Entry  Thursday, May 23, 2013, 14:07, Bevan Moss, Conditioning Station, Repair, , , Chiller Unit Repaired 

 ESC came today and "repaired" the chiller. There was something wrong with the VFD controller. The were able to get it to start and run correctly again but were not able to recreate the problem. At this point it appears that it has magically disappeared. 

Entry  Thursday, May 23, 2013, 14:12, Bevan Moss, Conditioning Station, Maintenance, , , Primary Circuit Drained and Flushed 

 Rob Walker has drained the primary side of the conditioning station. It will be flushed, filled  and chemically treated. It was desired to chemically treat the primary side before before but it took so long that sediment was found (things started to grow).

Entry  Monday, May 27, 2013, 11:55, chad fisher, South Hot-Cell, Standard Operation, , , Special Tooling for RFQ target 

The special tool made for the RFQ target autopsy has been inserted into the hot cell.

 

4-40 button head screws have been successfully lossened.

Entry  Monday, May 27, 2013, 15:59, Bevan Moss, Conditioning Station, Repair, , , Compressor fault 

 Once again the 7.5 compressors are tripping due to faults. I believe it is due to over pressure as a result of the chiller fans not coming on. I have contacted ESC.

Entry  Monday, May 27, 2013, 16:01, Bevan Moss, Conditioning Station, Repair, , , CanBUS card 

 During HV conditioning of TM4 with Ta#40 there was a spark at ~43 kV that caused the Bias card to "fry". Dave Morris has been contacted and has said he will replace it tomorrow.

Entry  Wednesday, May 29, 2013, 12:07, chad fisher, South Hot-Cell, Development, , SiC#28 RFQ, RFQ Autopsy 

Major portions of the RFQ target have now been sucessfully dismantled. More minor dismantling with conclude this afternoon.

Entry  Friday, May 31, 2013, 11:19, Travis Cave, Spent Target Vault, Standard Operation, , SiC#28 (RFQ Target), Spent target move Vault_Storage_May_31_2013.pdf

Spent target SiC#28 (RFQ Target) has been moved from the south hot to the storage vault. The target was placed in pail #105 in spot 2C of  the spent target vault. The target had a field of 24.8mSv/hr at about a meter upon removal from the south hot cell. See attached PDF for the status of the vault. It currently only has six free spots left.

Entry  Tuesday, June 04, 2013, 15:34, Bevan Moss, Conditioning Station, Repair, , , Relay replaced 

ESC was called out again to inspect the chiller as it was showing the same problem as before. This time when started one fan came on (this is not what happened last time) but the fan controlled by the VFD did not. It was eventually traced to a relay that has been replaced. The system was tested as best it could without a load and appears to be working. It will be difficult to tell until a heat load is in place if the fix has solved everything. 

Entry  Wednesday, June 12, 2013, 10:39, Travis Cave, South Hot-Cell, Standard Operation, , , spent source tray removal 

The spent source tray for TM#3 has been removed from the south hot cell and well be placed in the the hot cell ante room. To sit till maintenance day to be moved over to the vault storage tunnels.

Entry  Thursday, June 13, 2013, 09:21, chad fisher, South Hot-Cell, Development, , , Warm Cell Mock-up 20130613_084421[1].jpg20130613_084426[1].jpg

the warm cell mock-up has been inserted into the warm cell and final preparation for the remote test are being made.

Entry  Thursday, June 20, 2013, 13:47, Travis Cave, Spent Target Vault, Standard Operation, , , Spent Target Assay Vault_Storage_June_20_2013.pdf

Ten targets have been assayed or had field measurements(they were too hot to ship but were assayed the last time an assay was done) done on them  over the past two days. Of those that have been assayed we have total of ten shippable targets. See the attached PDF for the latest details of the storage vault.

Entry  Thursday, June 27, 2013, 14:27, chad fisher, South Hot-Cell, Development, , , Polishing Cleaning tool - Water blocks 20130626_144941.jpg

The polishing/cleaning tool prototype is now finished and appers to work great.

Thanks to Dan and Maico for the great job making my design a reality.

Entry  Wednesday, July 03, 2013, 08:43, chad fisher, South Hot-Cell, Standard Operation, , , Ta#39 Transfered to spent target storage vault 
 
Entry  Wednesday, July 03, 2013, 08:44, chad fisher, Travis Cave, South Hot-Cell, Standard Operation, , , Ta#39 Transfered to spent target storage vault Vault_Storage_July_3_2013.pdf

Ta#39 has been transferred to spent target storage vault. Ta#39 was placed into pail #106 and placed into spot of 4C of the spent target vault. The pail measured 95.8mSv/hr upon removal from the hot cell. See attached PDF for details.

Entry  Friday, July 26, 2013, 11:06, David Wang, South Hot-Cell, Standard Operation, , , The steel shielding plug has been put on theSHC top in target hall 

to reduce the radioactive shining from  SHC Ta# 40 target.

Entry  Monday, July 29, 2013, 14:32, Travis Cave, Spent Target Vault, Standard Operation, , Ta#40, Spent target move Vault_Storage_July_29_2013.pdf

Spent target Ta#40 has been placed into storage. The target was placed in pail #107 and was put into slot 5A of the vault. It had a field of 224mSv/hr upon removal from the south hot cell. See attached PDF for more details.

Entry  Wednesday, July 31, 2013, 11:13, Travis Cave, Spent Target Vault, Standard Operation, , , Spent target move Vault_Storage_July_31_2013.pdfMini_Vault_Storage_July_31_2013.pdf

Five spent targets have been removed from the storage vault and placed into the mini storage. The target placed into the mini storage are UO#3, UC#'s  3,4,5 and SIC#23. See attached PDFs for vault details.

Entry  Wednesday, August 07, 2013, 06:47, maicodallavalle, Spent Target Vault, Maintenance, , , F-308 

All the F-308's have been torqued up  and the locks installed. Ready to be moved.

Entry  Wednesday, August 28, 2013, 14:17, Travis Cave, South Hot-Cell, Standard Operation, , UC#6, Spent target move Vault_Storage_August_28_2013.pdf

Spent target move, UC#6 has been moved from the south hot cell to the target storage. The target is in pail 108 and in slot 8C of the vault. See attached PDF for details.

Entry  Tuesday, September 24, 2013, 14:46, Bevan Moss, South Hot-Cell, Repair, , , Right manipulator repair 

 The right manipulator A-9885 Handle Cable Assembly has been repaired by Maico and myself. We repaired the manipulator following some verbal instructions from Chad on the modified repair strategy. This allows the repair to be completed without going into the hot cell. The instructions in the repair manual are very vague and can actually cause problems. For example it is best to pin the manipulator before completing any work. Other than that the work went smoothly with the exception that the counter weight hangs up on the manipulator occasionally and can cause the cable to come off of the pulley. Also it appears that the left manipulator has had the cable installed incorrectly as it rides on the housing of the wrist.