61
|
Tuesday, November 22, 2011, 15:07 |
Bevan Moss | Conditioning Station | Standard Operation | TM1 | UCx #3 | HV testing | High Voltage (HV) testing was completed
on TM1 today. Vacuum was very good 1.9 x
10^-7 T in the service cap, 3.2 x 10^-7 in |
|
|
68
|
Tuesday, January 10, 2012, 11:51 |
Grant Minor | Conditioning Station | Repair | | | IMC at Cond. Station is VENTED - DO NOT PUT MODULE IN | Hi Remote Handling,
The guage on the IMC circuit in the
Target Hall is reading atmosphere, and the |
|
|
79
|
Monday, April 02, 2012, 08:17 |
David Wang | Conditioning Station | Development | | | conditioning station IMC pump down. | I pumped down conditioning station IMC
today. The inside bellow pressure is -20
psi on the gauge.Visually checked the bellow |
|
|
80
|
Tuesday, April 03, 2012, 12:11 |
David Wang | Conditioning Station | Development | | | leak check on conditioning station vacuum system | I did a leak check on conditioning station
vacuum system today.The vacuum system had
been roughed over night . This morning before |
|
|
82
|
Thursday, April 12, 2012, 09:38 |
Travis Cave | Conditioning Station | Standard Operation | TM1 | no target | Move ot TM#1 | TM#1 has been moved from the NE silo to
the Conditioning Station. |
|
|
83
|
Thursday, April 12, 2012, 14:40 |
David Wang | Conditioning Station | Development | TM1 | | conditioning staion and TM1 is under TP1 and TP2 pumping now. | TM1 moved to conditioning station to today.
After moving, I connected the vacuum system
which include all gauges ,vacuum lines , |
|
|
84
|
Friday, April 13, 2012, 12:31 |
David Wang | Conditioning Station | Development | TM1 | | TM1 and conditioning station leak check. |
Normal
0
|
|
|
85
|
Monday, April 16, 2012, 16:17 |
Bevan Moss | Conditioning Station | Standard Operation | TM1 | No Target | High Voltage Test | A high voltage test was completed
on a target free TM1 in the conditioning
station. Only the turbo pumps on the target |
|
|
90
|
Friday, April 20, 2012, 14:07 |
Travis Cave | Conditioning Station | Standard Operation | TM1 | Nb#6 | module move | TM#1 with Nb#6 is now in the conditioning
station. The fields of the module at the
south cell was 15.8mSv/hr. The move was uneventful. |
|
|
93
|
Tuesday, April 24, 2012, 10:36 |
Bevan Moss | Conditioning Station | Standard Operation | TM1 | Nb#6 | HV test April 23 | A HV test was complete on TM1 with
Friedhelm, David, and Myself. The module
behaved as it has in other tests. The vacuum |
|
|
94
|
Tuesday, April 24, 2012, 10:38 |
David Wang | Conditioning Station | Standard Operation | TM1 | LP SIS Nb6 | TM1 heat shield circuit leak check with Nb5 |
Normal
0
|
|
|
108
|
Tuesday, May 22, 2012, 08:33 |
Travis Cave | Conditioning Station | Standard Operation | TM4 | SiC#27 | Electrical check | Electrical check of TM#4 with SiC#27 under
vacuum at that conditioning station. See
attached PDF for details. |
|
|
109
|
Tuesday, May 22, 2012, 10:00 |
David Wang | Conditioning Station | Standard Operation | TM4 | sic 27 | helium pressure test on heat shield circuit | I did a helium pressure test on heat shield
circuit. The leak detector is concected to
the TM4 primary vacuum system.The IG1 is |
|
|
120
|
Thursday, June 07, 2012, 11:58 |
Bevan Moss | Conditioning Station | Standard Operation | TM1 | Ta38 | Module Move from SHC to TCS | TM1 was moved from SHC to the TCS. The
mode took roughly 1 hour. During the move
the north east corner of the containment |
|
|
121
|
Friday, June 08, 2012, 11:07 |
David Wang | Conditioning Station | Standard Operation | TM1 | Ta38 | conditioning staion and TM1 is under TP1 and TP2 pumping now. | I connected vacuum system to TM1 and conditioning
station and started two turbo pumps yesterday.
The pumping an d vacuum readings are |
|
|
125
|
Monday, June 11, 2012, 14:14 |
Travis Cave | Conditioning Station | Standard Operation | TM1 | Ta#38 | Electrical check | Electrical check of TM#1 with Ta#38 at
the conditioning station under vacuum. See
attached file for details. |
|
|
126
|
Monday, June 11, 2012, 14:41 |
David Wang | Conditioning Station | Standard Operation | TM1 | Ta38 | Heat shield helium pressure test | Connected leak detector to TM1 and CS vacuum
system. The vacuum readings on TM1 and CS:PNG1
1.3 xE-6 Torr, IG1 4.7xE-7torr, IG4(diagnostic |
|
|
139
|
Wednesday, July 04, 2012, 13:18 |
David Wang | Conditioning Station | Standard Operation | TM4 | uo#3 | leak check on heat shield circuit |
|
|
|
140
|
Wednesday, July 04, 2012, 14:16 |
Travis Cave | Conditioning Station | Standard Operation | TM4 | UO#3 | module move | TM#4 with UO#3 moved from the south hot
cell to the conditioning station. The fields
of the module at the hot cell was 74.4 mSv/hr. |
|
|
141
|
Friday, July 06, 2012, 09:24 |
Travis Cave | Conditioning Station | Standard Operation | TM4 | UO#3 | Electrical check | Electrical check of the target was done
at the conditioning station under vacuum,
see attached file for details. |
|