1545
|
Friday, May 19, 2017, 13:49 |
David Wang | Conditioning Station | Repair | TM4 | | TM4 TP1 at TCS | TM4 TP1 is replaced. TCS and TM4 was argon
vented before the job.The job took about
30minutes. I started the all turbo |
|
|
1547
|
Tuesday, May 23, 2017, 13:30 |
David Wang | ITE | Standard Operation | TM4 | | TM4 has been connected in ITE | Yasmine and I connected TM4 in ITE . All
turbo pumps are started. |
|
|
1548
|
Tuesday, May 23, 2017, 14:10 |
David Wang | ITE | Standard Operation | | | ITE water interlock check is done. | We do this check once a year now. Rene
found a target oven reset issue during the
check . He will consult with Friedhelm. The |
|
|
1549
|
Wednesday, May 24, 2017, 08:11 |
David Wang | ITW | Standard Operation | TM2 | | TH schedule 132 update weekly | See attachments. |
 |
|
1551
|
Wednesday, June 07, 2017, 13:33 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 SiC#36 leakc check and electrical check. | The results are good. See attachment. |
|
|
1552
|
Wednesday, June 07, 2017, 13:34 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 and TCS vacuum system has been connected. | I started all turbo pumps. |
|
|
1553
|
Thursday, June 08, 2017, 07:37 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Helium pressure test on TM2 water llines at TCS. |
The helium pressure test on HS line is done |
|
|
1554
|
Thursday, June 08, 2017, 08:35 |
David Wang | Conditioning Station | Development | TM2 | | TM2 gas line reconfiguration on the module top. | Reconfigured TM2 gas line on the module
top. It matches with the febiad gas line
we are using on service tray now. Facing |
|
|
1555
|
Friday, June 09, 2017, 11:21 |
chad fisher | North Hot-Cell | Maintenance | | | Model 'N' Slave Removal Through Roof | Isaac and Chad disengaged the slave end
of the manipulator and performed a slave
removal through the slave removal roof hatch. |
|
|
1556
|
Monday, June 12, 2017, 13:51 |
Travis Cave | Spent Target Vault | Standard Operation | | | Spent Target move | The spent Ta#51 target has been moved from
the south hot cell to the spent target vault.
It was placed in pail#149 and put in spot |
|
|
1558
|
Tuesday, June 13, 2017, 11:10 |
Grant Minor | Crane | Maintenance | | | ISAC THall Crane 100% / 125% Load Test Documentation - 2011 | The ISAC Target Hall Crane was load tested
and re-certified in January 2011 prior to
doing a near-capacity lift for the North |
    |
|
1559
|
Tuesday, June 13, 2017, 13:41 |
David Wang | ITW | Standard Operation | TM2 | | TM2 has been connected in ITW. | Yasmine and I connected TM2 in ITW today.
the control page is set to febiad mode. Both
gas line in ITW are opened for febiad run. |
|
|
1560
|
Thursday, June 15, 2017, 11:29 |
Isaac Earle | North Hot-Cell | Development | | | NHC inlet ducting installed | The North Hot Cell inlet ducting assembly
was installed today in the target hall at
the north end of the NHC roof block. A |
   |
|
1561
|
Monday, June 19, 2017, 07:29 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Update TH MS project schedule. | Update TH MS project schedule. See attachment
1,2. |
 |
|
1562
|
Thursday, June 22, 2017, 11:10 |
chad fisher | South Hot-Cell | Maintenance | | | In cell airline | The in cell airline has preemptively been
replaced. The hose was, as far as I know
the original. |
|
|
1563
|
Friday, June 23, 2017, 12:08 |
David Wang | Crane | Repair | | | TH crane inspection and probem fixing by Gordon crane | Gordon crane technician Peter came in today
and checked TH crane. Maico and I were there
with him. What he found is that brake gap |
|
|
1564
|
Friday, June 23, 2017, 17:28 |
Isaac Earle | North Hot-Cell | Development | | | NHC module flange and cameras installed | The North Hot Cell module support
flange (IRH1152D) was installed on June 21,
2017 using 1/8" rubber sheet as a sealing |
    |
|
1569
|
Tuesday, June 27, 2017, 14:34 |
David Wang | Conditioning Station | Standard Operation | TM4 | | TM4 vacuum has been connected at TCS | Turbo -pumps are started . The vacuum looks
good so far. |
|
|
1574
|
Thursday, June 29, 2017, 11:55 |
David Wang | Conditioning Station | Repair | | | TCS HV cable and feed through installation | John Chow and I installed new TCS HV cable
and feed through with their mounting panel
back to TCS Faraday cage this Tuesday. ECO-4269 |
|
|
1577
|
Wednesday, July 05, 2017, 15:36 |
Isaac Earle | North Hot-Cell | Development | | | NHC and SHC nuclear ventilation flow sensors installed | Installation of new flow sensors
and transmitters for the NHC and SHC duct
lines was completed in the target hall today. |
 |