  1880   Friday, March 01, 2019, 10:23 Travis CaveSpent Target VaultStandard Operation  Source tray moved The old TM#2 source tray and TM#4
optics tray have been removed from the vault
and placed into the spent target storage
  
  1882   Tuesday, March 05, 2019, 09:38 chad fisherSouth Hot-CellRepair  Transfer Fixture RepairTransfer fixture has been remotely disassembled
to the point where the ball nut lock plate
assembly can be inserted into the tool port
 20190305_092228.jpg20190305_092231.jpg20190305_092326.jpg20190305_092558.jpg 
  1883   Tuesday, March 05, 2019, 14:29 chad fisherSouth Hot-CellRepair  Tray Transfer Fixture Repair CompleteRepair of the tray transfer fixture is
complete (minus testing).
A distorted ball nut lock plate was
 20190305_130312.jpg20190305_132303.jpg20190305_133800.jpg20190305_141346.jpg 
  1903   Monday, April 01, 2019, 14:56 Isaac EarleSafe Module ParkingDevelopment  SMP shield box and vacuum vessel installed in final location Last week drilling of the additional
required holes in the SMP shield box was
completed in the Target Hall.  This
 20190401_101459.jpg20190401_110433.jpg20190401_144133.jpg20190401_110353.jpg 
  1904   Thursday, April 04, 2019, 14:49 Isaac EarleSafe Module ParkingDevelopment  SMP vacuum vessel support roller friction checkWith the SMP vacuum vessel now installed
inside the shield box, a test was performed
to measure the torque required to rotate
 CRR_check_for_as-built_SMP_-_April_4_2019.pdf 
  1905   Friday, April 05, 2019, 13:44 chad fisherSpent Target VaultDevelopment  2019 Pail drop tests
    Drop test performed January
8, 2019 with 25 lb target, UN pail and lug
cover. Drop failed. Lug cover half removed.
  
  1906   Friday, April 12, 2019, 11:44 chad fisherSouth Hot-CellStandard Operation  Pail transferPail transfer was undertaken in the south
hot cell. went very well except near the
end the master tong cable of the right hand
  
  1907   Wednesday, April 17, 2019, 12:03 chad fisherSouth Hot-CellRepair  Manipulator repairBroken handle cable of east manipulator
has been replaced and manipulator is operational
again.
  
  1908   Thursday, April 18, 2019, 10:04 Travis CaveSouth Hot-CellMaintenance Ta#50, SiC#34, Ta#46, Ta#47, and Ta#45Target transfer from old pail to new pail. Targets Ta#50 and SiC#34 have been
transferred from their old pails to new ones.
Ta#50 was done on April 12th 2019 it was
  
  1909   Monday, April 29, 2019, 07:56 chad fisherSouth Hot-CellDevelopment  Pail transfersTwo pail transfers took place April 25th.
Ta#47 transfered from pail 137 to
pail 201. existing plastic bag from 137 showed
 20190425_133750.jpg20190425_134106.jpg 
  1910   Monday, April 29, 2019, 09:32 Travis CaveSpent Target VaultStandard Operation SiC#31,32 and UC#19,20,21Spent targets moved to mini vault. The following targets have been moved
from the spent target vault to the mini vault:
#127 - SiC#31 (front)
  
  1916   Thursday, May 02, 2019, 09:37 Travis CaveSpent Target VaultStandard Operation UC#26Spent Target Move The spent UC#26 target was moved
from the south hot cell to the spent target
vault. It was place in pail #209 and put
 Target_Index_2019-05-02.pdf 
  1917   Wednesday, May 08, 2019, 10:29 Travis CaveSouth Hot-CellStandard Operation  Entrance module move The entrance module has been moved
from the west station to the south hot cell.
  
  1918   Friday, May 10, 2019, 10:23 chad fisherSouth Hot-CellRepair  West Entrance module wire scanner replacementWest entrance module - visible broken or
disconnected wire visible on old/existing
wire scanner. Wire scanner removed, new one
 20190509_085908.jpg20190510_101235.jpg 
  1919   Monday, May 13, 2019, 09:55 Travis CaveITWStandard Operation  Entrance module move The West Entrance module has been
moved from the south hot cell to the west
target station.
  
  1920   Monday, May 13, 2019, 11:22 David WangITWRepair  ITW entrance module has been connnected.Entrance module has been connected back
to ITW. Everything is normal.
  
  1921   Wednesday, May 15, 2019, 16:06 Isaac EarleSafe Module ParkingDevelopment  SMP module support flange installed and leak checkedThe SMP module support flange sub-assembly
(IRH1755) was installed today according to
drawing IRH1683.  Dow Corning 111 sealing
 20190515_094730.jpg20190515_094740.jpg20190515_103253.jpg20190515_103824.jpg 
  1925   Friday, May 17, 2019, 16:46 Adam NewsomeSafe Module ParkingDevelopment  SMP Controls Installation Update 
The following controls-related
 IMG_20190417_100838.jpgIMG_20190417_100843.jpgIMG_20190517_162230.jpgIMG_20190517_162305.jpg 
  1930   Thursday, May 23, 2019, 11:22 Travis CaveSouth Hot-CellMaintenance  Removing garbage from the south hot cell. A 55 Gal. drum was remotely lowered
into the south hot cell. It was then filled
with compressable waste. Then the drum was
  
  1937   Monday, June 10, 2019, 14:13 Travis CaveSpent Target VaultStandard Operation  Old TM#4 source tray moved The old TM#4 source tray in the south
hot cell was moved to the spent target vault.
The tray had a low of 7.5mSv/hr to a high
  