ID |
Date |
Author |
Category |
Type |
Module |
Target/Number |
Subject |
2690
|
Monday, September 23, 2024, 16:06 |
Aaron Tam | South Hot-Cell | Repair | TM3 | | Insulator Addition to Water block |
September 23, 2024 - C. Fisher
- Containment box removed
- Insulator installed
- New window line VCR seals installed
- Dropped bolt from TiC#8 removed
- Containment box reinstalled
September 23, 2024 - A. Tam
- Containment box cover reinstalled
Photos attached |
1842
|
Wednesday, December 19, 2018, 14:41 |
Anders Mjos | Conditioning Station | Standard Operation | | No target | Installed Shield Block on TCS |
Frank and Anders installed lid on TCS and started vacuum system yesterday. To run over the Holidays. Retrieved dose badge from operational storage area. Measured field to be ~ 10 mSv/h at ~9am. Beam went off about 8:30am. |
536
|
Wednesday, November 06, 2013, 10:41 |
David Wang | South Hot-Cell | Repair | TM2 | | Installed 2 turbopumps on TM2 |
Bevan and I installed 2 turbo pumps on TM2. The o- ring flanges on TM2 had been cleaned before the installation. |
1634
|
Thursday, October 05, 2017, 11:04 |
Anders Mjos | ITW | Maintenance | | | Installation of new valve for module move ventilation |
David installed the new ball valve and connections for the SAS project module move ventilation. SASP0482. Drawing reference ISK5029B. |
1483
|
Thursday, April 06, 2017, 15:16 |
Anders Mjos | Conditioning Station | Maintenance | | | Installation of new break out box to accommodate both ITM:MP2 and TCS:MP1 |
Installation by Marshall. Dave M from controls adjusted circuitry to get TCS:MP1 to start.
Work is being done in preparation for the Module Move Ventilation SAS project |
1781
|
Wednesday, September 12, 2018, 15:30 |
Isaac Earle | North Hot-Cell | Development | | | Installation of NHC operator-level lighting completed |
Installation of of operator-level lighting in the NHC was completed today according to drawing IRH1801. 2" x 2" Panduit was mounted to the wall on aluminum brackets to support the power cables. These lights can be replaced remotely by unplugging the power cords using the manipulators, lifting the cable out of the Panduit with a hooked pole tool through the manipulator slave end removal roof hatch, lifting the light fixture off the support bracket with the pole tool, then installing a new fixture in the opposite order. This RH procedure will be tested at a later date as part of NHC commissioning.
|
1663
|
Wednesday, November 15, 2017, 08:55 |
David Wang | Conditioning Station | Standard Operation | | | Install shield plug onto TCS and pumping down TCS. |
Shielding plug is installed onto TCS. TCS is being pumped down to keep it under vacuum for the rest of the year. |
1102
|
Wednesday, October 14, 2015, 14:49 |
David Wang | South Hot-Cell | Standard Operation | TM2 | | Install new high current cables to TM2 |
I installed a set of new high current cables for TM2 Febiad run. The top of TM2 is configured to Febiad mode. See attachments |
2532
|
Thursday, January 25, 2024, 07:31 |
David Wang | Crane | Standard Operation | | | Inspection oftareg hall crane below hook attachment pins and plates ITA6550-01 |
Tom Kauss inspected target hall crane below hook attachment pins and plates ITA6550-01 yesterday. He certified the use of these pins and plates for year 2024. The inspection of these pins and plates was in Target hall crane annual check list. It was issued as a calibration index by Isaac Earle in 2022-Feb-08. After inspection, The inspection tag was issued and attached to pin. Tom has an inspection record on this job. |
2531
|
Thursday, January 25, 2024, 07:27 |
David Wang | Crane | Standard Operation | | | Inspection of target module lifting frames ITA0494-1997-01 and ITA0494-1997-02 |
Tom Gauss inspected two target module lifting frames ITA0494-1997-01 and ITA0494-1997-02 yesterday. He certified the use of these two frames for 2024. Inspection tags have been issued and attached to frames. He has inspection record on them. |
2413
|
Friday, January 27, 2023, 07:18 |
David Wang | Crane | Standard Operation | | | Inspection of target module lifing frame ITA0494-1997-01 and ITA0494-1997-02 |
Tom Gauss inspected two target module lifting frames ITA0494-1997-01 and ITA0494-1997-02 yesterday. He certified the use of these two frames for 2023. Inspection tags have been issued and attached to frames. He has inspection record on them. |
53
|
Wednesday, November 16, 2011, 07:46 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | TaC#1 | Inspection of TaC#1 |
Inspection of TaC#1 showed that the oven was indeed broken on the A+ (left oven leg) side of the central block.
See the following for pictures.
https://documents.triumf.ca/docushare/dsweb/View/Collection-7438 |
2622
|
Monday, June 24, 2024, 14:37 |
Carla Babcock | South Hot-Cell | Development | TM3 | UCx#44 | Inspection of TM3 and UCx#44 after no-protons run |
TM3 and UCx#44 ran in ITE but issues with the cyclotron prevented proton beam delivery. Nonetheless, the target was heated and provided stable beam to TITAN as well as for tuning and some tests.
