OperationTM2 HV conditioning  It was attempted to HV condition
TM2 to 55kV and leave it operating there
for an hour to demonstrate stability. Unfortunately
 TM2_conditioning_03122013.JPG 
  575   Friday, December 06, 2013, 15:09 Bevan MossConditioning StationStandard OperationTM2 TM2 no source tray 55kV 1 hourToday 55kV was applied to TM2 and held
for over 1 hour with the EINZEL at 27.5kV.
There were 2 sparks and the current was unstable
 06122013_TM2_No_source_Tray_55kV_1_hour.JPG06122013_TM2_No_Source_Tray_55kV_1_Hour.txt 
  578   Thursday, December 12, 2013, 11:14 Bevan MossConditioning StationStandard OperationTM2 HV Chase Electrical TestWhile under vacuum Travis and I completed
diagnostics of the HV  chase. Majority of
the lines showed OL at 1kV but there were
  
  635   Monday, March 31, 2014, 13:22 Bevan MossConditioning StationStandard OperationTM4Ta #42HV conditioning TM4 with Ta#42 was HV conditioned
to 35kV with the optics tray at 17.5kV. There
was some vacuum response while ramping but
 31032014_TM4_Ta#42_HV_Conditioning.txt31032014_Ta#42_HV_conditioning.JPG 
  645   Thursday, April 10, 2014, 14:03 Bevan MossConditioning StationStandard OperationTM3TiC#4HV conditioning The TiC#4 target that is on TM3 was
conditioned to 25kV today with the EINZEL
lens at 12.5kV. There was one spark shortly
 10042014_Tm3_TiC#4_HV_conditioning.JPG10042014_TM3_TiC#4_HV_conditioning.txt 
  273   Friday, March 22, 2013, 18:49 Aurelia LaxdalConditioning StationDevelopmentTM4FEBIAD HP with Dummy TargetCommissioning TCS - Part 1Today, the commissioning of the TCS went
well. The water/vacuum interlocks were checked
OK. Then, the TCS was HV conditioned up to
  