823
|
Monday, December 15, 2014, 15:55 |
Grant Minor | Conditioning Station | Repair | | | Access to ISAC TCS TK2 Expansion Tank - Fall Arrest | Hello all,
Access was required this morning to |
|
|
831
|
Thursday, January 08, 2015, 10:34 |
chad fisher | South Hot-Cell | Standard Operation | | | TM2 Tray Build Status and Problems | Final assembly of the source tray for TM2
was started this morning.
Sliding tray was received from keensert |
|
|
840
|
Friday, February 06, 2015, 08:06 |
David Wang | Crane | Repair | | | TH crane lost movement controls since last Friday. | Last Friday, During the crane per use check,
I found the main power supply to to crane
was shut off. I was told Don and Travis |
|
|
841
|
Friday, February 06, 2015, 12:27 |
David Wang | Crane | Repair | | | TH crane troubleshoot | Gordon crane technician started TH crane
trouble shooting this morning. The problem
is found that there is no 115VAC power supply |
|
|
842
|
Wednesday, February 11, 2015, 13:13 |
chad fisher | South Hot-Cell | Maintenance | | | New gas bottle storage rack | The new gas bottle storage rack has been
installed by/for the south hot cell.
|
|
|
844
|
Monday, February 16, 2015, 11:57 |
David Wang | Crane | Repair | | | TH crane | Dave.Morris installed a new battery on
crane control PLC board and uploaded the
program. Travis, Dan and I tested the crane |
|
|
845
|
Tuesday, February 17, 2015, 13:06 |
Anders Mjos | ITE | Development | | | Resistance measured of TGHT and TBHT lines to ITE | The copper bars was installed by David
and Anders. After the measurements were completed,
the copper bars were removed. |
|
|
846
|
Tuesday, February 17, 2015, 13:07 |
Anders Mjos | ITW | Development | | | Resistance measured of TGHT and TBHT lines to ITW | See e-log entry
for ITE for details. The copper bars have
not been removed. They can be used for testing |
|
|
847
|
Monday, February 23, 2015, 12:28 |
David Wang | ITE | Maintenance | | | 2015 shut down coils and pedal wheels replacement on ITE water flow sensors. | Dan and I replaced pedal wheels and coils
on ITE water flow sensors. It is a shut down
job we did every two years. See attachment |
|
|
848
|
Wednesday, February 25, 2015, 10:44 |
David Wang | ITW | Maintenance | | | 2015 shut dwon ITW water sensor coils and pedal wheels replacement | Dan and I replaced pedal wheels and coils
on ITW water flow sensors. It is a shut
down job we did every two years. See attachment |
|
|
849
|
Thursday, February 26, 2015, 09:22 |
David Wang | ITW | Standard Operation | | | TH Shut Down Activities Schedule Feb 23th- Mar 25th | TH shut down activities schedule from Feb
23th-March 25th. The schedule will be updated
each week. See attachment 1. |
|
|
850
|
Friday, February 27, 2015, 09:34 |
chad fisher | South Hot-Cell | Maintenance | | | Hot cell Entry February 25 2015 | See attached report.
Summary:
Radio problems just before entry |
|
|
853
|
Thursday, March 05, 2015, 07:17 |
David Wang | ITW | Standard Operation | | | TH Shut Down Activities Schedule Feb 23th- Apr 15th update | TH shut down jobs are processing as scheduled
this week. Discussed with Don, and we think
the jobs scheduled in next week should be |
6x |
|
854
|
Thursday, March 05, 2015, 14:30 |
chad fisher | South Hot-Cell | Development | | | Dissection Box | Box for dissecting targets almost complete.
Should be done tomorrow. |
|
|
855
|
Monday, March 09, 2015, 09:42 |
chad fisher | South Hot-Cell | Development | | | Hot Cell Table Swiping | 3 swipes of the south hot cell table were
taken from the target hall through the roof
hatch (2 standard, 1 alpha). |
|
|
861
|
Friday, March 13, 2015, 13:36 |
Travis Cave | Spent Target Vault | Standard Operation | | ThO#1 | Spent Target Move | The ThO#1 has been placed in the storage
vault placed in pail #122 in spot 2B of the
vault. It was 6.2mSv/hr upon removal from |
|
|
864
|
Tuesday, March 17, 2015, 10:33 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#11 | Spent Target Move | The spent UC#11 has benn moved from the
south hot cell to the spent target vault.
See attached PDF for details. |
|
|
865
|
Friday, March 20, 2015, 13:37 |
chad fisher | South Hot-Cell | Development | | | TM2 Optics Tray | Final assembly and alignment of TM2 optics
tray continued today. Front section is "aligned". |
|
|
866
|
Monday, March 23, 2015, 07:56 |
David Wang | ITE | Standard Operation | | | TH Shut Down Activities Schedule Feb 23th- Apr 15th update | This schedule is following Dons schedule
on module moves. See attachments for updating.
2015-03-27: Weekly update the schedule. |
|
|
867
|
Monday, March 23, 2015, 14:03 |
chad fisher | South Hot-Cell | Standard Operation | | Ta#45 | Ta#45 inserted into hot cell | Ta#45 has been inserted into the hot cell.
Swipe taken of inner tool port area: 100000
counts/min. |
|