Entry  Thursday, June 27, 2013, 14:27, chad fisher, South Hot-Cell, Development, , , Polishing Cleaning tool - Water blocks 20130626_144941.jpg
The polishing/cleaning tool prototype is now finished and appers to work great.
Thanks to Dan and Maico for the great job making my design a reality.
Entry  Wednesday, July 03, 2013, 08:43, chad fisher, South Hot-Cell, Standard Operation, , , Ta#39 Transfered to spent target storage vault 
 
Entry  Wednesday, July 03, 2013, 08:44, chad fisher, Travis Cave, South Hot-Cell, Standard Operation, , , Ta#39 Transfered to spent target storage vault Vault_Storage_July_3_2013.pdf
Ta#39 has been transferred to spent target storage vault. Ta#39 was placed into pail #106 and placed into spot of 4C of the spent target vault. The pail
measured 95.8mSv/hr upon removal from the hot cell. See attached PDF for details.
Entry  Friday, July 26, 2013, 11:06, David Wang, South Hot-Cell, Standard Operation, , , The steel shielding plug has been put on theSHC top in target hall 
to reduce the radioactive shining from  SHC Ta# 40 target.
Entry  Monday, July 29, 2013, 14:32, Travis Cave, Spent Target Vault, Standard Operation, , Ta#40, Spent target move Vault_Storage_July_29_2013.pdf
Spent target Ta#40 has been placed into storage. The target was placed in pail #107 and was put into slot 5A of the vault. It had a field of 224mSv/hr
upon removal from the south hot cell. See attached PDF for more details.
Entry  Wednesday, July 31, 2013, 11:13, Travis Cave, Spent Target Vault, Standard Operation, , , Spent target move Vault_Storage_July_31_2013.pdfMini_Vault_Storage_July_31_2013.pdf
Five spent targets have been removed from the storage vault and placed into the mini storage. The target placed into the mini storage are UO#3, UC#'s 
3,4,5 and SIC#23. See attached PDFs for vault details.
Entry  Wednesday, August 07, 2013, 06:47, maicodallavalle, Spent Target Vault, Maintenance, , , F-308 
All the F-308's have been torqued up  and the locks installed. Ready to be moved.
Entry  Wednesday, August 28, 2013, 14:17, Travis Cave, South Hot-Cell, Standard Operation, , UC#6, Spent target move Vault_Storage_August_28_2013.pdf
Spent target move, UC#6 has been moved from the south hot cell to the target storage. The target is in pail 108 and in slot 8C of the vault. See attached
PDF for details.
Entry  Tuesday, September 24, 2013, 14:46, Bevan Moss, South Hot-Cell, Repair, , , Right manipulator repair 
 The right manipulator A-9885 Handle Cable Assembly has been repaired by Maico and myself. We repaired the manipulator following
some verbal instructions from Chad on the modified repair strategy. This allows the repair to be completed without going into the hot cell. The instructions
Entry  Tuesday, October 08, 2013, 13:11, Travis Cave, Spent Target Vault, Standard Operation, , SiC#29, Spent target move Vault_Storage_October_8_2013.pdf
SiC#29 has been moved to the spent target vault. The target was placed in Pail #109 and placed into slot 2B it was 24.7mS/hr upon removal from the south
hot cell. See attached PDF of the vault details.
Entry  Tuesday, October 08, 2013, 14:58, Anders Mjos, South Hot-Cell, Standard Operation, , SiC#29, Target to Heat Shield electrical short 
The SiC#29 CTL target has been taken apart with the help of Isaac and Chad. Electrical measurements were done between Target and Heat Shield as the target
was disassembled. Work was done on October 2nd, 4th, 7th and 8th.
The megger showed about 30kOhm at 50V with the following changes
Entry  Tuesday, October 15, 2013, 16:44, Grant Minor, Crane, Repair, , , Target Hall Crane - operational with temporary thermal sensor bypass ISAC_THall_Crane_elec_E5_1slash1_15Oct2013.pdf
E-mail correspondence on the Target Hall crane fault diagnosis between October 11th and 15th:
On 15/10/2013 3:34 PM, Grant Minor wrote:
Hello all,
Entry  Wednesday, October 16, 2013, 18:53, Grant Minor, ITE, Repair, , , ITE Harp 9 Removed & Blanked-Off - blocks NOT YET replaced 11x
The blocks above the pre-separator section of the ISAC beam lines     were removed today in the Target Hall by Bevan Moss and Chad Fisher     with Lynne
LeMessurier present from RPG.
Entry  Thursday, October 17, 2013, 17:16, Grant Minor, ITE, Repair, , , Pre-Separator-area (ITE Harp 9) Blocks Replaced 8x
The pre-separator-area blocks were replaced today by Bevan and Travis, with Grant present for photos and observation.
Photos are attached of each block replacement.
Some difficulty was encountered in replacing the "Layer #3" blocks (photo 9 attached).  An interference occurred between the outside
Entry  Friday, October 18, 2013, 10:17, Bevan Moss, ITW, Repair, , , Paddle Wheel 
 Yesterday I visually inspected the paddle wheel and noticed that it was spinning freely and constant. As the signal was intermittent replaced the
coil at the back of the wheel only. This does not require access to the high active water. With the coil replaced the signal looked strong. I asked operations
to keep and eye on it and advise if the problem has been resolved. I also discussed with David this morning and he informed me that this is the same procedure
Entry  Tuesday, October 22, 2013, 16:52, Bevan Moss, Conditioning Station, Repair, , , Canbus base card for BIAS  
 The base card in the canbus BIAS module was determined to be faulty. Dave Morris removed a card VECC to repair the conditioning station. 
Entry  Tuesday, October 22, 2013, 17:07, Bevan Moss, Conditioning Station, Standard Operation, , , services shut down 
 The turbo pump, roughing pump, have been turned off and the valves for venting opened. The cooling package has also been turned off.
Entry  Thursday, October 24, 2013, 11:31, Travis Cave, Spent Target Vault, Standard Operation, , UC#7, Spent target move Vault_Storage_October_24_2013.pdf
UC #7 has been moved from the south hot cell to the spent target vault, it was placed in pail #110 and put in slot 8B of the vault, it was 22.6mSv/hr
upon removal from the hot cell. See attached PDF for vault details.
Entry  Tuesday, November 12, 2013, 14:33, Bevan Moss, Conditioning Station, Repair, , , Cooling manifold returned 
 The cooling manifold for the conditioning station high power water cooled lines has been returned. The cooling package can once again be operated
Entry  Monday, November 18, 2013, 16:44, Bevan Moss, Conditioning Station, Standard Operation, , , Testing of cooling package 
 I have tested all of the compressors for TCS. All are operational and cycled as they should. 