390
|
Thursday, June 27, 2013, 14:27 |
chad fisher | South Hot-Cell | Development | | | Polishing Cleaning tool - Water blocks | The polishing/cleaning tool prototype is
now finished and appers to work great.
Thanks to Dan and Maico for the great |
|
|
393
|
Wednesday, July 03, 2013, 08:43 |
chad fisher | South Hot-Cell | Standard Operation | | | Ta#39 Transfered to spent target storage vault | |
|
|
394
|
Wednesday, July 03, 2013, 08:44 |
chad fisher, Travis Cave | South Hot-Cell | Standard Operation | | | Ta#39 Transfered to spent target storage vault | Ta#39 has been transferred to spent target
storage vault. Ta#39 was placed into pail
#106 and placed into spot of 4C of the spent |
|
|
412
|
Friday, July 26, 2013, 11:06 |
David Wang | South Hot-Cell | Standard Operation | | | The steel shielding plug has been put on theSHC top in target hall | to reduce the radioactive shining from
SHC Ta# 40 target. |
|
|
413
|
Monday, July 29, 2013, 14:32 |
Travis Cave | Spent Target Vault | Standard Operation | | Ta#40 | Spent target move | Spent target Ta#40 has been placed into
storage. The target was placed in pail #107
and was put into slot 5A of the vault. It |
|
|
416
|
Wednesday, July 31, 2013, 11:13 |
Travis Cave | Spent Target Vault | Standard Operation | | | Spent target move | Five spent targets have been removed from
the storage vault and placed into the mini
storage. The target placed into the mini |
|
|
417
|
Wednesday, August 07, 2013, 06:47 |
maicodallavalle | Spent Target Vault | Maintenance | | | F-308 | All the F-308's have been torqued up
and the locks installed. Ready to be moved. |
|
|
432
|
Wednesday, August 28, 2013, 14:17 |
Travis Cave | South Hot-Cell | Standard Operation | | UC#6 | Spent target move | Spent target move, UC#6 has been moved
from the south hot cell to the target storage.
The target is in pail 108 and in slot 8C |
|
|
462
|
Tuesday, September 24, 2013, 14:46 |
Bevan Moss | South Hot-Cell | Repair | | | Right manipulator repair | |
|
|
497
|
Tuesday, October 08, 2013, 13:11 |
Travis Cave | Spent Target Vault | Standard Operation | | SiC#29 | Spent target move | SiC#29 has been moved to the spent target
vault. The target was placed in Pail #109
and placed into slot 2B it was 24.7mS/hr |
|
|
499
|
Tuesday, October 08, 2013, 14:58 |
Anders Mjos | South Hot-Cell | Standard Operation | | SiC#29 | Target to Heat Shield electrical short | The SiC#29 CTL target has been taken apart
with the help of Isaac and Chad. Electrical
measurements were done between Target and |
|
|
503
|
Tuesday, October 15, 2013, 16:44 |
Grant Minor | Crane | Repair | | | Target Hall Crane - operational with temporary thermal sensor bypass | E-mail correspondence on the Target Hall
crane fault diagnosis between October 11th
and 15th: |
|
|
505
|
Wednesday, October 16, 2013, 18:53 |
Grant Minor | ITE | Repair | | | ITE Harp 9 Removed & Blanked-Off - blocks NOT YET replaced | The blocks above the pre-separator section
of the ISAC beam lines were removed today
in the Target Hall by Bevan Moss and Chad |
11x |
|
507
|
Thursday, October 17, 2013, 17:16 |
Grant Minor | ITE | Repair | | | Pre-Separator-area (ITE Harp 9) Blocks Replaced | The pre-separator-area blocks were replaced
today by Bevan and Travis, with Grant present
for photos and observation. |
8x |
|
508
|
Friday, October 18, 2013, 10:17 |
Bevan Moss | ITW | Repair | | | Paddle Wheel | Yesterday I visually inspected the
paddle wheel and noticed that it was spinning
freely and constant. As the signal was intermittent |
|
|
518
|
Tuesday, October 22, 2013, 16:52 |
Bevan Moss | Conditioning Station | Repair | | | Canbus base card for BIAS | The base card in the canbus BIAS
module was determined to be faulty. Dave
Morris removed a card VECC to repair the |
|
|
520
|
Tuesday, October 22, 2013, 17:07 |
Bevan Moss | Conditioning Station | Standard Operation | | | services shut down | The turbo pump, roughing pump, have
been turned off and the valves for venting
opened. The cooling package has also been |
|
|
523
|
Thursday, October 24, 2013, 11:31 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#7 | Spent target move | UC #7 has been moved from the south hot
cell to the spent target vault, it was placed
in pail #110 and put in slot 8B of the vault, |
|
|
541
|
Tuesday, November 12, 2013, 14:33 |
Bevan Moss | Conditioning Station | Repair | | | Cooling manifold returned | The cooling manifold for the conditioning
station high power water cooled lines has
been returned. The cooling package can once |
|
|
547
|
Monday, November 18, 2013, 16:44 |
Bevan Moss | Conditioning Station | Standard Operation | | | Testing of cooling package | I have tested all of the compressors
for TCS. All are operational and cycled as
they should. |
|