Entry  Wednesday, May 21, 2014, 13:56, Travis Cave, Spent Target Vault, Standard Operation, , , Spent target assay Vault_Storage_May_22_2014.pdf
All targets in the vault have been assayed and measured. Results will be posted soon. 
Results of assay are now attached in a new layout.
Entry  Wednesday, May 21, 2014, 13:56, Travis Cave, Spent Target Vault, Standard Operation, , , Spent target assay 
All targets in the vault have been assayed and measured. Results will be posted soon.
Entry  Thursday, May 15, 2014, 14:38, David Wang, ITE, Repair, TM3, TM3, Bias short on ITE 
Anders and I opened the HV cover in ITE and did  a visual check inside ITE HV  cover and top of TM3.Bill was with us and took the pictures.
There was nothing obviously wrong when we opened the HV cover in ITE. We disconnected TM3 high current cables from ITE. Then we did an electrical check
on TM3.The TM3 was good and passed megga test (465Mohm at 500V). The module was good and was separated electrically from the ITE at that moment. Then,
Entry  Wednesday, May 14, 2014, 19:01, Grant Minor, ITE, Maintenance, TM3, , HV short inspection at ITE 
Friedhelm Ames commented to me that there appears to be a short between High Voltage and Ground at TM3 at ITE.
Friedhelm, Anders and I initiated a survey by Andrew from RPG, and entered the Target Hall at approximately 5pm to visually assess the HV cover
at the MAA.  There was no clear indication of a problem.  We opted to wait for David to return as we weren't sure exactly what we were looking
Entry  Wednesday, May 07, 2014, 10:15, David Wang, ITE, Repair, TM3, , ITE TM3, entrance module and BL2A3 window flange seals leak check.. 
ITE TM3, entrance module, and 2A3 window flange seals have been leak checked this morning after 2 new seals replacement.The LD base leak rate was 0.0xE-9
atm.cc/sec,  base pressure was 0.0 XE-4 Torr. I sprayed lots helium around the TM3, entrance module and 2A3 flange seals. No any response had been
found on LD during the  spraying. All three flanges are sealed perfectly now.
Entry  Wednesday, May 07, 2014, 10:08, David Wang, ITE, Repair, TM3, , ITE entrance module flange seal had been replaced. 7x
ITE entrance module flange seal had been replaced yesterday.The flange and the seal groove were cleaned with Acetone before the new seal is installed.
See pictures
Entry  Tuesday, May 06, 2014, 14:05, Travis Cave, ITE, Standard Operation, , , module move 
The entrance module was out a new seal went in and then the entrance module went back, and then TM#3 went back. So all modules are now back in place
in the east target station.
Entry  Monday, May 05, 2014, 13:11, David Wang, ITE, Repair, TM3, , ITE Entrance module has been disconnected. 011.JPG025.JPG033.JPG035.JPG032.JPG
ITE entrance module has been disconnected and the lifting yoke is installed for module move. See attached pictures.
Entry  Monday, May 05, 2014, 13:05, David Wang, ITE, Repair, TM3, , ITE target module flange seal has been replaced. 004.JPG008.JPG008.JPG007.JPG
ITE target module flange seal has been replaced.The flan surface and the o-ring groove have been cleaned with Acetone before the new seal is installed.
See attached picture.
Entry  Monday, May 05, 2014, 10:40, Travis Cave, ITE, Standard Operation, TM3, TiC#4, module move 
TM#3 with TiC#4 has been moved from the east station to the south west silo.
Entry  Wednesday, April 16, 2014, 17:08, Keith C Ng, ITE, Repair, , , 2a3 window - He leak check 
Helium leak checked 2a3 window after installing using remote line: 
- There was a leak found between the target and entrance module at the target pit, rate of 9E-6 atm-cc/sec.
- One test performed with the remote helium line to the window. There was a response but the leak detector was located above the window access
Entry  Friday, April 04, 2014, 16:59, Anders Mjos, ITW, Development, , , Flow meters installed on Heat Shield and Coil water return 20140404_165829_1.jpg
David W. has installed two SST Proteus flow meters, model OV7006FTA32, on ITW Heat Shield and Coil. The flow meters are connected to a power supply and
a data logger in the electrical room.
The Heat Shield flow meter has SN 00278112 and is on the Black wire pairs and connected to CH3 & CH4 on the logger.
    Reply  Wednesday, April 16, 2014, 10:16, Anders Mjos, ITW, Development, TM3, Ta#42, Flow meters installed on Heat Shield and Coil water return 
 

    
        
            Anders Mjos wrote:
        
        
            
Entry  Tuesday, April 15, 2014, 08:53, Travis Cave, ITE, Standard Operation, TM3, TiC#4, module move 
TM#3 with TiC#4 has been moved from the conditioning station to the east target station.
Entry  Monday, April 14, 2014, 13:58, David Wang, ITE, Repair, , , Reconnected ITE entrance module 
I reconnected the entrance module back to the ITE station. All diagnostic cables, turbo- pump, air lines, water lines on ITE entrance module and BL2A3
window are connected back.
Entry  Monday, April 14, 2014, 11:57, Travis Cave, ITE, Standard Operation, , , entrance module move 
The East Entrance module has been moved from the south west silo to the east target station. The move went well.
Entry  Friday, April 11, 2014, 18:17, Keith C Ng, ITE, Repair, , , 2a3 window - install 
Today:
1) Installed new cradle and shortened beam pipe section in wall penetration.
- Removed tank dust cover from flange and cleaned
Entry  Friday, April 11, 2014, 11:35, David Wang, Conditioning Station, Standard Operation, TM3, , Helium pressure test on TM3 HS water line with new Ta target. at CS 6x
The helium pressure test on TM3 HS water line with new Ta target is finished at CS. The circuit is leak tight.. No any response on LD. See pictures.
Entry  Thursday, April 10, 2014, 14:03, Bevan Moss, Conditioning Station, Standard Operation, TM3, TiC#4, HV conditioning 10042014_Tm3_TiC#4_HV_conditioning.JPG10042014_TM3_TiC#4_HV_conditioning.txt
 The TiC#4 target that is on TM3 was conditioned to 25kV today with the EINZEL lens at 12.5kV. There was one spark shortly after reaching 25kV that
reset the bias PS and another one  after the module sat at 25kV for ~30 minutes. Attached is the strip tool data and screen shot. Prior to starting
the conditioning the power on the chiller needed to by cycled as the VFD on the fans had tripped due to a recurring inrush problem.
Entry  Wednesday, April 09, 2014, 11:10, David Wang, South Hot-Cell, Standard Operation, TM3, , TM3 heat shield circuit leack check at SHC 
This Monday morning, Chad and I leak checked heat shielding circuit on TM3 with new target installed. The base LR on LD :0.0xE-9 atm.cc/sec, base pressure
0.0xE-4 torr. Chad sprayed helium twice on the VCR joints. No leak has been found. The circuit will be pressured with helium at CS.
Entry  Tuesday, April 08, 2014, 09:05, Travis Cave, South Hot-Cell, Standard Operation, TM3, TiC#4, module move 
TM#3 with TiC#4 has been moved from the south hot cell to the conditioning station.