Results of inspection of TM3 module after run:
The module looked pretty good. There were no marks on the polished surface of the containment box, next to the water blocks, that were visible. But we didn't remove the box, only looked with the camera and it was visible by turning the module. So some things may have been hidden. There were some black marks on the door, near the bolts that hold in the handle (see attachment). This seems a very unlikely spot for sparking as the fields should be considerably lower than at the target handles, lower down. Maybe the spots are from oil left on the door that had a chemical reaction? There is one very faint matching spot on the top of the copper trident connector, but it doesn't look much like a spark mark. The other two marks have no corresponding mark on the source tray. There were no marks on the ground electrode, or anywhere else on the source tray. There was a scuff on one of the trapezoidal insulators, but it could have happened during installation.
Results of inspection of the target after run:
The FEBIAD target developed the same cathode short we have seen on almost every FEBIAD we run online - a high resistance short from cathode to HVC that prevents voltage on the cathode. This time the short remained after cooling the target, and David measured 208kOhms with the ohmmeter on the module top (11kOhms with the megger). We used a multimeter in the hot cell to test after the target had been dismounted and we found no short. So it must be related to either the position of the target (upright vs face down) or time (a conductive trace on an insulator oxidizes and becomes non-conductive again) or some pressure/shaking during the de-installation.
There weren't many marks on the target - a faint mark near where the faint mark on the copper trident was observed, some marks on the EE which had no counterparts on the ground electrode. See pictures. |
2414
|
Friday, January 27, 2023, 07:25 |
David Wang | Crane | Standard Operation | | | Inspection of TH crane below hook attachment pins and plates ITA6550-01 |
Tom Kauss inspected target hall crane below hook attachment pins and plates ITA6550-01 yesterday. He certified the use of these pins and plates. The inspection of these pins and plates was in Target hall crane annual check list. It was issued as a calibration index by Isaac Earle in 2022-Feb-08. After inspection, The inspection tag was issued and attached to pin. Tom has an inspection record on this job |
1622
|
Thursday, September 21, 2017, 16:26 |
Anders Mjos | South Hot-Cell | Standard Operation | TM2 | | Inspection of Source Tray |
Chad and Anders inspected the Source Tray today using the camera in the hot cell. A dark spot was observed on one of the four insulators separating the Extraction Electrode from the Ground Electrode. This could potentially influence the high leakage current. Some discolored areas were also observed in the Service Tray, but these was present when the module was built. See attachment for details. |
443
|
Wednesday, September 04, 2013, 19:01 |
Grant Minor | South Hot-Cell | Repair | TM3 | | Inspection / Ante Room Leak Check Results on TM3 Heat Shield lines (3 Sept 2013) |
Yesterday, Grant entered the Ante Room with David Wang to visually inspect the two sets of failed c-seals from the Heat Shield circuit, to remove the second set from the Heat Shield water blocks, and to leak check the heat shield circuit with o-rings and a water-block-to-leak-detector fitting.
Some photos of the inspected seals are in the attached design review presentation. Some unusual marks were observed on both sets of failed seals.
The heat shield lines and water block assembly leak checked successfully to the bottom of the leak rate range ("UNDER" ~1x10-9 atm cc / sec on the Varian 979) with a great flood of helium on all joints with no response anywhere. |
2294
|
Wednesday, January 19, 2022, 13:26 |
David Wang | Crane | Standard Operation | | | Inpection of Target module lifting frames ITA0494-1997-01 and ITA0494-1997-02. |
Tom Gauss inspected two target module lifting frames ITA0494-1997-01 and ITA0494-1997-02.. He certified the use of these two frames. Inspection tags have been issued and attached to frames. He has inspection record on them. See attachments. |
1562
|
Thursday, June 22, 2017, 11:10 |
chad fisher | South Hot-Cell | Maintenance | | | In cell airline |
The in cell airline has preemptively been replaced. The hose was, as far as I know the original. |
718
|
Monday, July 28, 2014, 17:26 |
Ron Kuramoto | ITW | Repair | | | ITW:IV5 Air leak repair |
Air leak was found at the Solenoid control valve located in the Pre-Separator & DB0 room. The gasket between the solenoid body and its manifold block was broken, see attached photos. The gasket and solenoid body were replaced. Air was turned back on to IV5 (B/L gate valve) with no apparent air leaks. The gate valve was actuated open & closed from the control room seeing both limits successfully.
Repair was done by Dimo Y. who received 0.01 mSv, and assisted by Anthony I. & Ron K. who both received zero dose.
Rad fields measured by RPG were; 1300 uSv/hr above B/L and 350 uSv/hr @ the Solenoid valves at knee height.
|
1821
|
Wednesday, November 14, 2018, 16:10 |
Anders Mjos | ITW | Repair | TM2 | UC#25 | ITW:FC5 safety signal troubleshooting |
Measured resistance on safety limit switches for FC5 on Exit Module 2. Determined that the in connected signal did not work (shows not connected irregardless of FC position). Confirmed proper operation of the OUT limit. See attachment for details. The Harp 5 x and y signal connectors were checked and reconnected. |